Draw 14 on a mixed-use construction loan: four exceptions, two signatures
A mixed-use project, 186 units over 14,200 sq ft of retail, sends Draw 14 for $4,384,970. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Start of the week
What needs the administrator, on one screen
Construction loan administratorThe administrator runs 23 active construction loans, $412.6M committed. The home screen shows 8 draws in the queue for $12.4M, the oldest waiting 10 days on 3 missing waivers, and 7 open exceptions, including a lien affidavit and an out-of-balance loan the agents found on two other projects.
Agents at work: the title date-down checker found a $48,200 lien affidavit, and the borrower was asked to bond around it.
- 02The queue
Draws ranked by risk and days waiting
Construction loan administratorEach draw shows the amount requested, when it arrived, its documents, inspection, waivers, exceptions and stage. Draw 14 has 51 of 51 documents in and 27 of 28 waivers, and is ready for review.
The contractor's clock starts when the package is complete.
- 03One click
Start review: six agents read 51 documents
The agentsThe pay application reader checks the G702 and G703: 20 lines, contract sum to date $50,048,900, the G703 ties to G702 line 4, retainage 10%. The invoice and waiver matcher ties 13 invoices and 27 waivers. The inspection reconciler compares the inspector's report, the budget and balance checker runs the in-balance tests, and the title date-down checker reads the title search since the last draw.
Each step is shown as it runs, with what it found.
- 041 min 24 s later
Four exceptions, each with its proof
Funding recommenderTwenty of 20 lines tied to their proof. Four exceptions, $782,750 held: framing billed ahead of the inspection, the electrical sub's missing unconditional waiver for Draw 13, change order 8 not yet approved by the bank, and the plumbing sub's conditional waiver $20,000 short. Each links to the page it came from. Recommended: $3,602,220.
Recommended $3,602,220 by the funding recommender; needs a second signature.
- 05The framing line
Billed 88%, inspected 81%: the gap is held
Inspection reconcilerThe G703 bills the framing sub's wood framing line to 88% ($6,116,000 of $6,950,000). The inspector certifies 81%: on Level 5 the east wing walls are framed but not sheathed, and the roof trusses are on site but not set. The $486,500 billed ahead of the site is held, $437,850 net of retainage, until a later inspection certifies it. The other lines are within the 3-point tolerance, and the 212 stored windows are counted on site.
The inspection reconciler never changes a percentage the inspector certified.
- 06Waivers
A missing waiver and a short one
Invoice and waiver matcherEach waiver is read for its type, amount, through date, signer and Texas statutory form. The electrical sub's unconditional waiver for the $241,650 paid in Draw 13 has not arrived, so its $257,760 due this period, net of retainage, is held. The plumbing sub's conditional waiver releases $176,605 against $196,605 due, so $20,000 is held. One click asks the contractor for both.
Rule: no new money to a party until its unconditional waiver for the last payment is in.
- 07Budget
Still in balance, with the reserve to watch
Budget and balance checkerAfter the draw the undisbursed loan of $28,452,720 covers the cost to complete. Contingency after change order 8 would be $1,663,500, 8.2% of the work left and above the 5% minimum. General conditions are 3.3 points ahead of the project, inside the 10-point limit. To watch: $1,157,600 left in the interest reserve against $1,094,000 of projected interest.
- 08The recommendation
From the request to the amount to fund
Funding recommenderHard costs of $3,992,730 after retainage plus $392,240 of soft costs make the $4,384,970 request. Four holds come off, each with the document that releases it, leaving $3,602,220 to fund through the title and escrow company, which issues the ALTA 33-06 date-down for the advance. The borrower notice is sent only once the administrator signs.
- 09One more hold
A $25,000 hold, asked for in plain words
Construction loan administratorThe inspector's report also notes three storefront units in retail bay C installed with cracked panes, at about $25,000 to replace. The administrator asks the assistant to hold it. A fifth holdback appears, released when the inspector confirms the units are replaced: fund $3,577,220, hold $807,750.
Activity: the funding recommender added a $25,000 holdback for cracked storefront glass, retail bay C.
- 10Signed, funded in a day
Above the administrator's limit, the officer co-signs
Administrator and lending officerThe administrator approves with the meaning of the signature: Reviewed, fund as recommended. Above the $2,500,000 limit, the draw goes to the senior construction lending officer for a second signature, and then $3,577,220 goes to the title company for disbursement, one business day after the package was complete.
The signature, the time, the amount and each holdback are written to the audit trail and cannot be changed.