- Before
- Gathers the proof for each draw by hand, in spreadsheets and email, while the contractor calls for cash.
- Now
- Opens a draw already checked line by line, with four exceptions and their sources, and spends the time on the decision.
Draw 14 on a mixed-use construction loan, with four exceptions and two signatures
A mixed-use project has 186 units above 14,200 sq ft of retail. Its contractor sends Draw 14, asking for $4,384,970. Here is what happens next in the working solution, screen by screen.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Start of the week
Everything waiting for the administrator, on one screen
Construction loan administratorThe administrator runs 23 active construction loans, with $412.6M committed. The home screen shows 8 draws in the queue, worth $12.4M. The oldest has waited 10 days on 3 missing waivers. There are also 7 open exceptions, problems that hold up payment. The agents found two of them on other projects. One is a lien affidavit, and the other is a loan out of balance.
Agents at work: the title date-down checker found a $48,200 lien affidavit, and the borrower was asked to bond around it.
- 02The queue
Draws ranked by risk and days waiting
Construction loan administratorEach draw shows the amount asked for, when it arrived and its stage. It also shows its documents, inspection, waivers and exceptions. Draw 14 has 51 of 51 documents in and 27 of 28 waivers, so it is ready for review.
The contractor's clock starts when the package is complete.
- 03One click
After Start review, six agents read the 51 documents
The agentsFirst, the pay application reader checks the G702 and G703. It finds 20 lines and a contract sum to date of $50,048,900. The G703 ties to G702 line 4. Retainage, the share of each payment kept back until the job is done, is 10%. Then the invoice and waiver matcher ties 13 invoices and 27 waivers. The inspection reconciler compares the inspector's report with what was billed. Next, the budget and balance checker runs the in-balance tests. Last, the title date-down checker reads the title search since the last draw.
Each step is shown as it runs, with what it found.
- 041 min 24 s later
Four exceptions, each with its proof
Funding recommenderAll 20 lines are tied to their proof. There are four exceptions, with $782,750 held. Framing is billed ahead of the inspection. The electrical sub's unconditional waiver for Draw 13 is missing. Change order 8 is not yet approved by the bank. The plumbing sub's conditional waiver is $20,000 short. Each exception links to the page it came from. The recommended amount is $3,602,220.
Recommended $3,602,220 by the funding recommender. Needs a second signature.
- 05The framing line
Framing billed at 88% and inspected at 81%, so the gap is held
Inspection reconcilerThe G703 bills the framing sub's wood framing line to 88%, or $6,116,000 of $6,950,000. The inspector certifies 81%. On Level 5, the east wing walls are framed but not sheathed. The roof trusses are on site but not set. So the $486,500 billed ahead of the work is held, or $437,850 after retainage. It stays held until a later inspection certifies it. The other lines are within the 3-point tolerance, and the 212 stored windows are counted on site.
The inspection reconciler never changes a percentage the inspector certified.
- 06Waivers
A missing waiver and a short one
Invoice and waiver matcherEach waiver is read for its type, amount, through date and signer, and whether it is on the Texas statutory form. The electrical sub's unconditional waiver for the $241,650 paid in Draw 13 has not arrived. So the $257,760 due to it this period, after retainage, is held. The plumbing sub's conditional waiver releases $176,605, but $196,605 is due, so $20,000 is held. One click asks the contractor for both.
Rule: no new money to a party until its unconditional waiver for the last payment is in.
- 07Budget
Still in balance, with the interest reserve to watch
Budget and balance checkerAfter this draw, the loan money not yet paid out is $28,452,720. It still covers the cost to finish. Contingency, the budget kept for surprises, would be $1,663,500 after change order 8. That is 8.2% of the work left, above the 5% minimum. General conditions, the contractor's site overhead, are 3.3 points ahead of the project. That is inside the 10-point limit. One thing to watch is the interest reserve, the money set aside to pay interest during building. It has $1,157,600 left against $1,094,000 of projected interest.
- 08The recommendation
From the request to the amount to fund
Funding recommenderThe $4,384,970 request is $3,992,730 of hard costs after retainage plus $392,240 of soft costs. Four holds come off, each with the document that releases it. That leaves $3,602,220 to fund through the title and escrow company, which issues the ALTA 33-06 date-down for the advance. The borrower notice goes out only once the administrator signs.
- 09One more hold
A $25,000 hold, asked for in plain words
Construction loan administratorThe inspector's report also notes three storefront units in retail bay C with cracked panes. They will cost about $25,000 to replace. The administrator asks the assistant to hold that amount. A fifth holdback appears, released when the inspector confirms the units are replaced. The draw now funds $3,577,220 and holds $807,750.
Activity: the funding recommender added a $25,000 holdback for cracked storefront glass in retail bay C.
- 10Signed, funded in a day
Above the administrator's limit, the officer also signs
Administrator and lending officerThe administrator approves, and the meaning of the signature is recorded as “Reviewed, fund as recommended”. Because the draw is above the $2,500,000 limit, it goes to the senior construction lending officer for a second signature. Then $3,577,220 goes to the title company to pay out, one business day after the package was complete.
The signature, the time, the amount and each holdback are written to the audit trail and cannot be changed.