- Before
- Learns of an overrun only when a draw shows it and the contingency is gone. Retypes site reports, schedules and change-order logs into a spreadsheet for each loan.
- Now
- Starts the week with loans ranked by how far each interest reserve falls short of its finish. Each has its S-curve, forecast, sources and recommended actions.
An apartment loan that passed its last draw test and is forecast to run short
A 248-unit apartment project passed its balancing test at Draw 16. Five documents have arrived since. Here is what happens on a Monday morning in the working solution, screen by screen.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Monday morning
Thirty-one loans, ranked by how far the reserve falls short
CRE portfolio managerThe bank has 31 construction loans. The S-curve screen ranks them by how far each interest reserve falls short of the project's finish, and the apartment loan is first. Its curve has bent below plan. It is 61.4% built against a plan of 68.0%, so 6.6 points and $3.34M of work is not in place. By trade, drywall on Levels 3 to 5 ($1.50M) and the main switchgear ($0.74M) are furthest behind.
The agents' forecast: “Interest reserve hits $0 · 4 months before the finish at 90% leased.”
- 02The new forecast
A new forecast from the five new documents
The six agentsFive documents have landed since Draw 16. They are site report 17, schedule update rev 9, pending change orders 11 to 13, the general contractor's letter and the leasing agent's report. In 1 min 12 s the agents read each one. They price the budget again and project interest to 90% occupancy. Then they run eight tests and score the loan again, from 55 to 84, showing what each step found.
“Balance and covenant tester ran 8 tests · In balance today · forecast out of balance $613,000 at completion.”
- 03To the finish
The money running down, on the same timeline
Interest reserve forecasterUnder the S-curve, two lines show the money left. The interest reserve has $1,835,000 and the contingency has $1,026,000. Each line is solid up to today and dotted to the finish. The reserve hits $0 four months before the building is 90% leased. Those months are shaded: $210,000 of interest with nothing to pay it. The contingency runs out sooner still, $403,000 over once the delay claim is counted.
The forecast reads “short $613,000 at the finish”, while today's test still passes.
- 04Trying a scenario
What moves the date the money runs out
CRE portfolio managerThe portfolio manager sets leasing to 18 a month, and the dotted line redraws. The reserve now runs dry a month sooner, seven months before 90% leased, and the loan is short $793,000. Two more buttons move the run-out date the same way. One is completion (rev 9, +30 or +60 days). The other is Term SOFR, the benchmark rate the loan's interest is based on (3.60% forward or +50 bp). Setting leasing back restores the forecast, and the published numbers stay the agents'.
- 05Line by line
Cost to complete, and why the draw test cannot see it
Change order and cost watcherLeft in the loan is $25,713,000, equal to the budget remaining, so the loan is in balance today. The forecast cost to complete is $26,326,000. A bridge chart shows why. Pending change orders add $1,148K, and the contingency absorbs $1,026K of that. The delay claim adds $281K, and interest to 90% occupied adds $210K. Pending change order 11, the switchgear and copper feeders at $612,000, follows a supplier letter citing metals tariffs.
“Today’s draw test compares the left-in-loan bar with the approved budget only. The four steps in between are not in it yet.”
- 06The critical path
The original schedule against rev 9, milestone by milestone
Site and schedule readerSubstantial completion moves 70 days later. That leaves 96 days of margin before the outside date in §5.2 of the loan agreement. The critical path, the chain of tasks that sets the finish date, runs through the switchgear delivery. After it come permanent power, the elevators and the temporary certificate of occupancy. The consultant's percentages stay as the consultant wrote them, and each date cites its page.
The consultant, in site report 17: “Rev 9’s completion date is achievable only if the switchgear date holds; it shows no float on that path.”
- 07Each assumption shown
The reserve, month by month to 90% occupied
Interest reserve forecasterThe calculator shows each assumption. Completion is on the rev 9 date. At completion 46 units are leased, against a plan of 72. Leasing runs at 22 a month, against a plan of 26. The rate is Term SOFR 3.60% plus 2.85%, or 6.45%. Net operating income starts the month after completion. Here, 90% occupied means 223 of 248 units.
“The forecaster uses 22 a month: the three comparable buildings average 22.0, and the closing plan assumed 26.”
- 08Drafted
Four actions and a balancing notice, each figure sourced
Risk and action drafterThe drafter recommends four actions. First, a balancing notice to the borrower for $613,000 under §7.3, asking it to pay in the shortfall. Second, a recovery schedule from the general contractor, with the $281,000 claim held. Third, the watch list, with the risk rating moving from 4 to 5 (Special Mention). Fourth, a date for the extension test. The notice splits the shortfall into three parts and says Draw 17 will be funded as usual meanwhile.
“drafted by the assistant · sent only when you sign”
- 09Signed
The portfolio manager approves, and the meaning is recorded
CRE portfolio managerThe portfolio manager reviews the four actions and signs. The signature records what it means: “I have reviewed the forecast and its sources and approve these actions”. The rating change goes to the chief credit officer. Nothing reaches the borrower until the lending officer sends it.
- 1024 days before Draw 17
The rating approved, ten months before the reserve runs dry
Chief credit officerThe chief credit officer approves risk rating 5 (Special Mention), and the loan goes on the watch list. That is 24 days before Draw 17 and 10 months before the reserve runs dry. This week's monthly portfolio report for the credit committee picks up the new rating and the signed notice.