- Before
- Builds each pack by hand from the job plan library, the drawing store, GIS, the permit portal, the one-call centre and stores. “I spend a day building a pack and still find out on the morning that the permit ran out.”
- Now
- Opens a pack the agents built overnight, sees every dated item against the job day, fixes only what is flagged and releases it.
One ring main unit replacement, from approved request to the crew's tablet
Lumina Utilities has to replace RMU-0417, an 11 kV ring main unit installed in 1987 with a condition score of 2 out of 10, at Kilnfield Lane on feeder KF-04. Crew 7 is booked for Tuesday 27 October, 07:00–15:00, with 212 customers off supply from 08:00 to 14:00 — two of them on the priority services list. Here is what happens, screen by screen, in the working solution.
- 01Approved for planning
Every request arrives matched to a standard job plan
Job plan matcherMarcus Hale approved work request WR-77104 for planning on 12 October at 16:40. On the Requests screen, each request waiting for a pack — fault follow-ups, asset inspections, new connections, water network and treatment jobs — already shows its best standard job plan and a match score. For the LV cable fault at Ellery Close it is SJP-LVJ-01 v3, LV straight joint in the footway, at 97%, with the carriageway joint at 71% as the runner-up.
“Match from the asset class, the defect in the request and the last three jobs on this asset · Job plan matcher”
- 0206:12
Seven agents build the pack at 06:12
Seven agentsFrom WR-77104 the agents assemble the pack in 6 min 40 s, and the run log shows each step as it happens. The job plan matcher takes SJP-RMU-11 v4 at 96%. The drawings gatherer collects five sheets. The permit and consent checker finds four permits and notices. The kitting agent reserves 17 of 18 lines. The isolation planner drafts SP-KF04-118 and sends it to the control room. Then the date checker holds nine dated items against Tue 27 Oct.
“Date checker · Held 9 dated items against Tue 27 Oct — Permit RO-26-3317 ends Sun 25 Oct — 2 days short · TJ-185 order arrives 30 Oct”
- 0309:05
Six tabs and a date line, tested against the job day
Nadia Ferreira · Work planner, Distribution NorthNadia opens the pack to six tabs — Scope, Drawings, Permits, Materials, Method statement, Isolation plan — each marked ready, at risk, missing or waiting. Under them the date line runs from today to beyond the job, with the job day as a vertical rule. Road opening permit RO-26-3317 is valid 12–25 Oct, so its bar stops two days short. Because her rule extends an existing permit automatically, an extension to Fri 30 Oct already went to Calder Bay Highways at 06:14; their decision is due Tue 20 Oct.
9 of 12 ready · “3 to resolve before the crew sets off”
- 04Scope tab
14 steps, three hold points, four authorisations checked
Job plan matcherThe scope is copied from SJP-RMU-11 v4: 14 steps and 26 crew hours, from the pre-job briefing to redlining the as-built and logging the SF₆. Three hold points are marked — switching confirmation, proving dead and earthing, and tests signed before restoration. Below them, every crew member's authorisation is checked for the job day: Tomás Reyes as authorised person for 11 kV switching and earthing, Liam Doyle for HV jointing to 15 Nov 2026.
“Copied from the job plan; hold points cannot be removed”
- 05Materials tab
Three joint kits short — and three at another depot
Kitting agentThe ring main unit, a Norvale NX3 from Westmere, is reserved and on site Mon 26 Oct. But Calder North has no TJ-185 transition joint kits, and purchase order PO-88412 delivers on Fri 30 Oct, three days after the job. Harbour depot holds four with none reserved. The kitting agent proposes moving three on the Wednesday stores run; it cannot do it alone. Nadia approves, and transfer TR-2291 arrives Wed 21 Oct.
“Joint kits TJ-185: none at Calder North; the order arrives three days after the job”
- 06Method statement
The site's hazards, written into the method
Method statement writerThe method statement comes in the Lumina template, nine sections, as a draft for Tomás to review. The writer adds what only the site shows: the joint bay is 14 m from the Kilnfield Primary School entrance, so no vehicle moves during drop-off and pick-up and a banksman stands at the gate. A Calder Gas 125 mm PE main runs at 0.6 m, 1.1 m from the bay, so the crew hand-digs within 0.5 m.
“Hold points are copied from the job plan and cannot be removed.”
- 07With the control room
Grace approves the switching programme, not the paperwork
Grace Lindqvist · Control-room authorised engineerThe isolation planner drafted SP-KF04-118 from the network model: close the normal open point RMU-0419, open RMU-0418 and RMU-0416 towards the work, lock off and tag both points of isolation, prove dead and apply earths E1–E3. Grace sees the back-feed already checked — KF-05 carries 186 A of 400 A — and both priority customers listed for calls by 22 Oct. She approves, or returns it with comments.
The isolation planner never issues a switching programme — only the control-room authorised engineer approves.
- 08Approved · 09:12
Who goes off supply, and who is called first
Isolation plannerThe isolation plan shows the feeder during the work and the 212 customers off at TX-0417: 197 homes and 15 businesses. Kilnfield Primary stays on, fed from TX-0420. Two priority services customers are listed by address — a home oxygen concentrator and home dialysis — with a call booked by 22 Oct and a generator offered. The planned interruption letter to all 212 posts Mon 19 Oct, five working days ahead.
“Approved by Grace Lindqvist · Control-room authorised engineer · 13 Oct, 09:12 · SP-KF04-118 issue 1”
- 09Release
Released to scheduling with one condition, watched every night
Nadia Ferreira · Work plannerEleven of 12 checks are ready. The permit extension is still open, so Nadia releases WO-48213 to Owen Mercer for Tue 27 Oct with one condition: RO-26-3317 extended to 30 Oct by Tue 20 Oct. If Calder Bay Highways refuses it, the date checker warns Nadia and Owen the same night, a week before the crew sets off.
“If it is refused — the date checker warns you and Owen the same night”
- 10Mon 26 Oct, 17:30
The crew lead gets the whole pack on his tablet
Tomás Reyes · Crew lead, Crew 7Tomás receives the crew pack the evening before: the cover sheet, five briefing points — the school entrance, the gas main, the three hold points, the 410 kg unit lifted by HIAB only, the priority customers already called — and the six sections behind them. He asks whether the HIAB is booked for 06:30 or 07:00 and gets the answer from the plant hire booking. Then he accepts the pack.
“06:30 at Calder North, driver Pete Lowry, HR-5521 · answered from the plant hire booking.”