- Before
- Starts at 07:00 with 700+ tickets on the one-call feed and a 2-working-day clock on each. Sends people to anything uncertain, since nobody can look at 700 maps.
- Now
- Opens a map where the clears have already gone back with their reasons. Decides only the tickets near a cable or main, with the depth section, the score and the drafted precautions in front of them.
One morning's tickets screened, and a standby put on the riskiest dig
A depot on a Tuesday morning. At 16:18 the day before, a civil contractor filed a ticket to renew a storm drain along one road with a tracked 21 t excavator. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
704 tickets on the board, 38 new since yesterday
Damage prevention coordinatorThe coordinator owns the response to each ticket in the utility's area. The dig map opens on the depot. It shows 704 tickets on the board and 89 replies due today, none late. Of these, 7 need a standby, 36 carry raised risk, 161 need a locate and 500 are clear. Thirty-eight new tickets have come in from the one-call center since 16:05 yesterday. They wait to be screened over the buried cables and mains, drawn in the colors field crews know.
With 700 maps to read by hand, any doubt becomes a truck roll.
- 0207:42 · one click
Five agents screen the 38, in order
Ticket reader, Asset overlay and Risk scorerThe coordinator presses Screen 38 new tickets. The ticket reader reads the work, method, depth and extent from each description. Four gave no depth, so the method's worst case is used. The asset overlay draws 38 dig areas with a 3 m buffer and finds 61 of the utility's assets inside. It holds back one area where as-builts, the drawings of what was actually built, are not yet posted. The risk scorer scores 37: 27 clear, 7 locate, 2 raised risk and 1 standby over a 600 mm trunk main.
Clear responder: “sent 27 no-conflict replies · code 10 to the one-call center and an email to each excavator · 07:43”
- 0307:43
The storm drain dig turns red: standby required
Risk scorerThe last dig area draws along the road and crosses the 132 kV cable route. The contractor plans to dig to 1.8 m with a tracked 21 t excavator. According to the as-laid survey, the 132 kV circuit lies at 1.1 m. So the bucket would go 0.7 m below the cable. The score is 94 of 100. On the right, the depth section draws the trench to its depth. Each asset sits at its recorded depth, with its 0.5 m safe margin.
“Rule: a mechanical excavator within 3 m of a cable of 33 kV or more always gets a standby.”
- 04What if
Switch to vacuum excavation, and the score falls to 69
Damage prevention coordinatorThe coordinator tries the other methods on the depth section. With vacuum excavation to the same 1.8 m, the method adds 6 points instead of 22. The safe-margin points fall from 18 to 9. So the score falls to 69, and the outcome becomes raised risk. That means the locator marks out, then meets the excavator on site before work starts. The standby rule for machine digs no longer applies. This is a what-if only, and the ticket still says mechanical excavator.
“What-if: the ticket says mechanical excavator to 1.8 m (score 94). Not saved.”
- 05The ticket
Each value read from the ticket, each asset inside the dig
Ticket reader and Asset overlayThe ticket appears as received. The start, location, depth and method are highlighted where the ticket reader found them. Six assets lie inside the dig area and its 3 m buffer. The 132 kV circuit crosses at chainage 76 m, the distance along the dig, with its protection signaling fiber at 78 m. A 150 mm main lies at 104 m and an 11 kV feeder at 120 m. There are six 25 mm service pipes. A 450 mm ductile iron trunk main runs 2.1 m beside the trench. Its depth, 1.4 m ±0.4, is estimated from an old drawing.
Why 94: 132 kV cable +35 · mechanical excavator +22 · dig reaches the 0.5 m safe margin +18. Other points: 2 crossings +8 · excavator history +7 · depth uncertain +4
- 06Who is digging
The contractor carries +7 for its strike history
Risk scorerThe excavator history adds points for strikes in the last 24 months. One strike adds 4, two add 7, and three or more add 10. The contractor has 412 tickets in 12 months and 2 strikes. One was an 11 kV cable, hit by a mini excavator that did not keep clearance. The other was a 100 mm main. The coordinator can send a safe-dig briefing before Thursday's job.
“Strikes in the last 24 months add to each new ticket's risk score.”
- 07Decide
The precautions, drafted and confirmed
Damage prevention coordinatorThe locator dispatcher has drafted what the dig needs. An HV-qualified (high-voltage) locator marks out the next morning, before the reply is due. A pre-dig meeting is set on site at 07:00 on the dig day, with the contractor's site foreman. From 07:00 to 15:30, a standby crew stays on site. Trial holes are dug by hand at chainage 76 m and 120 m. Safe-dig instructions go to the contractor. The coordinator signs the plan, and it goes to the cable engineer.
“No machine within 0.5 m of the indicated line until the asset is exposed.”
- 08Approved
The cable engineer approves, and the reply goes back
Third-party works engineer, transmission cablesAny work within 3 m of a 33 kV or 132 kV cable needs this engineer's approval. Once it is approved, code 30 goes to the one-call center. It means marked, with a site meeting and a standby. The contractor gets the safe-dig instructions, with asset plans, depths, the 0.5 m margin and the standby contact.
“Approved by the cable engineer · code 30 sent to the one-call center”
- 09The field day
Locators by qualification, standbys against the dig start
Locator dispatcherThe locator board shows 8 locators and 113 mark-outs in route order, with travel time from each depot. HV work goes only to HV-qualified locators. One of them carries 16 jobs and is 79% booked. Standby crews are booked against each dig start. A two-person crew covers the storm drain dig on Thursday, and the trunk mains crews cover the big water mains.
“HV work goes only to HV-qualified locators. Standbys are booked against the dig start.”
- 10Later
A person checks 5% of the clears
Damage prevention coordinatorEach clear says why it was clear. It names the nearest asset and its distance, against the 15 m clear distance, with the reply time and code 10. Today's sample is 26 of 527 clears. The coordinator marks each one Agree or Should have been located. Three tickets on a new housing estate were held instead of cleared. Their phase 2 as-built drawings for low-voltage (LV) and water are not posted yet, so they went to a locator.
“Any area with as-builts still to post is held and sent to a locator.”