- Before
- Reports the backlog each week from exports and spreadsheets. Knows how many jobs there are, but not when they will be done.
- Now
- Opens the backlog sized in hours and crew-weeks, with the date it clears. Tries a crew, overtime or putting work off, and sees the date, cost and risk change before spending anything.
A region's open work orders sized, dated and forecast overnight
This utility region runs electricity and water work from three depots with 14 crews. On a Tuesday in October it has 1,940 open work orders. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
The whole backlog on one screen, sized in hours
Work management managerThe manager owns the region's open work. The backlog is 8,640 labor hours, or 8.3 crew-weeks against a target of 6.0. Thirteen work types appear as tiles, sized by hours and colored by median age. Pole replacements is the biggest red tile: 1,420 h in 58 jobs, a median of 141 days old, with 23 at risk. Below it, a chart shows 12 weeks of history, the late-summer storm and the forecast at current capacity.
Backlog back to target in 20 weeks, next March. At 1,040 h a week of planned work, the backlog falls 120 h a week
- 0206:10
Each open job sized, checked and dated before the manager arrives
Backlog sizer, Readiness checker, Due-date watcherOvernight, the Backlog sizer read 1,940 open work orders and sized them at 8,640 labor hours in 13 work types. The Readiness checker checked six prerequisites per job. It found 3,180 h ready and 4,020 h blocked, each with its purchase-order line, permit or calendar entry, plus 1,440 h in planning. The Due-date watcher applied 13 deadline rules. It found 90 jobs past their date and 31 compliance jobs at risk before the year end.
“412 had no estimate: hours filled from 3 years of completed jobs, marked as estimates”
- 03One click
Pole replacements, with 23 condemned poles against the 180-day limit
Due-date watcherOpening the tile shows how old the jobs are and how ready they are: 380 h ready, 820 h blocked and 220 h in planning. It also shows the deadline rule. License condition 14 says a condemned pole must be replaced within 180 days of its inspection. The jobs table lists the 23 condemned poles due by the year end first. Two on one road have 12 days left and are ready. Two on another are waiting for an outage window.
“Compliance work: it can never be deferred in a scenario.”
- 04The job
One condemned pole, with everything in place except the outage
Readiness checkerThe job is to replace a condemned pole on feeder section 3. It will take 26 h, estimated from 41 similar replacements. The inspection found 38% of the pole's cross-section lost at ground line. Four prerequisites are proven, each with its record: the inspection, the design pack, the pole reserved in a depot bay and the traffic plan. The outage window was never requested. There are 214 customers on that section, and 3 of them are on the priority services list.
“20 days left · 160 of 180 days used.” Request the outage window by Friday to get one before the limit
- 05Drafted
Six outage windows, asked for in one note
Blocker chaserThe Blocker chaser has already drafted the request to the outage planner in network control. It covers six condemned poles on three feeders and gives each pole's license date. It asks for a first window in the morning, 09:00 to 13:00, for an overhead line crew. The note says the poles, traffic plans and job packs are in place. The manager edits it and presses send.
“Releases 14 jobs · 486 h · 6 compliance jobs”
- 06The blockers
4,020 blocked hours, ranked by the deadlines they release
Blocker chaserThere are eight blockers, and each has a named owner. By cause, the blocked hours are materials 1,610 h, permits and outages 1,140 h, design 690 h and customer access 580 h. Second on the list is one purchase order. The pole supplier pushed the delivery of 24 poles back two weeks, and nine condemned poles and 12 line defects wait for it. The stores lead gets a drafted follow-up asking the supplier for a part delivery of 9 poles a week sooner.
“Resolving a blocker moves its hours to ready; the date, risk and map update.”
- 0712 weeks ahead
The deadline runway, week by week
Due-date watcherThis view sets license, permit and customer dates for the next 12 weeks against what the crews can reach. At risk are 23 condemned poles, 6 priority B line defects and 2 reservoir inspections. The first deadlines are the two ready poles, due within two weeks, with no crew time free before then. Valve exercising already has 38 jobs past their date, and customer connections have 11.
“The holiday week is light: the depots work a holiday roster.”
- 08What if…
A contractor crew brings the clearance date 14 weeks closer
Burn-down forecasterThe manager adds a 7-person contractor line crew from the following week. It gives 336 h a week at $118 an hour. The backlog now falls 456 h a week and reaches target in November, 14 weeks earlier, for $198,240. Compliance jobs at risk fall from 31 to 6. Ready work stays at 3.1 crew-weeks, inside the 2 to 4 week band.
“Spend over $150K needs the Director of Operations.”
- 09Sent 07:58
Four plans side by side, one sent for approval
Work management managerThe what-if plans, called scenarios on screen, are compared on date, cost and compliance risk. Plan A, current capacity, clears next March. Plan B, the contractor crew, clears in November for $198,240. Plan C puts off 640 h of low-risk work to the first quarter. It clears in late January at no cost, but 29 jobs stay at risk. Plan D does both and clears a week before B for $158,592. The manager sends B to the director, saying plainly what the crew cannot fix.
“Even with the crew, 6 compliance jobs stay at risk until their blockers clear: six poles need outage windows.”
- 10Approved 08:14
The director approves the spend and stores raises the order
Director of OperationsThe director sees the date, the cost and what is still at risk, and approves plan B at 08:14. The stores lead raises the contractor order. The approval is recorded with its name and time. The weekly backlog report was drafted at 06:24, with each figure linked to its screen. It now reads “Scenario B is approved.”
“Approved by the Director of Operations · 08:14 · recorded in the audit trail”