- Before
- Runs four live tenders and prepares each evaluation for the committee. Knows the cheapest bid is often cheap for a reason nobody finds in time.
- Now
- Opens the leveling grid with each exclusion priced in, each adjustment showing its basis, and the clarifications already drafted for review.
Four substation bids, leveled to one scope before the tender committee
The utility needs a new GIS substation to connect 14,200 homes in a growth area. GIS means gas-insulated switchgear, a compact type of switchgear. The tender covers 8 GIS bays, two 63 MVA transformers, switchgear, protection and SCADA, cables and civil works. It has closed, and the engineer's estimate is $64.2M. The commercial envelopes open today, and the Tender Committee meets in two weeks. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Envelopes opened
As quoted, Bidder B looks like the winner
Category managerThere are four bids, 10,510 pages in all. As the bidders priced them, Bidder A is cheapest at $59.20M. Next come Bidder B at 61.90M, Bidder C at 63.40M and Bidder D at 63.95M. The category manager runs four live tenders, and this one goes to committee in two weeks.
“Bidders A and B look cheapest. Their quoted prices leave out different scope, so they cannot be compared yet.”
- 0206:40
412 requirements, checked against each bid
Tender reader and Compliance checkerThe tender reader reads the RFP, its 4 addenda and 37 answers given before closing. It turns them into 412 requirements and 12 price lines. Each requirement cites its clause, and 86 of them are mandatory. The compliance checker then marks each requirement for each bid. All four bidders meet 365 of them. The matrix shows the 47 where a bid differs.
Bidders B, C and D meet all 86 mandatory requirements · Bidder A fails two and is set aside
- 0306:52
Bidder A fails two mandatory requirements
Bid reader and Compliance checkerPage 4 of Bidder A's commercial proposal sets the term of its bank guarantee. It “shall remain valid for one hundred and twenty (120) days from the date of tender closing”. The tender asks for 180. Its technical volume 2 also has no type-test reports for the offered GIS. Bidder A is not leveled. The committee is asked to confirm that the bid is set aside.
Price effect: “Mandatory: bid security may not be corrected after closing (ITB §17.3)”
- 0406:58
Spares, warranty and price clauses, priced into each bid
Price levellerBidder D leaves out travel for four of the utility's engineers to the factory acceptance tests (+0.12M). It also leaves 2 of 14 mandatory spares unpriced (+0.31M), which brings it to $64.38M. Bidder C offers 24 months of defects liability against 36 (+0.36M) and 10 training days against 20 (+0.07M). That brings it to 63.83M. Bidder B has a copper price clause on the transformers (+0.42M). Its no-load losses are 38 kW against 35 kW (+0.08M). That leaves it at 62.40M, still the lowest.
Commercial exceptions (delay damages, advance payment, performance security, the copper clause) go to contracts counsel.
- 0507:11
Page 214: “shall be by others”
Bid readerDeep in Bidder B's technical proposal, in volume 3 §7.4, the bid reader finds a sentence the deviation schedule never declared. Bidder B's own price schedule, line 7, says the same works are “Included in item 6”. The grid still shows Bidder B first, at $62.40M. Meanwhile the price leveller works out what the missing scope is worth.
“Civil works for the transformer foundations, firewalls and oil containment bunds shall be by others.”
- 0607:12
The missing scope priced, with its basis
Price levellerThe leveller adds $2.30M. That is the median of line 7 in the other compliant bids (Bidder D 2.41M, Bidder C 2.19M). For the same line, the engineer's estimate is 2.38M. The bid reader opens on page 214 with the sentence highlighted, beside the price line that contradicts it. Bidder B's item 6 is 7.05M. That is close to item 6 alone in the other bids (6.70 to 6.85M). It is far below their items 6 and 7 together (8.89 to 9.26M).
“The transformer bays are not in it.”
- 0707:14
Leveled: Bidder B drops from first to third
Category managerWith $2.80M of adjustments, Bidder B is leveled at 64.70M. The price ladder re-sorts on the real scope. Bidder C is now first at 63.83M, 0.55M below Bidder D at 64.38M. Bidder B is third. Each red chip in the grid is one of the leveller's 7 adjustments. The category manager can click any cell to see its source.
“Bidder C is cheapest at $63.83M, 0.55M below Bidder D.”
- 08Drafted for review
A clarification that cannot reopen the price
Report and clarification writerThe clarification to Bidder B quotes page 214 and price line 7 side by side. It asks Bidder B to confirm whether the works in RFP volume 2 §7.1 are in its price. The answer is due by the clarification deadline. A second clarification asks Bidder C to confirm 36-month defects liability and 20 training days, with no change to price. The category manager reviews, and procurement sends.
“This clarification does not permit any change to your tendered price or scope (Instructions to Bidders §28.2).”
- 09The score
Scores on leveled prices, and one score with no reason
Scoring consistency checkerA bid is scored only if it passes the technical mark of 70 and each mandatory requirement. The score weighs leveled price at 75% and the tender's other award criteria at 25%. Bidder C scores 100.00, Bidder B 97.50 and Bidder D 95.95. On quoted prices, Bidder B would have led by 98.51 to 98.23. One evaluator scored Bidder C's delivery schedule 5 of 15 and gave no reason. The other evaluators gave 12 and 11.5. That is a 7-point spread, and the limit is 5 points.
“At the panel's median, Bidder C's technical score would be 88.0. The award order would not change.”
- 10Signed
The evaluation, cited and signed for committee
Category managerThe draft report has nine sections. Each number links to the page or the run it came from. It recommends an award to Bidder C at its tendered $63.40M, subject to its clarification. That avoids a scope gap of about $2.30M that would come back as a variation. It is also $0.87M lower than Bidder B for the same scope. The lead engineer has already signed the technical evaluation. Now the category manager signs, confirming they reviewed the leveling adjustments and their sources.
The agents draft, and the Tender Committee awards.