- Before
- Carries 11 long-lead orders across 7 suppliers. Reads 40 to 60 supplier emails a day and retypes the dates into a tracker. The supplier often did report the slip, in an email nobody read for three weeks.
- Now
- Opens the milestone lines with each supplier email already read and the projects it touches marked. Tests recovery options and sends the cited follow-up.
One supplier email, a three-week winding slip and two substations at risk
The sample utility has 11 long-lead orders open, worth $56.4M, feeding 8 projects. Two 90 MVA 132/33 kV transformers are on the same winding line at one supplier. T2 is for a new substation, and T1 is for a substation reinforcement. One Tuesday at 07:41, the supplier writes. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0107:41
The day opens on the milestone lines
Senior expediter, grid equipmentEach order is one line of factory milestones: design, core, winding, factory test and ex-works. The line runs against the date its project needs the unit on site. The board reads 11 orders, 7 suppliers and 8 projects fed. None is late, and 5 have under 21 days to spare. T2 and T1 each have 7 days to spare. In the right rail, a new email from the supplier's project manager names both orders.
“…the winding of units 2 and 3 under the frame contract (your two purchase orders) will complete three weeks later than in schedule rev. E…”
- 02One click
The email and the revised schedule, read
Supplier mail reader · Milestone trackerThe expediter clicks Read and apply. The supplier mail reader reads the email and schedule rev. F. It finds two orders and the cause, a late conductor delivery from the supplier's own sub-supplier. The milestone tracker moves both windings 21 days. It carries the slip down the line, using the 49 days from factory to site.
“Carried down the line: T2 and T1 each on site three weeks later (49 days factory to site)”
- 031 min 50 s later
The winding node slides three weeks, and two substations turn red
Project impact mapper · Contract checkerOn the board, the winding milestones jump right with a “W +21 d” marker. Both lines go red at −14 days. The project impact mapper finds both deliveries on the zero-float path to energization. That is the chain of work with no slack before the substation is switched on. So the new substation and the reinforcement are each 14 days late. Then the contract checker finds clause 14.2 of the frame contract. The delay notice is due within 10 working days.
“Winding slips 3 weeks on T2 and T1. Projects late: new substation −14 d · reinforcement −14 d. Delay notice due in 10 working days.”
- 04The order
Transformer T2, last promise against today's schedule
Senior expediterThe order page shows T2, a $4.82M purchase order. It now arrives on site 14 days after the date the project needs it. Rev. E and rev. F sit one above the other, so the moved milestones are plain to see. Each date change carries its source, from the purchase order acknowledgment to today's revised schedule. Delay damages run at $24K a week.
“Schedule rev. F: windings +21 days, on site 14 days late”
- 05The new substation
What T2's delay means for a customer's connection date
Project manager, new substationThe project page follows T2 through the site sequence to energization. In order, it is set on its plinth, dressed with its fittings, filled with oil and dried out, and tested on site. Protection and control come last. Energization is now forecast two weeks later than planned. The new substation enables a 38 MW business park connection and 4,100 homes in a new housing development.
“Late by 14 days since this morning… The 38 MW business park connection date would be missed.”
- 06The reinforcement
A reinforcement that has to beat the winter peak
Project manager, reinforcementT1 drives energization of the reinforcement, now forecast two weeks later than planned. The second transformer restores N-1 at a primary substation, meaning it can lose one unit and keep supply on. That substation runs at 104% of its winter rating. The new unit is needed before the winter peak.
“N-1 would not be restored before the winter peak.”
- 07Recovery
Four options priced, one ruled out
Senior expediterThe agents price four options. A second shift on the supplier's winding line at the contract's acceleration rate costs $38K and saves 9 days on both units. A direct road haul from the quay for T2 costs $22K and saves 6 days. Protection works can run alongside dressing at the new substation, from its project manager's site sequence rev. 3. That costs $0 and saves 8 days. Weekend commissioning at the reinforcement costs $31K and saves 7 days. The agents' plan takes all four. With it, the new substation has 9 days to spare and the reinforcement has 2. It costs $91K against $412K of contractor standby avoided.
Ruled out: “Swap the 90 MVA spare in for T1. The spare winds after T1.”
- 08Approval
The spend and the re-sequencing, signed
Head of capital deliveryRecovery spend over $25K needs the head of capital delivery. They see the plan: 4 options for $91K, leaving 9 days to spare at the new substation and 2 at the reinforcement. They sign the spend and the re-sequencing, the change in the order of site work. The meaning of the approval is recorded. The plan holds until the supplier confirms the second shift.
Meaning: “I approve the recovery spend and the site re-sequencing”
- 09The reply
A recovery-plan request, cited, for the expediter to send
Expediting action drafter · Senior expediterThe drafter writes to the supplier's project manager. It says what moved and which need dates it misses. Under clause 14.5, it asks for a recovery plan within 5 working days. The plan should cover the second shift and the days it recovers, conductor from the alternate sub-supplier, and keeping both factory test-bay slots. The expediter edits it if needed and sends it under their own name.
Agents draft, and a named person sends. Nothing goes to a supplier on its own.
- 10Day 1 of 10
The delay notice goes on the first day of the window
Category manager, power transformers and HV switchgearThe notice under clause 14.2 is drafted in the contract's wording. It says the utility became aware of the delay that morning. It reserves the utility's right to delay damages of 0.5% of the unit price per complete week, up to 10%. The category manager signs and sends it the morning of the slip. That is day 1 of 10 working days.
“Delay notice sent on day 1 of 10 · delay damages kept claimable”