- Before
- Carries 11 long-lead orders across 7 suppliers, reads 40–60 supplier emails a day and retypes the dates into a tracker. The supplier often did report the slip, in an email nobody read for three weeks.
- Now
- Opens the milestone lines with each supplier email already read and the projects it touches marked; tests recovery options and sends the cited follow-up.
A three-week winding slip, from one supplier email to two substations
The sample utility has 11 long-lead orders open, worth $56.4M, feeding 8 projects. Two 90 MVA 132/33 kV transformers are on the same winding line at one supplier: T2 for a new substation and T1 for a substation reinforcement. One Tuesday at 07:41, the supplier writes. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0107:41
The day opens on the milestone lines
Senior expediter, grid equipmentEach order is one line of factory milestones (design, core, winding, factory test, ex-works) against the date its project needs it on site. The board reads 11 orders, 7 suppliers, 8 projects fed, 0 late and 5 under 21 days to spare. T2 and T1 each have 7 days to spare. In the right rail, a new email from the supplier's project manager names both orders.
“…the winding of units 2 and 3 under the frame contract (your two purchase orders) will complete three weeks later than in schedule rev. E…”
- 02One click
The email and the revised schedule, read
Supplier mail reader · Milestone trackerThe expediter clicks Read and apply. The supplier mail reader reads the email and schedule rev. F: two orders, and the cause, conductor late at the supplier's own sub-supplier. The milestone tracker moves both windings 21 days and carries the slip down the line using the 49 days from factory to site.
“Carried down the line: T2 and T1 each on site three weeks later (49 days factory to site)”
- 031 min 50 s later
The winding node slides three weeks, and two substations turn red
Project impact mapper · Contract checkerOn the board the winding milestones jump right with a “W +21 d” marker, and both lines go red at −14 days. The project impact mapper finds both deliveries on the zero-float path to energization: the new substation −14 days, the reinforcement −14 days. The contract checker finds clause 14.2 of the frame contract: the delay notice is due within 10 working days.
“Winding slips 3 weeks on T2 and T1 · Projects late: new substation −14 d · reinforcement −14 d · Delay notice due in 10 working days”
- 04The order
Transformer T2, last promise against today's schedule
Senior expediterThe order page shows T2, a $4.82M purchase order, now arriving on site 14 days after the date the project needs it. Rev. E and rev. F sit one above the other, so the moved milestones are plain to see. Each date change carries its source, from the purchase order acknowledgment to today's revised schedule. Delay damages run at $24K a week.
“Schedule rev. F: windings +21 days; on site 14 days late”
- 05The new substation
From the plinth to a customer's connection date
Project manager, new substationThe project page follows T2 through the site sequence (on the plinth, dress, oil fill and dry-out, site tests, protection and control) to energization, now forecast two weeks later than planned. The new substation enables a 38 MW business park connection and 4,100 homes in a new housing development.
“Late by 14 days since this morning… The 38 MW business park connection date would be missed.”
- 06The reinforcement
A reinforcement that has to beat the winter peak
Project manager, reinforcementT1 drives energization of the reinforcement, now forecast two weeks later than planned. The second transformer restores N-1 at a primary substation that runs at 104% of its winter rating, and it is needed before the winter peak.
“N-1 would not be restored before the winter peak.”
- 07Recovery
Four options priced, one ruled out
Senior expediterA second shift on the supplier's winding line at the contract's acceleration rate ($38K, 9 days on both units). A direct road haul from the quay for T2 ($22K, 6 days). Protection works alongside dressing at the new substation, from its project manager's site sequence rev. 3 ($0, 8 days). Weekend commissioning at the reinforcement ($31K, 7 days). The agents' plan takes all four: the new substation +9 days, the reinforcement +2 days, for $91K against $412K of contractor standby avoided.
Ruled out: “Swap the 90 MVA spare in for T1. The spare winds after T1.”
- 08Approval
The spend and the re-sequencing, signed
Head of capital deliveryRecovery spend over $25K needs the head of capital delivery, who sees the plan (4 options, $91K, the new substation +9 days, the reinforcement +2 days) and signs with the meaning of the approval recorded. The plan holds pending the supplier's confirmation of the second shift.
Meaning: “I approve the recovery spend and the site re-sequencing”
- 09The reply
A recovery-plan request, cited, for the expediter to send
Expediting action drafter · Senior expediterThe drafter writes to the supplier's project manager: what moved, the need dates it misses, and a request under clause 14.5 for a recovery plan within 5 working days, covering the second shift and the days it recovers, conductor from the alternate sub-supplier, and both factory test-bay slots kept. The expediter edits it if needed and sends it under their own name.
Agents draft; a named person sends. Nothing goes to a supplier on its own.
- 10Day 1 of 10
The delay notice goes on the first day of the window
Category manager, power transformers and HV switchgearThe notice under clause 14.2 is drafted in the contract's wording: the utility became aware of the delay that morning, and reserves its right to delay damages of 0.5% of the unit price per complete week, up to 10%. The category manager signs and sends it the morning of the slip, day 1 of 10 working days.
“Delay notice sent on day 1 of 10 · delay damages kept claimable”