- Before
- Checks and approves 6–10 switching orders a day before they are issued, as the second person, by reading them. “I read every step twice. It's the step I read once that worries me.”
- Now
- Opens each order on the live single-line diagram with every step simulated, every finding cited to its rule, and decides the reconciliation flags after the job.
One switching order, from a work request to a signed, simulated sequence
Lumina Utilities' Distribution Control North has a cable joint to replace on the Palm Quarter ring: joint J-14 on 11 kV cable Marisol F4 – PQ1 Cedar Lane, on Thursday 15 October, 09:00–15:30. Here is what happens to its switching order, screen by screen, in the working solution.
- 018 Oct
The work request: dead and earthed both ends, nobody off
Joel Mwangi · Cable engineerAn online partial-discharge alarm on 7 Oct reads 2,400 pC at joint J-14 against an alarm level of 500 pC, trending up since August. Joel raises work request WR-48213: points of isolation CB F4 at Marisol Primary and switch PQ1-A at PQ1 Cedar Lane, earths ES-F4 and PQ1-AE, and PQ1–PQ6 kept on supply from Westhaven via W7 — 1,654 customers, 3.1 MW. Four priority customers are on the ring, including Northgate Clinic's dialysis unit.
“I need the cable dead and earthed both ends from nine till half three. Nobody on the ring should lose supply.” — Joel Mwangi
- 02Checked 08:47
Rev A, cloned from last year's order — and checked by four agents
Ravi Iyer · Switching order writerRavi writes SO-26-0418 rev A, 16 steps, cloned from SO-25-0911, a November 2025 joint on cable PQ1–PQ2. The agents check it as soon as he submits. The prior-order finder finds 3 earlier orders on CB F4 and PQ1 and shows rev A is 81 % identical to SO-25-0911. The network simulator runs all 16 steps from the SCADA states on the Marisol–Westhaven model.
Prior-order finder: “rev A is 81% identical to SO-25-0911 — step 7 copied unchanged from its step 9”
- 03Step 3
Opening the feeder first drops the whole ring
Customer impact checkerRev A opens CB F4 at Marisol before switch PQ6-B is closed. On the diagram every RMU from PQ1 to PQ6 goes off supply: 1,654 customers, including Northgate Clinic and 3 life-support registrations, for the roughly 22 minutes it takes to reach PQ6 — 36,388 customer minutes on a job that needed none. SO-25-0911 did exactly this.
LSR 5.4 · “An alternative feed exists: close PQ6-B first.” — Warning
- 04Step 7
A copied close onto an earthed cable — blocked
Safety rule checkerAt step 6 the crew closes earth switch ES-F4, so cable F4–PQ1 is earthed. Step 7, copied from SO-25-0911 step 9, closes CB F4 to restore supply. In the old order the worked section was PQ1–PQ2 and this cable was never earthed. Here CB F4 would close onto the crew's earths. The run stops, CB F4 is ringed in red on the diagram and the step is marked Blocked: it cannot be issued.
“LSR 4.3 · CB F4 would close onto cable F4–PQ1, earthed by ES-F4 at step 6. This step cannot be issued.”
- 05The fix
Rev B: make before break, and the copied step removed
Order drafterThe order drafter proposes rev B as a side-by-side change to the order, not a rewrite. Close PQ6-B now comes before Open CB F4, so all 1,654 customers stay on supply. The copied step 7 is removed: the restoration close of CB F4 already sits at new step 13, after both earths are off. Earths, permit and restoration are unchanged; 15 steps.
The drafter changes as little as possible and explains each change. It never issues or approves an order.
- 06Re-simulated
Fifteen steps, nothing blocked, nobody off supply
Network simulatorRev B is applied and the simulator re-runs every step: 0 blocked, 0 customers off supply, 3 notes. The brief parallel of Marisol and Westhaven through PQ6-B is permitted, both on Coral Ridge 132 kV at an angle of 0.4°. W7 Ridgeway carries 7.3 MW of its 8.0 MW rating (91 %), forecast 7.6 MW (95 %) at the 15:00 peak — within the limit.
LSR 7.1 · “W7 Ridgeway at 7.3 MW of 8.0 MW (91%); forecast 7.6 MW (95%) at the 15:00 peak — within the 100% limit.” — Note
- 07Signed 09:16
Leila signs, with the meaning of her signature
Leila Haddad · Senior control engineerApprove and sign stays shut while any step is blocked or warned. With rev B clean, Leila sees the order, the work, the window, 15 of 15 steps simulated with 0 blocked, and 0 customers off at every step. She signs with her password and the meaning “Checked and approved for issue”. Kwame Asante issues it on Thursday at 09:00, with permit PTW-26-3318 to Tomás Reyes.
“I read every step twice. It's the step I read once that worries me.” — Leila Haddad
- 08On the day
Repeat-back, confirm, next — matched to SCADA as it happens
Kwame Asante · Control room operatorWhile SO-26-0409, CB 3K2 maintenance at Kingsgate Primary 33 kV, runs, Kwame instructs Hamid Rahimi on radio channel 4. Each step carries the time instructed, the repeat-back, the field confirmation and the SCADA event — 3K2 ISOLATED 09:21:57, ES-3K2 CLOSED 09:30:52 — and the order reconciler marks each one Match. Step 7, the permit, waits for Kwame to confirm it.
“Repeat-back, confirm, next. One step at a time.” — Kwame Asante
- 09After the job
Two flags the paper record would have hidden
Order reconcilerSO-26-0396, a cooling fan replacement on transformer T1 at Westhaven Primary, finished Monday at 16:58. 13 of 15 steps matched SCADA and the radio log automatically; 4 of 4 earths were applied and removed. Two flags go to Leila: the field confirmation that ES-T1H was open came in after the disconnector and CB 3T1 had closed, and the clearance for PTW-26-3288 was released by the control room operator, not by Hamid Rahimi, who received it.
“The earth was off in time; the record is not.” · LSR 6.5: only the person who received a clearance may release it, unless a transfer is recorded.
- 10Tue 09:12
Every earth on the network, and the one that should not be there
Order reconcilerThe earths board lists 11 earths under 5 clearances, from SCADA, permits and field confirmations. Ten are under a live permit. E-HR3 at Harbour Road substation, transformer T3, is still recorded as applied 40 hours after permit PTW-26-3290 was cancelled. Until it is confirmed removed, LSR 4.3 blocks any close onto T3's 11 kV side; Leila asks the field to confirm, with a photo.
“Still recorded · 40 h after permit cancelled”