- Before
- Watches frequency, voltage and flows across the transmission network. Knows the low-frequency instruction exists, but not which of its six references applies right now.
- Now
- Asks in plain words and gets numbered actions, each with its clause. Beside them is the branch of conditions and exceptions, checked against the live values.
A 1,000 MW double trip at evening peak, answered clause by clause
A transmission control center, one Monday. Demand is near its evening peak. The control engineer on shift has been on the desk for 14 months and is watching the frequency. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0117:42:06
Two trips, 1,000 MW lost
Control engineerA combined-cycle gas unit trips at 610 MW. Three seconds later an HVDC link, a direct current line to the neighboring system, trips on a converter fault. Its 390 MW of import is gone. The alarms list shows the frequency below 49.5 Hz, lowest 49.42 Hz at 17:42:26. Primary response, the automatic boost from generators, delivered 310 MW from 11 units. The live strip holds at 49.46 Hz, falling at −0.004 Hz/s. Automatic stage 1, set at 49.0 Hz, has 490 MW armed.
“Ask what to do. The answer comes back as numbered actions, each linked to its clause, with the conditions and exceptions beside it.”
- 0217:42:31
Asked in plain words while the agents read the live state
The agentsThe engineer types “Frequency below 49.5 Hz, what now?”. The situation reader reads the live values, without writing anything back. The clause finder matches the operating instruction “Low System Frequency”, revision 9, §4.1 to 4.7. The branch builder follows 11 references into the grid code, the load-shed plan, the demand reduction schedules and the safety rules. It checks each condition against the live values.
Branch builder: “Rate of fall: not met · reserve above 300 MW: applies · 5-minute clock: watching”
- 039.1 seconds later
Four numbered actions, each linked to its clause
Step writerFour actions come from the instruction, with 11 clauses cited. First, dispatch all contingency reserve, 520 MW within 10 minutes. Second, instruct contracted demand reduction, 180 MW. Third, if the frequency is not above 49.5 Hz by 17:48:40, shed 5% in rotation on the shift manager's order. Fourth, declare the emergency state and log each instruction by 18:12. Beside step 3, its branch is already open.
Step 3: “group A, 7 blocks, 490 MW. Hospital, water-pumping and life-support blocks are excluded.”
- 04Step 1
Conditions checked against the live values
Branch builderThe first condition is a reading below 49.5 Hz on two independent measurements for 10 s. The branch shows 49.46 Hz for 64 s, on 2 of 2 measurements. A fast rate of fall would send the engineer straight to step 3, but that condition is not met. Reserve above 300 MW means the shift manager must be told at dispatch, so that applies. One gas turbine unit is under an outage permit, so it is not counted as reserve.
Pumped storage 300 MW and two gas turbine units, 220 MW: “Tell the shift manager as you dispatch.”
- 05Step 2
The contract schedule overrides the instruction
Branch builderThe instruction gives 10 minutes' notice for demand reduction. The grid code says the notice in each contract schedule applies instead. One industrial customer's schedule gives 15 minutes and allows one instruction in 24 hours. That one was last used earlier in the month. So the branch tells the engineer the full 95 MW arrives by 17:59, five minutes later than the instruction suggests.
The contract schedule gives 15 minutes' notice, where the instruction says 10
- 06Step 3
The exception, word for word
Control engineerThe engineer opens §3.4 of the load-shed plan from the branch. The clause opens beside the answer, highlighted, on page 9 of 64. It says the blocks that supply protected sites are never selected in any rotation. Next, clause §3.5 puts the two life-support blocks, 1,284 customers, last. Clause §3.6 leaves out the 14 blocks armed for stage 1. Safety rule 9.2 takes one 33 kV block out because it is under permit.
Load-shed plan §3.4 protects the general hospital block (two 11 kV feeders) and the water treatment works and high-lift pumping station. It also protects the control center's own supply.
- 07Same answer
A superseded table, caught before anyone opens it
Revision checkerThe instruction's §4.5.2 still says to select blocks in the rotation order of Table 3 in the old load-shed plan. That plan was replaced earlier this year, and in it the hospital block sat in rotation group B. The answer uses the current plan. The revision checker raises a High gap. It shows both clauses side by side, with a drafted change for the instruction's owner.
“An operator reading the instruction literally would open the old table.”
- 0817:47:10
The shift manager decides on step 3
Shift managerThe engineer works through the event checklist. Reserve is dispatched from 17:43:40 and demand reduction from 17:44:15, each with its repeat-back. Group A is prepared at 17:45:02. Then the shift manager is asked to decide. The decision window shows the frequency at 49.77 Hz and rising. It also shows group A, each block left out and why. The shift manager chooses to hold.
The choices are “Hold: prepared but not executed” or “Authorize the shed”. Only the shift manager decides.
- 0917:48:20
Above 49.8 Hz, no customer disconnected
Shift log writerThe frequency is back above 49.8 Hz at 17:48:20, six minutes after the trip. The neighboring system is told at 17:51:20 and the regulator's duty officer at 17:58:05, both well before 18:12. Each instruction carries its time and repeat-back. Step 3 shows “Held by the shift manager at 17:47:10, prepared but not executed”. The engineer closes the checklist into the shift log.
The shift log writer records only what a person ticked, said or decided. Entries cannot be edited after the shift closes.
- 10The record
Tonight's event, with the clauses it used
EventsThe event goes on record. The grid lost 1,000 MW and fell to a low of 49.42 Hz. No demand was cut off, and the grid was back to normal in 6 minutes. The record lists the clauses used and the lesson. The revision checker caught §4.5.2 pointing at the old plan. Three rows down is an earlier event. Back then the hospital block was read out from group B of the old plan, and the field engineer stopped it. That event is why §3.4 exists.
“Revision checker caught §4.5.2 pointing at the superseded load-shed plan.”