- Before
- Places 40–60 outage requests a week and builds next week's plan by Wednesday so letters can go out. “I find out the backup feeder is out when the control room rings me on the morning.”
- Now
- Sees every day on a feeder's row light up green, amber or red before she drops an outage, and the reason and first clear day the moment it lands.
One ring main unit swap, from an email to letters ready to post
Lumina Utilities is planning the week of Monday 19 October across Harrow Vale, Kingsmere and Saltmarsh primary substations and the Ridgeway water supply zone. It is Tuesday 13 October, 10:20, and next week's letters must post by Wednesday 14 October at 16:00. Here is what happens to one request, screen by screen, in the working solution.
- 01Tuesday 10:20
The week on one chart, by substation and feeder
Leila Moreno · Outage coordinatorLeila's plan shows 12 outages and 1,980 customers and properties off, with 5 requests to schedule and 1 conflict. A lane across the top carries the Quarry Road closure on Thursday, an amber wind warning on Friday, the cup semi-final and the half marathon. The one red bar is OR-26-0416, the Hollins Park reconductor, which the event and weather watcher has already flagged.
“Event and weather watcher read the amber wind warning for Fri 23: OR-26-0416, overhead work on KM-07, must move”
- 02Read at 09:40
Tom's email, read into nine fields
Request readerTom Brennan's email of 12 Oct 16:41 asks to replace the Lucy-type ring main unit at H47 on Marsh Lane, which failed its partial discharge survey on 2 Oct. The request reader fills the asset, work, dates, times, crew, section off, backup, kit and requester, each cited to the sentence it came from: 08:00–14:00, Ashby Jointing crew B, 412 customers off between RMU-H46 and RMU-H48, back-fed from HV-14 Quarry Road through NOP-1214 at 3.9 MVA.
One assumption flagged: “Back-feeds the rest from Quarry Road” assumes HV-14 is in service on the day.
- 03Picked up
Every day on the row lights up before she drops it
Leila Moreno · Outage coordinatorLeila picks OR-26-0418 from the tray and the HV-12 Marsh Lane row lights up. Monday and Tuesday: Harrow Vale is on one transformer while T2 is overhauled. Wednesday: amber, 4 medically dependent customers and 412 customers off. Thursday: the backup feeder is out. Friday to Sunday: Ashby Jointing crew B is not free.
“Thu 22 Oct — Backup feeder HV-14 Quarry Road is out”
- 04Dropped on Thursday
A red bar, linked to the outage that causes it
Network checkerThursday is one of the two days the crew prefers, so Leila drops it there. The six checks rerun in the side rail and the bar turns red, with a red link to OR-26-0409: Hamid Rezaei's cable diversion for the Kingsway Metro station takes HV-14 out from 07:00 to 17:00. NOP-1214 has nothing to close onto, and the only other tie, HV-13 Orchard Rise, already carries 1.8 MVA of HV-14's load, leaving 0.3 MVA spare against 3.9 MVA needed.
“Can't go on Thu 22 Oct. Backup feeder HV-14 Quarry Road is out. Without it, 1,284 customers would be off for 6 hours instead of 412, and 11 medically dependent instead of 4.”
- 05The reason
Backup headroom, feeder by feeder, day by day
Network checkerThe backup feeds view shows the spare capacity on every feeder's backup for the week, after every approved outage, from network model HV-NM 2026.10.2. HV-12 Marsh Lane needs 3.9 MVA to HV-14: 4.9 MVA spare on most days, 0 on Thursday. The Harrow Vale one-line diagram for Thursday shows HV-14 out and NOP-1214 open with nothing behind it.
“Thursday: HV-14 is out all day for OR-26-0409 … HV-12 has no backup that day: NOP-1214 has nothing to close onto.”
- 06Moved to Wednesday
The first clear day, with actions
All six agentsOne click moves it to Wed 21 Oct, the first clear day. HV-14 takes 3.9 MVA through NOP-1214, with 4.9 MVA spare against 4.29 MVA needed with the 10 % margin. Both transformers are in service, no other outage uses the open point, crew B is free and there is no event, closure or warning near Marsh Lane. One amber remains: 4 medically dependent customers — a home ventilator, two oxygen concentrators, home dialysis — and Marsh Lane Primary School, 312 pupils.
“Clear, with actions · 4 medically dependent customers · 412 customers off”
- 07Approve
What she approves, and what stays with others
Leila Moreno · Outage coordinatorThe approval shows the outage, its date and hours, 412 customers off and the backup through NOP-1214, and the open actions handed to the notice writer. It also says what the approval does not do: the switching stays with network control, and nothing reaches a customer until the communications lead releases it.
“Network control writes and runs the switching from this plan. Nothing is sent to customers until Grace Whitlow releases the notices.”
- 08Approved
Letters, texts, calls and a generator, drafted
Notice writerThe bar turns green on Wednesday. The notice writer drafts 412 letters, 386 texts and 241 emails to post by Wed 14 Oct 16:00, books 4 priority care calls and generator MG-07 for the home ventilator at 23 Heron Close, and writes a letter to the school. Everything waits for release.
“Notices drafted · waiting for Grace Whitlow to release.”
- 09Before release
Who is off, who needs a call, and what they will read
Grace Whitlow · Customer communications leadGrace sees the four medically dependent customers with what each needs power for and the action — generator on site and a call for E. Barlow, a call 48 hours before for the other three. The school gets its own letter and a call: kitchen and heating off 08:00–14:00. Five streets, 412 customers, 386 with a mobile number, and the plain-English letter and text beside them.
Letter: “If you rely on power for medical equipment and have not told us, call us on 0800 555 0142 so we can help.”
- 10The clock
Every notice on its clock
Grace Whitlow · Customer communications leadOn the notices list, OR-26-0418 shows Drafted with its clock at “tomorrow”: letters post by Wed 14 Oct. The other outages of the fortnight sit beside it, sent or drafting when approved, with their channels and calls. Grace releases them; every step, by agent and by person, is already on the append-only decision log.
“Letters post by 16:00 on the post-by day · texts and emails go at 09:00 the next morning · regulatory floor: 2 days”