- Before
- Owns the scope and the network for B4-26. “I find out what a finding costs when the schedule is already late.”
- Now
- Adds a finding and sees the critical path, the return date and the cost redraw at once — with a parallel way to do the job when it would push the date out.
One late boiler finding, from the survey to a signed scope change
Lumina Utilities' Harrowgate Bay Unit B4 is a 320 MW steam unit that also supplies steam to desalination unit D4. Outage B4-26, a major overhaul, opens the breaker on Mon 2 Nov 2026 at 06:00 and returns the unit on Mon 30 Nov: 28.0 days. Today is T-20, and the scope freezes in 3 days. Here is what happens next, screen by screen, in the working solution.
- 01T-20 · morning
The critical path is the home screen
Mariam Saleh · Outage plannerMariam owns the scope and the network for B4-26. Her home is the time-scaled network: 26 jobs and 286 work orders across days 0–30, lanes for unit, turbine, generator, boiler, balance of plant and water, the critical path in red. The header reads 28.0 days on plan, return Mon 30 Nov, boiler float 1.0 day — near-critical. The scope inbox shows three items waiting: the new boiler survey at the top, a feedwater pump seal leak and a challenged chemical clean.
“An outage day at Harrowgate Bay: $412,000 — replacement energy $318,000 · auxiliary-boiler water $94,000”
- 02One click
Every bar shows the evidence that put it there
Condition evidence readerSwitched to Evidence, the same network is coloured by why each job is in the outage: condition evidence, statutory, OEM interval, or no evidence and challenged. Of 286 work orders, 198 are justified by a condition reading, 31 are statutory, 31 are past the OEM interval and 26 were challenged.
“Challenges took the outage from 31.0 to 28.0 days in August: the LP turbines are clean, so they stay closed.”
- 03Before the freeze
No reading, no outage time
Evidence challengerEach challenged item says where it came from, what the challenger looked for and what it found. The boiler chemical clean came from the B4-20 plan template; tube sample TS-B4-0926 shows 18 g/ft² of deposit against the 40 g/ft² trigger, so the proposal is to defer it to B4-28 and keep 2.5 days off the boiler path. For the ID fans it proposes a split: keep 4A, rising at 4.8 mm/s, defer 4B, flat at 2.1 mm/s for 18 months.
Statutory items are never challenged · the evidence challenger proposes, the planner decides, the outage manager signs after the freeze.
- 04Add to scope
Fourteen front-wall tubes under minimum wall
Condition evidence reader and Scope builderSurvey UT-B4-0926 by Corrin Inspection Services, raised by boiler engineer Yusuf Demir at 08:12, found 14 front-wall tubes below the 4.10 mm minimum wall at burner level; the thinnest, tube 47 at 31 m, reads 3.62 mm, thinning 0.38 mm a year since 2022. Tube 52 already leaked on 17 Sep and forced the unit off for 5.2 days. Mariam adds it. The reader goes through all 1,152 readings and cites page 6, table 3; the scope builder drafts the job — 840 crew-hours, 56 m of tube, $212,000 — and joins the open pad-weld work order WO-B4-41620.
Readiness tracker: “40 m of tube in stock; 16 m from Arlo Steel, ETA Tue 27 Oct, needed day 15.”
- 05Seconds later
The boiler path goes critical: +2.0 days
Critical path schedulerPlaced after the superheater pendant repairs — same welders, same scaffold lift — the job puts the boiler on the critical path. The network redraws: 30.0 days, return Wed 2 Dec, boiler float 0.0 days. Priced at the value of an outage day, that is $824,000, and the turbine path now has 2.0 days of float.
“The front-wall job made the boiler path critical: +2.0 days. Return moves from Mon 30 Nov to Wed 2 Dec · +$824,000 at $412,000 a day.”
- 06The swap
Panels welded on nights, beside the pendants
Sequence advisorThe advisor offers a parallel way, citing lesson L-B3-25-07: sister unit B3 replaced 9 front-wall tubes on nights in 2025 and saved 1.5 days. Kestrel Fabrication prefabricates 2-tube panels before the outage, and a second crew fits them through 7 window cuts on nights, days 8–12. Mariam swaps: back to 28.0 days, boiler float 1.0 day, $775,400 net avoided.
“Back to 28.0 days. The panels go in on nights, days 8–12, beside the pendant repairs; the boiler keeps 1.0 day of float. Night crew $48,600 against $824,000 of outage days.”
- 07The job
The wall-thickness map behind the job
Yusuf Demir · Boiler engineerThe job page shows the front wall as a map of 128 tubes by 9 elevations, coloured by wall: 14 below 4.10 mm, 22 on the 4.10–4.60 mm watch list. Margin notes cite the survey page and table, the forced outage and design calculation DC-B4-PP-017. The work package runs from isolation and confined-space entry through 100 % radiography of the 28 welds and a re-survey of the 22 watch tubes, with each material's quantity and status.
Margin note: “Against survey UT-B4-0322 (March 2022), the burner zone thinned 0.38 mm a year. The 22 watch tubes reach 4.10 mm in about 18 months.”
- 08Signed
The evidence, both options and the money on one page
Tomas Eriksen · Outage managerScope change SC-B4-26-014 goes to Tomas with the finding, the options and their effect. Option A, in place after the pendants: 30.0 days, $1,036,000 with the outage days. Option B, panels on nights: 28.0 days, $260,600. Mariam raised and placed it, Yusuf confirmed the evidence, and Tomas signs as outage manager. The panel order goes to Kestrel and the baseline is updated.
When signed: panel order to Kestrel Fabrication (7 panels, ready Thu 29 Oct) · night crew booked days 8–12 · work package WP-B4-26-287 issued · baseline updated.
- 09Day 5 clash
One 40 t crane, two lifts on the same shift
Grace Mwangi · Contracts and procurementHeadcount follows the network: 88 people on site at the peak, day 5. On that day Halden Turbine Services' HP rotor lift, on the critical path, and Brightline Scaffolding's scaffold deck lift both need the 40 t crane on the day shift. In B4-22 the same clash cost the rotor 7 hours. The fix is one button: move the deck lift to the night of day 4.
Readiness tracker: it finds the clash and never books a contractor — Grace moves the lift.
- 10T-20 · ready?
What still needs someone before breaker open
Readiness trackerThe milestone line runs from T-180 to breaker open, with the work-package milestone at T-30 missed at 93 %. The checklist covers work packages, materials, contractors, the crane, isolations and permits, the outage notice and the water plan for D4. Materials at risk are listed by need date against ETA: the HP diaphragm seal strips arrive a day after they are needed, and the condenser tube plugs are not yet ordered.
“D4 on auxiliary steam from Unit B3 · 52,000 m³ a day · approved by Water Operations”