WorkflowPower Generation & Water Production

Power Plant Outage Planning

Power plant outage planning that builds each job from condition data and shows what a new finding does to the return date

See one case, screen by screen ↓
Watch with transcript →

Built forOutage plannersOutage managersBoiler engineersTurbine engineersProcurement teams

The Problem Today

Planners match the outage work list to the schedule by hand, so they learn too late what a new finding does to the return date.

$450K
a day, up to $700K, to buy in power while one coal unit is down published

Matched by hand in spreadsheets

  • Work orders
  • Surveys
  • Trends
  • Bulletins
  • Copied jobs, no evidenceJobs done by the calendar take crew-hours and crane time
  • Two crews, one craneContractor clashes are found on the day

The Solution

  1. Readings become jobsSurvey, trend and bulletin readings turned into planned jobs
  2. Unproven work challengedJobs with no reading, test or bulletin behind them are questioned
  3. Effect on the date shownEach job placed on the schedule, with a way to run it alongside other work if it slips
  4. The outage manager signsEach change after the freeze signed, with its evidence, options and cost

Built-in controls

  • Each job cites its reading, test or bulletin
  • Jobs the law requires are not challenged
  • Agents do not order parts or book crews

What You Get

Fewer days of replacement power bought in, because late findings are worked alongside other jobs where they can be.

10 → 2
working days from a late finding to a signed change our estimate
  • Clean turbines left closedRoutine openings put off when the readings show no need
  • Crane clashes found earlyTwo contractors on one crane, seen before the day
  • Past lessons matched to jobsLessons from earlier outages matched to this outage's jobs
In short

What is Power Plant Outage Planning?

It plans and controls the work and schedule of a planned unit outage. That means what work goes in, why, when it is done and what it does to the return date. Power Plant Outage Planning adds seven agents. They build the work list from condition data, challenge jobs with no evidence and place each job on the schedule. The planner chooses and the outage manager signs.

How to choose AI solutions for utilities →

Updated

The problem

Outage plans live in spreadsheets, so late findings cause overruns

From time to time a power plant unit shuts down for a planned overhaul, called an outage. The planner decides which jobs go in and how long it all takes. The work list comes from many places. There are open and deferred work orders in the maintenance system, and inspection and tube thickness surveys in PDFs. There are vibration and performance trends, equipment makers' bulletins, the last outage's plan and contractors' proposals. The schedule lives in a different tool, and people join the two by hand, in spreadsheets and meetings. Say a survey finds boiler tubes worn too thin, three weeks before the unit shuts down. The planner only learns the new return date after re-running the schedule by hand.

That is how late findings become overruns, and each extra outage day is expensive. The utility buys in power to replace the unit's output. If the unit also supplies steam to a nearby plant, that steam must come from a costly backup boiler. Some jobs are done only by the calendar and copied from the last plan. They take crews, crane time and days on the critical path, the chain of jobs that sets the end date. Yet the readings say these jobs are not needed. Two contractors book the same crane for the same shift. And the lesson from the last outage that would have saved a day sits in a file nobody opened.

typical$450,000-700,000a dayto buy in replacement power while one coal unit was down, from a utility's filing with its regulator
typical92%of the work list unchanged after the freeze is the top-quarter benchmark (INPO figures, cited in an Ontario Energy Board filing)
Where the working days go, from one late finding to a signed changeestimated
By hand10 days
With the solution1.8 days
  • Reading the survey and checking each reading against the minimum safe thickness1.5 → 0.1 d
  • Writing up the job: steps, materials, crew-hours, permits2 → 0.3 d
  • Re-running the schedule to see the new return date1.5 → 0.1 d
  • Finding and pricing a way to do the job alongside other work2 → 0.5 d
  • Checking for clashes over materials, the crane and contractors1.5 → 0.3 d
  • Writing up the change and getting it signed1.5 → 0.5 d

Our estimate for one late finding on a major overhaul, in working days, by hand and with the solution.

How it works

From condition readings to a scoped job on the outage critical path

What comes in
Evidence inreports, work orders, bulletins · inspections, tests, plant data, lessons
Agents at work
Condition evidence readerreadings + sources
Evidence challengerno evidence?
Then
Scope builderjob + materials
Readiness trackerstock, arrivals, crane
Then
Critical path schedulerdays + dollars
Then
Sequence advisorparallel ways
Lessons matcherpast outages
A person decides
Outage plannerchooses, and the outage manager signs
What comes out
Jobs with evidence
End date held
Signed change
One case, step by step

One late boiler finding on a 28-day power plant outage, worked alongside other jobs

The unit is a 320 MW plant that makes power and also supplies steam to a nearby plant. Its major overhaul starts on a Monday at 06:00, when the unit is cut off from the grid. It is due back four weeks later, at 28.0 days. Today is 20 days before the start, and the work list freezes in 3 days. Here is what happens next, screen by screen, in the working solution.

A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.

  1. 01T-20 · morning

    The schedule is the home screen

    Outage planner

    The planner owns the work list and the schedule for the outage. The home screen shows the schedule as a network over time: 26 jobs and 286 work orders across days 0 to 30. There are lanes for the unit, turbine, generator, boiler, the rest of the plant and the steam supply. The critical path, the chain of jobs that sets the end date, is in red. The header reads 28.0 days, with only 1.0 day of spare time on the boiler, so it is close to the critical path. Three items wait in the inbox: the new boiler survey, a feedwater pump seal leak and a challenged chemical clean.

    “An outage day at this station: $412,000 · replacement energy $318,000 · auxiliary-boiler steam $94,000”

  2. 02One click

    Each bar shows the evidence that put it there

    Condition evidence reader

    Switched to Evidence, the same schedule is colored by why each job is in the outage. A job can rest on a condition reading, a legal requirement or the maker's service interval. Or it has no evidence and is challenged. Of 286 work orders, 198 rest on a reading, 31 on the law and 31 on the maker's interval. The other 26 were challenged.

    “Challenges took the outage from 31.0 to 28.0 days: the LP turbines are clean, so they stay closed.”

  3. 03Before the freeze

    No reading, no outage time

    Evidence challenger

    Each challenged item says where it came from, what the challenger looked for and what it found. The boiler chemical clean was copied from an old outage plan. The tube sample shows 18 g/ft² of deposit, against a 40 g/ft² trigger. So the proposal is to put it off to the next outage and keep 2.5 days off the boiler work. For the two fans, it proposes a split. Keep 4A, whose vibration is rising at 4.8 mm/s. Put off 4B, flat at 2.1 mm/s for 18 months.

    Jobs the law requires are not challenged · the challenger proposes, the planner decides, the outage manager signs changes after the freeze.

  4. 04Add to scope

    Fourteen front-wall tubes worn below the safe thickness

    Condition evidence reader and Scope builder

    At 08:12 the boiler engineer raised the inspection contractor's new survey. It found 14 front-wall tubes at burner level below the 4.10 mm minimum safe thickness. The thinnest, tube 47 at 31 m, reads 3.62 mm and has thinned 0.38 mm a year since the previous survey. Tube 52 leaked weeks earlier and forced the unit off for 5.2 days. The planner adds the finding. The reader checks all 1,152 readings and cites page 6, table 3. The scope builder drafts the job: 840 crew-hours, 56 m of tube and $212,000. It also joins the job to the open pad-weld work order.

    Readiness tracker: “40 m of tube in stock; 16 m from the supplier, arriving the week before breaker open, needed day 15.”

  5. 05Seconds later

    The boiler sets the end date: +2.0 days

    Critical path scheduler

    The job is placed after the superheater pendant repairs, because it needs the same welders and scaffold. That puts the boiler on the critical path. The schedule redraws at 30.0 days, so the unit returns two days later. The boiler has no spare time left. At the value of an outage day, those two days cost $824,000. The turbine work now has 2.0 days to spare.

    “The front-wall job made the boiler path critical: +2.0 days. Return moves two days later · +$824,000 at $412,000 a day.”

  6. 06The swap

    Tube panels fitted on night shifts, beside the superheater repairs

    Sequence advisor

    The advisor offers a way to do the job alongside other work. It cites a sister unit that replaced 9 front-wall tubes on nights last year and saved 1.5 days. A fabricator builds 2-tube panels before the outage. A second crew fits them through 7 cuts in the wall, on nights, days 8 to 12. The planner takes it. The outage is back to 28.0 days, with 1.0 day of spare time on the boiler. The net saving is $775,400.

    “Back to 28.0 days. The panels go in on nights, days 8 to 12, beside the pendant repairs; the boiler keeps 1.0 day of float. Night crew $48,600 against $824,000 of outage days.”

  7. 07The job

    The tube thickness map behind the job

    Boiler engineer

    The job page shows the front wall as a map of 128 tubes at 9 heights, colored by thickness. Fourteen are below 4.10 mm and 22 are on a watch list, between 4.10 and 4.60 mm. Notes in the margin cite the survey page and table, the forced outage and the design calculation. The work package runs from isolation and confined-space entry to X-ray checks of all 28 welds. It includes a new survey of the 22 watch tubes and each material's quantity and status.

    Margin note: “Against the previous survey, the burner zone thinned 0.38 mm a year. The 22 watch tubes reach 4.10 mm in about 18 months.”

  8. 08Signed

    The evidence, both options and the money on one page

    Outage manager

    The change goes to the outage manager with the finding, both options and their effect. Option A, tubes replaced in place after the superheater repairs: 30.0 days and $1,036,000 with the outage days. Option B, panels on nights: 28.0 days and $260,600. The planner raised and placed it, and the boiler engineer confirmed the evidence. The outage manager signs. The panel order goes to the fabricator and the approved schedule is updated.

    When signed: panel order to the fabricator (7 panels, ready before breaker open). Then: night crew booked days 8 to 12 · work package issued · baseline updated.

  9. 09Day 5 clash

    One 40 t crane, two lifts on the same shift

    Contracts and procurement

    The number of people on site follows the schedule. It peaks at 88 on day 5. On that day two lifts need the 40 t crane on the same day shift. One is the turbine contractor's rotor lift, which is on the critical path. The other is the scaffolders' deck lift. In an earlier outage the same clash cost the rotor 7 hours. The fix is one button: move the deck lift to the night of day 4.

    Readiness tracker: it finds the clash and does not book a contractor. Procurement moves the lift.

  10. 10T-20 · ready?

    What still needs someone before the outage starts

    Readiness tracker

    A timeline runs from 180 days out to the day the unit comes off the grid. The work-package milestone, due 30 days out, was missed at 93 %. The checklist covers work packages, materials, contractors, the crane, isolations and permits, the outage notice and the steam plan. Materials at risk are listed by the date they are needed, against when they arrive. The turbine seal strips arrive a day after they are needed, and the condenser tube plugs are not yet ordered.

    “Host plant on auxiliary steam from a sister unit · approved by the host plant's operations”

Who it’s for

The planners, engineers and outage manager who run one outage

The same outage, seen by the five people who own it. What the weeks before the start looked like, and what they look like now.

Outage planner
Places the work and chooses how it is done
Before
Owns the work list and schedule for the outage. Finds out what a finding costs only when the schedule is already late.
Now
Adds a finding and sees the critical path, return date and cost redraw at once. Gets a way to do the job alongside other work when it would push the date out.
Outage manager
Chairs the board that approves changes
Before
Signs changes argued over in meetings and spreadsheets, and wants the evidence and the days before signing.
Now
Gets one page with the finding and the options in days and dollars. It shows the effect on the return date and budget, and who confirmed the evidence.
Boiler engineer
Raises findings and confirms evidence
Before
Reads the tube thickness surveys and raised the front-wall finding. Fourteen tubes below the safe limit must be fixed, whatever it costs.
Now
Sees the survey read and mapped tube by tube, with each reading cited by page and table. Confirms the evidence before the change is signed.
Turbine engineer
Owns the turbine work, the longest in the outage
Before
Argues every outage against routine jobs. Knows the low-pressure turbines are clean, and that opening them each time is six years of habit.
Now
Sees each job with no reading challenged. Opening the low-pressure turbines is put off to the next outage, with its reason, saving 3.0 days.
Contracts and procurement lead
Mobilizes contractors, materials and the crane
Before
Chases materials and crane bookings for six contractors. Wants a real need date for each item, instead of as soon as possible.
Now
Sees each material's need date against its arrival date, the number of people on site each day and the crane clash with its fix. Places the orders.
The agents

Evidence, planning, schedule and readiness agents for each outage

Seven agents turn condition readings into jobs and place each one on the schedule. The planner chooses and the outage manager signs.

Condition evidence reader

Reads inspection reports, tube thickness surveys, vibration, oil and heat-camera trends and makers' bulletins. Pulls out each reading with its location, unit and limit. Works out how fast it is changing since the last survey, and links it to the job it supports.

  • Never invents or estimates a reading
  • Each value cites its page and table
  • Marks a reading older than 36 months as out of date
Scope builder

Turns findings, deferred work orders and makers' bulletins into jobs. Each job has its steps, materials and quantities, crew-hours by trade, permits and contractor. It joins any open work order on the same equipment.

  • Never adds to the approved plan on its own
Evidence challenger

Looks for a reading, test, bulletin or legal rule behind each job. Challenges any job with none, saying where it came from, what it looked for and what it found. Proposes to put it off, split it or keep it, with the days and hours at stake.

  • Never challenges a job the law requires
  • Never removes a job. A person decides
Critical path scheduler

Places each job on the outage schedule with its order, crew and shared equipment. Works out the new end date, the critical path and the spare time on each lane. Prices the change at the value of an outage day.

  • Never changes the approved schedule without a signed change
Sequence advisor

When a job pushes out the end date, looks for ways around it. That can be a second crew or shift, parts built ahead of time, a different way in or a different window. Prices each in days and dollars and cites the past lesson behind it.

  • Recommends one option and never picks it. The planner does
Readiness tracker

Watches materials against the dates they are needed, contractor arrival, permits and clashes over shared equipment such as the 40 t crane. Tracks the milestones up to the start of the outage.

  • Never places an order or books a contractor
Lessons matcher

Matches lessons from three earlier outages, on this unit and sister units, to the jobs in this outage.

  • Never marks a lesson as applied. The owner does
Outage manager

Signs every change after the freeze.

Ask in plain words

Power plant outage planning answers on a job, a finding or a date

Ask about any job, finding, contractor or date in the outage, or say what to change. Each answer points to its records. These answers use the sample data.

Why is the front-wall tube job in the scope?

Because the survey shows it is needed. It found 14 front-wall tubes below the 4.10 mm minimum safe thickness. The thinnest, tube 47, reads 3.62 mm. Tube 52 leaked weeks ago and forced the unit off for 5.2 days. The minimum comes from the unit's design calculation. This is condition evidence, so the job will not be challenged.

What does the tube job do to the end date?

Done in place after the superheater repairs, it puts the boiler on the critical path. That adds 2.0 days, about $824,000 at $412,000 a day. Done as ready-made panels fitted on nights, it adds 0 days and costs $48,600. A sister unit did it that way last year.

Which scope items have no evidence?

Of 286 work orders, 26 had no reading, test or bulletin behind them. Nine are put off to the next outage, saving 1,940 crew-hours and $462,000. Eleven were kept once evidence was found. Six are still open, among them the boiler chemical clean (18 g/ft² against 40, 2.5 days of boiler work). The low-pressure turbines were the big one. Putting them off took the outage from 31.0 to 28.0 days.

Are we ready for the outage to start?

We are 91 % ready, 20 days out. Three things need someone this week. Work packages are at 93 %, and the 100 % milestone 30 days out was missed. The 40 t crane is double-booked on day 5. The turbine seal strips arrive a day after they are needed. Isolations, the outage notice and the steam plan are done.

The screens

The schedule, the evidence view and a signed change in outage planning software

From the working solution, on its sample data. Pick one to see it large.

The critical pathThe outage as a schedule over time, with the critical path in red and spare time on each lane. It shows the return date and the value of an outage day. The inbox and the new finding sit beside it.
Why each job is in the outageThe same schedule colored by evidence: condition reading, legal requirement, maker's interval, or no evidence and challenged.
Agents placing the jobStep by step: the survey read and cited, the job drafted with its crew-hours and materials, and stock and arrival dates checked.
The path grows two daysPlaced after the superheater repairs, the tube job puts the boiler on the critical path: 30.0 days and +$824,000, with two ways to do it.
Swapped for the parallel jobReady-made panels fitted on nights: back to 28.0 days with 1.0 day spare on the boiler, for a $48,600 night crew.
The jobThe thickness map of the front wall, margin notes citing each source, both options and the work package.
The work listEach job with its evidence, work orders, crew-hours, days, spare time and contractor. Filter by type of evidence or by the critical path.
ChallengedJobs with no current evidence: where each came from, what was looked for and found, and the proposal to put off, split or keep.
The signed changeThe finding, the options in days and dollars, the effect on the outage and budget, the sign-off and what happens once it is signed.
Contractors and the cranePeople on site day by day, the 40 t crane, storage space and furnace access, and the day-5 clash with its fix.
ReadinessMilestones from 180 days out to the start, the readiness checklist, materials at risk by need date against arrival date, and work packages by lane.
LessonsLessons from three earlier outages on this and sister units, matched to this outage's jobs. Each shows its owner and whether it was applied.
SettingsThe outage window and freeze date, the value of an outage day, what counts as evidence, the challenge rules and who signs.
Governance

Jobs backed by evidence, old jobs questioned and a signed plan

Each job cites its evidenceEach job shows the reading, test, bulletin or legal rule that put it in the outage. That can be the survey with its page and table, a trend from the plant's data or a maker's bulletin.
Jobs with no evidence are challenged. Jobs the law requires are notJobs copied from an old plan, done only by the calendar or proposed by a contractor are challenged. Each says what was looked for and found. A person keeps, splits or puts off each one. The agents do not remove a job.
After the freeze, the outage manager signsEach change after the work list is frozen goes to the outage manager. It carries the evidence, the options with their days and dollars, the effect on the return date and budget, and the plant engineer's confirmation.
The approved schedule changes only on a signatureThe scheduler shows the effect of each option. It does not change the approved schedule without a signed change.
Agents do not order or bookThe readiness tracker watches materials, crews and the crane. Contracts and procurement place the orders and book the contractors. The sequence advisor recommends, and the planner chooses.
Each step on the activity trailEach agent step and each decision is recorded with its time: who raised a finding, who confirmed the evidence, who signed. Each change to the rules is kept as a new version with its reason.
Configuration

Freeze, outage-day value and evidence rules for each plant

The freeze date, the value of an outage day, what counts as evidence and who signs are settings. Each station chooses its own.

SettingDefaultChoose from
Scope freezeT-17T-17 · T-14 · T-24
Value of an outage day$412,000 (energy $318,000 + steam $94,000)$412,000 · $380,000 at the winter energy price. The value is used to price every option
Near-critical when float is2.0 days or less2.0 days or less · 1.0 day or less · 3.0 days or less
Condition reading counts whenWithin 36 monthsInspection, ultrasonic testing (UT), vibration, oil, heat camera, performance test. Jobs the law requires are never challenged, and jobs with no evidence always are
Challenge a time-based item with no reading in24 months24 months · 12 months · 36 months
Propose defer when the reading is below50 % of its trigger50 % · 30 % · 70 % of its trigger
Ask the plant engineer before a deferOnOn · Off
Connections

The surveys, trends, bulletins and work orders the outage plan is built from

Work ordersopen, deferred and planned, from the maintenance system, updated hourly
Inspection and test reportstube thickness surveys, replica reports, heat-camera images and test results, as PDFs and spreadsheets
Plant datathe plant's data history: vibration, temperatures, performance
OEM bulletinsthe turbine, generator and boiler makers' advice and service intervals
Lessons registerswhat happened in past outages on this and sister units, and what was done about it
Spares and contractorspurchase orders, contractor plans and the booking calendar for shared equipment
What it changes

Outage days, a stable work list and challenged jobs in plant outage planning

Each figure carries its label: a target the solution is built to, an estimate, a typical published result, or a proven one.

demo
$412ka day
for each outage day avoided at the sample's 320 MW unit, which also supplies steam to a nearby plant. One finding rearranged saved two days
Done in sequence30.0 days · +$824,000
Swapped to a parallel job28.0 days · +$48,600
target
92%
target for a stable work list: little work added after the freeze, because jobs are planned from condition data first
top-quarter benchmark
demo
26of 26
jobs with no evidence challenged before they used crew time. Nine were put off, saving 1,940 crew-hours and $462,000
26 of 26 challenged
9 deferred with their reason

“Demo” means seen in the working solution, on its sample outage data. “Target” means the design goal, measured in the live solution. “Estimated” means our estimate of the working days for one late finding on a major overhaul. They add up to 10 days by hand and 2 with the solution. “Typical” means published figures. A Portland General Electric filing on a coal unit outage in 2006 put replacement power at $450,000 to $700,000 a day. INPO AP-928 benchmarks are cited in an Ontario Energy Board filing. In the top quarter of plants, 92 % of the work list is unchanged after the freeze. The $412,000 value of an outage day is the sample utility's own setting (energy $318,000 + steam $94,000). The utility, its station, contractors and records in the worked example are sample data. Names on the screens are sample data.

Questions

Questions on power plant outage planning software

What is power plant outage planning software?

It plans and controls the work and schedule of a planned unit outage. That means what work goes in, why, when it is done and what it does to the return date. Power Plant Outage Planning adds seven agents. They build the work list from condition data, challenge jobs with no evidence and place each job on the schedule. The planner chooses and the outage manager signs.

How does it decide what work goes into the outage?

Each job carries the evidence behind it. That can be a condition reading from the last 36 months, a legal rule, or a maker's interval or bulletin. Jobs with none are challenged. They include jobs copied from an old plan, jobs done only by the calendar and contractors' proposals. A person keeps, splits or puts off each one. In the sample outage, 9 of 26 challenged items were put off, taking 3.0 days out.

How does it show what a new finding does to the schedule?

When the planner adds a finding, the scope builder drafts the job. The scheduler places it with its crew and shared equipment, then works out the critical path and spare time again. The header shows the new length, return date and cost at once. In the sample case that was +2.0 days and +$824,000.

What happens when a finding would push out the return date?

The sequence advisor looks for a way to do the job alongside other work. That can be a second crew or shift, parts built ahead, a different way in or a different window. It prices each in days and dollars and cites the past lesson behind it. It recommends one, and the planner chooses. In the sample case, ready-made panels fitted on nights kept the outage at 28.0 days for $48,600.

Does it count the cost of steam for a nearby plant during the outage?

Yes, if you set it. The value of an outage day is a setting used to price each option. In the sample it is $412,000. That is $318,000 of replacement energy plus $94,000 for steam from a backup boiler, while the nearby plant runs on steam from another unit.

How does it keep the outage ready to start?

The readiness tracker watches milestones from 180 days out to the start, work packages, and materials by need date against arrival date. It also watches contractor arrival, permits and clashes over shared equipment such as the 40 t crane. The lessons matcher puts past lessons against this outage's jobs. Neither one places an order, books a contractor or marks a lesson as applied.

Can an agent change the approved schedule or drop a job?

No. The agents read, draft, challenge and propose. They do not remove a job, pick an option, order material or change the approved schedule. The planner places the work and chooses how. The plant engineer confirms the evidence, and the outage manager signs each change after the freeze.

Can we test it on one of our past outages?

Yes. The Agentic Solution Engine builds and deploys it from your requirements and documents. That means your outage procedures, evidence and challenge rules, plan templates, inspection reports and lessons files. It goes live once each quality gate has passed. We will walk you through it on one of your own past outages first.

Replay a past outage
in power plant outage planning.

We'll run Power Plant Outage Planning on the scope, surveys and lessons of one of your past outages.