Power Plant Outage Planning demo
Outages scoped right, so they finish on time. 1:15
What the demo shows
A workflow solution for outage planners that builds plant outage scope from condition data.
Seven agents build the outage scope from condition data: every item shows the reading, test or bulletin that justifies it, items with no evidence are challenged, and each accepted job drops onto the outage's critical path so the planner sees at once what a finding does to the return date, with a parallel way to do it when it would push the date out; the outage manager signs every change after the freeze.
Transcript
- Power Plant Outage Planning builds outage scope from condition data for outage planners.
- Today, scope found late makes outages overrun at $400,000 a day.
- Outage B4-26 at Harrogate Bay, 28 days, every job on the critical path.
- Each job shows its evidence.
- Work with none is challenged.
- That took three days out.
- A boiler survey finds 14 tubes below below minimum wall.
- Merriam adds the job.
- Agents read the survey, draft the job, and place it.
- The critical path grows two days.
- The advisor offers panels welded on nights in parallel.
- Merriam swaps, 28 days again.
- Tomas signs the change with the evidence, both options, and the money on one page.
- Build on Botminds.
- Agents, data, screens, and governance on one platform.
Transcribed from the film’s narration. Captions are on the player.