- Before
- Leads each trip investigation on four combined-cycle blocks, with 9 trips so far this year. By the time the trends arrive, the shift log has already decided the cause.
- Now
- Opens one timeline to the millisecond, with the first-out marked and each possible cause tested against it, and accepts the cause.
Plant trip root cause analysis of one drum level trip, from first-out to proof
A power station runs four combined-cycle blocks. One night, Block 2 trips while it is ramping up. Here is the investigation, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01The night of the trip · 03:12:47
Block 2 trips while ramping up, and the log blames pump B
Shift charge engineerBlock 2 is ramping to 390 MW on a dispatch instruction. Then its heat recovery steam generator (HRSG) trips, because the water in its high-pressure (HP) drum falls too low. The gas and steam turbines go with it. The block loses 386 MW and is back on the grid 7 h 40 min later. At the sample plant's prices that costs an estimated $248K. The alarm journal lists 186 alarms in the first minute. A feed pump B alarm sits above the trip in the same second. At 03:20 the shift charge engineer writes what they saw first.
Shift log, 03:20: “HP FW pump B tripped then drum level low-low. Suspect pump B.”
- 02Two days later · 07:40
The agents build the timeline in seconds
Reliability engineerThe reliability engineer leads each trip investigation on the four blocks. They open this one and click Build the timeline. The evidence keeper had frozen the evidence at 03:41 on the night. The timeline builder corrects the journal by −0.42 s. It swaps the historian for the 250 ms trip buffer, a finer record kept around the trip. Then it merges 214 SOE events, 186 alarms and 38 trends on one GPS clock.
Agents' run: “journal −0.42 s · historian replaced by the 250 ms trip buffer · dispatch log ±0”
- 03The first-out
Drum level LO-LO first, pump B after
Timeline builderThe master trip relay records which signal tripped first. It names HP drum level LO-LO, 2 of 3 sensors, at 03:12:47.318. Pump B tripped at 03:12:47.902, 0.584 s after the first-out. Before that, the HP feedwater control valve sat at 41.2 % for 25.9 s while its demand rose to 100 %. Feedwater held at 214 t/h while steam rose to 231 t/h. The cause analyst drafts the cause: the feedwater valve stuck.
“Pump B tripped at 03:12:47.902, 0.584 s after the first-out”
- 045 s around the first-out
The level was falling 1.8 s before the trip
Reliability engineerZoomed to 5 seconds, each lane reads on the same time axis. The drum level crosses LO at −200 mm 1.8 s before the LO-LO trip at −350 mm. The valve is still stuck. Only after the trip does it break free and jump to 63.0 %. This is stick-slip, where a valve sticks and then jumps. The shift log's line is shown on the timeline, struck through.
On the timeline: “falling · 1.8 s before the first-out”
- 05The sequence of events
Each event on GPS time, with its source
Timeline builderUnder the trends, the merged list gives each event its GPS time, its gap from the first-out, its kind and its source. Events found only in a trend are marked no alarm. The valve's position stops following its demand at 03:12:21.400, 25.9 s before the trip, and no alarm sounded. The master trip relay operates 6 ms after the first-out, the gas turbine at 11 ms and the steam turbine at 17 ms.
“Valve position stops following its demand at 41.2%” · no alarm
- 0608:05
Five causes tested, four ruled out, one confirmed
Reliability engineerThe cause analyst tests the shift log's cause first, then the standard set. Pump B is ruled out, because it tripped after the first-out while pushing against a closed path. The level sensors are ruled out, because they agree within 12 mm. Operator response is ruled out, because level control was in automatic. The protection is ruled out, because the 2-of-3 vote worked. A stuck feedwater valve is confirmed. The reliability engineer accepts the cause.
Root cause: “The packing was torqued to 95 N·m at the last repack; the datasheet says 55 to 65”
- 07The record behind it
The last repack of the valve
Maintenance and history checkerIn the frozen evidence, a work order shows a contractor repacked the valve weeks before the trip. To stop a leak, they tightened the gland nuts to 95 N·m. The stroke was checked by a hand signal from the control room (moves OK). No test after the work is recorded. No source is given for the torque value. Between the repack and the trip, the positioner logged 14 travel deviations at 40 to 42 %.
“Read 22 work orders on this valve since 2019; this is the only repack at more than 65 N·m.”
- 08It has happened before
Last year's Block 1 trip had the same pattern
Similar event finderThe similar event finder searches 14 past investigations and 212 bulletins. It matches on the valve model, the travel band where it sticks and the shape of demand against position. Last year's Block 1 trip is a 94 % match. Its valve held at 40.6 % for 19 s. It was recorded as slow operator response and closed with operator retraining and no check. An earlier Block 3 runback, a fast automatic cut in output, is an 81 % match.
“A repack came first, each time. None of the three work orders records a torque source.”
- 0908:22
Five actions, each with a check that can fail
Control and instrumentation engineerThe action planner drafts five actions. The valve is repacked at 60 N·m. All 6 HP and IP feedwater valves get an alarm that compares demand to position. The work instruction for all 38 control valves gets the datasheet torque. The Block 1 investigation is reopened. And the block runs 30 days of load following without a deviation. At 08:22 the operations manager approves. The alarm action carries a change number because it changes an alarm. The control and instrumentation engineer runs the signal injection test, and it passes on 6 of 6 valves.
“Alarm action passed · alarm in 3.2 to 3.6 s on all 6 valves · 1 of 5 checks”
- 1008:26 · open for 30 more days
The manager signs, and the investigation stays open
Operations managerThe report is drafted with each fact linked to its source. It covers what happened, the cause, what was not the cause, the five actions and the safety note. A safety valve lifted for 4.4 s and reseated, and nobody was on the HRSG. Beside it, the forced outage report to the system operator is due within 3 days. It carries the cause code HRSG HP feedwater control valve. The operations manager signs, with the meaning of the signature recorded. The investigation closes only when all five checks pass, the last at the end of the 30-day window.
Signed: “I have reviewed the evidence and agree with the cause and the actions”