WorkflowNew Connections, Solar & EV Programs

Electrical Drawing Approval

Electrical drawing approval that checks each breaker, cable and CT against the consultant's load schedule and your standards, with clause-cited comments on day one

See one case, screen by screen ↓
Watch with transcript →

Built forDesign approval engineersConsulting engineersSubstation plannersConnections managers

The Problem Today

Reviewers check breakers and loads by hand on separate documents, so an undersized breaker is caught rounds later.

Checked by hand, sheet by sheet

  • Drawings
  • Schedule
  • Standards
  • Circulars
  • The same clauses, read againA few clauses cause most returns, yet each is checked by hand
  • Clock restarts each roundBuildings wait for power, and connection fees wait too

The Solution

  1. Each sheet readEach breaker, cable, relay setting and room size, found on its sheet
  2. Load recomputedMaximum demand worked board by board from the consultant's own schedule
  3. Ratings matched to loadsEach breaker and cable against the load it carries, each clause cited
  4. The engineer decides and signsAccepts, edits or dismisses each comment, then one cited sheet goes out

Built-in controls

  • Unreadable ratings flagged, with no guessing
  • Waiving a must-fix needs a second signature
  • No capacity committed before approval

What You Get

Buildings are connected sooner, and undersized breakers are fixed at the drawing stage, before anyone finds them on site.

  • Feeder headroom kept currentEach declared load held as pending on its feeder
  • Consultants fix it in one goEach comment gives location, value found, clause and action
  • Resubmissions checked fastEach revision compared, and earlier comments closed or kept open
In short

What is Electrical Drawing Approval?

Electrical drawing approval software is for the utility engineers who approve a consultant's electrical design before a building is connected. Electrical Drawing Approval reads the single line diagram, layouts and load schedule as soon as they arrive. It checks them against your design standards and circulars. Then it drafts a comment sheet that cites each clause. A design approval engineer decides each comment and signs.

How to choose AI solutions for utilities →

Updated

The problem

Reviewers match each breaker to its load by hand, across separate documents

Before a new building can be connected to the grid, the utility must approve its electrical design. The building's consulting engineer sends in a package. It holds the single line diagrams, which show how power flows from the supply to each board. It also holds the schedule of loads, the main distribution board (MDB) schedule, the substation room layout and the earthing layout. The utility's design approval engineer checks each breaker, cable, current transformer (CT), relay setting and room size against its design standards and circulars. Then the engineer writes the comment sheet. The same few clauses send most designs back. Yet the engineer checks those clauses by hand, from scratch, on each package.

The trouble is that the drawing and the load schedule are separate documents. So the most common mistake is easy to miss. That mistake is a breaker or cable smaller than the load the consultant's own schedule declares. For example, the main incoming breaker may be sized to an old load. The CT ratio may be sized to the breaker, or a cable sized without derating. Derating is the cut in a cable's rating for heat and how it is laid. The mistake is found at the second or third resubmission, and each one restarts the review clock. Or it is found at site inspection. There, an undersized breaker or cable means nuisance trips, an overheated cable or a failed inspection that delays switching the power on.

estimated2.7submissionsper approval in the sample utility's review log. Each one restarts the review clock.
estimated19working daysfrom first submission to approval, against a promise of 3 working days per review
typical29%less likely to fail inspection after automated plan review, in a published study of residential solar permits
Where a design package's working days goestimated
By hand19 days
With the solution6.7 days
  • Reading each sheet and the load schedule against the standards3 → 0.5 d
  • Writing the comment sheet, clause by clause1 → 0.2 d
  • Consultant revises the drawings after the first round5 → 4 d
  • Re-reviewing the resubmission3 → 0.5 d
  • Extra rounds for what the first review missed7 → 1.5 d

Our estimated split of the 19 working days from first submission to approval, by hand and with the solution. The 19 days come from the sample utility's review log, which is its baseline.

How it works

Portal to signed comment sheet, each step of a drawing approval

What comes in
Package in7 files · drawings, load schedule, calculations
Agents at work
Drawing readereach item read
Load schedule checkermaximum demand recomputed
Then
Rating matcherIb ≤ In ≤ Iz
Clause checker31 checks
Then
Comment writerbubbles on the drawing
Then
Network plan updaterload held as pending
A person decides
Design approval engineerdecides each comment and signs
What comes out
Clause-cited checklist
Comment sheet to consultant
Load in the network plan
One case, step by step

One apartment tower's design package, with a 400 A breaker on a 520 A load

A consulting engineer submits the design for one residential tower. It has 14 floors, 126 apartments, 6 retail units and 8 EV charging bays. It will run on a new 1000 kVA substation, fed from an 11 kV feeder, the supply line from the grid. Its load falls in the 250 kVA to 1 MVA band, so the utility has 3 working days to review it. Here is what happens, screen by screen, in the working solution.

A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.

  1. 01Morning

    The queue, sorted by its clock

    Design approval engineer

    The engineer's Submissions list shows 23 open packages. Of these, 4 are due today and 6 are resubmissions. Over the last 30 days, the median time to first comments is 1 day. Each row shows the load, the revisions, the clock and what the agents found. A hotel passes each check, and a townhouse scheme has only 2 advisory comments. Both are ready to approve. A retail park is on day 3 of 3 with 2 must-fix comments.

    “Review clock: 1 / 3 / 5 working days by load band · it restarts at each revision”

  2. 0208:52

    Seven files in, each rating read

    Drawing reader and Load schedule checker

    Rev A arrives through the portal as seven files. Five are drawings: E-001 single line diagram, E-002 MDB schedule, E-101 substation room, E-201 earthing and E-301 riser. The other two are the LS-02 schedule of loads and a 38-page calculation pack. The drawing reader reads 270 devices, cables and dimensions on the five drawings. The load schedule checker reads 42 rows and seven boards. Nothing is unreadable, so nothing is guessed.

    “Six agents checked this package when it arrived at 08:52, in 4 min 12 s. Each step is on the record.”

  3. 0308:56

    A bubble on the main breaker

    Rating matcher

    The single line diagram opens as a CAD sheet, with the comments placed on the drawing itself. Bubble 1 sits on the main incoming breaker, Q1. It is a 400 A MCCB, a moulded case circuit breaker, for a 520 A design current. The side panel shows what the drawing says and what the load schedule says. It also quotes the clause word for word and shows the comment the consultant will read. Ten passed checks show as green ticks on their devices.

    “Rated 400 A for a 520 A load · LDS-201 §5.3.2 · Must fix”

  4. 04The load thread

    The schedule is right and the drawing is wrong

    Load schedule checker

    The load check recomputes LS-02 with the utility's diversity table. Diversity is the allowance for loads that do not all run at the same time. The connected load is 1,294.6 kVA. Take away 934.2 kVA of diversity and the maximum demand is 360.4 kVA. At 400 V, that is a 520 A design current. The consultant's own diversity factors and total match the recompute. But E-001 shows Q1 at 400 A, which is 120 A short.

    “The consultant's total, 360.4 kVA, matches the recompute. The schedule is right; the drawing is not.”

  5. 05What if

    Try the fix the comment asks for

    Design approval engineer

    The engineer tries the fix the comment asks for. The incomer becomes a 630 A ACB, an air circuit breaker. The incoming cable becomes 2 × 4C 240 mm², rated 704 A after derating. The metering CT becomes 800/5. Each dependent rule runs again. The load current (520 A) is now below the breaker rating (630 A), which is below the cable rating (704 A). The 800/5 CT also clears the 650 A minimum. Comment 4 stays open, because the retail feeder and its board incomer are both 250 A.

    “C1, C2 and C3 would close · This is the fix in the comment sheet. C4 is on the retail board.”

  6. 06The other sheets

    The earth and the substation room, checked too

    Clause checker

    On E-201, note 6 records a measured earth electrode resistance of 2.4 Ω. LDS-305 §4.1 allows 1.0 Ω for an 11/0.4 kV substation. So the comment asks for an extended ring or more rods, a fall-of-potential re-test and the test sheet. On E-101, the substation door gives 1.2 m of clear space. A 1000 kVA transformer needs 1.5 m × 2.4 m. That comment is advisory, and it goes to substation planning.

    “Earth 2.4 Ω, limit 1.0 Ω · LDS-305 §4.1 · Must fix”

  7. 0731 checks

    All 31 checks in force for the load band

    Clause checker

    The compliance checklist lists the 31 checks in force for the 250 kVA to 1 MVA band. They are grouped by section: incomer and protection, cables, metering, earthing, substation room, loads and power quality. Of the 31, 24 pass, 5 are must fix and 2 are advisory. Each line shows its clause and links to its comment on the drawing.

    “31 checks in force for the 250 kVA to 1 MVA band · each tied to its clause and its place on the drawing”

  8. 0810:05

    The engineer decides and signs

    Design approval engineer

    The engineer accepts the seven comments. Any comment could instead be edited, or dismissed with a reason that goes on the record. Then the engineer signs the return with a PIN and a statement of what the signature means. No agent can send the sheet.

    Meaning of signature: “I have reviewed this design against the standards in force”

  9. 09Day 1 of 3

    One comment sheet with each clause, on day one

    Consulting engineer

    The consultant gets one comment sheet from the utility's network connections team. Each comment gives its drawing location, the value found, the clause and what is required. It asks for a 630 A ACB with LSIG trip, 2 × 4C 240 mm² in parallel and a CT 800/5 class 0.5S. It also asks for a 125 A retail board incomer or a selectivity table, and an earth re-test at 1.0 Ω or less. Rev B will restart the 3-day clock, and the agents will re-check only what changed.

    “Sent to the consultant, each comment with its clause, on day 1”

  10. 10Same morning

    The real maximum demand, in the network plan

    Substation planner

    The tower's 360.4 kVA appears on its substation as in review. That is 36% of the 1000 kVA transformer. A neighboring tower's 410 kVA reserve request would add 41% more. The 11 kV feeder from its primary substation has a firm capacity of 7.2 MVA. Of that, 4.9 MVA is the July peak, 0.9 MVA is approved but not yet connected and 0.36 MVA is pending. That leaves 1.04 MVA. The tower's load stays pending until the design is approved.

    “After this tower, the feeder keeps 1.04 MVA of firm headroom. The neighboring tower's 410 kVA request fits, leaving 0.63 MVA.”

Who it’s for

The consultant, reviewer, planner and head of connections

The same design package as four people see it, in a week before the agents and a week now.

Design approval engineer
Decides comments and signs
Before
Reviews 6 to 8 packages a day, each with 5 to 12 drawings and a load schedule. Checks them against four standards and a stack of circulars. The breaker is on one sheet and the load on another, and that is where the mistakes hide.
Now
Opens each package with the comments already on the drawing. Each one quotes its clause and shows the load-schedule rows behind it. Decides each comment, then signs.
Consulting electrical engineer
Engineer of record
Before
Designs the building, submits it and answers comments round after round. Wants all the comments in the first round, each with its clause, to fix them in one go.
Now
Gets one signed comment sheet on day one. Each comment gives its drawing location, the value found, the clause and the action required.
Substation planner
Confirms substation size and room
Before
Sizes substations and tracks feeder headroom from the loads declared in calculation packs. Needs the real maximum demand instead of the figure on page 1 of the calc pack.
Now
Sees each declared load on its substation and 11 kV feeder as soon as it is checked. The load stays pending until approval. Confirms the substation size.
Head of network connections
Second signature over 1 MVA and on waivers
Before
Owns the review commitments and the connection backlog. Each resubmission is a building that waits.
Now
Sees each package on its clock and each round of revisions. Gives the second signature for loads over 1 MVA and for any waived must-fix comment.
The agents

The reader, load checker and rating matcher behind each drawing approval

Six agents read the drawings and the load schedule together and cite each clause. A design approval engineer signs.

Drawing reader

Reads single line diagrams, layouts and riser diagrams in PDF or DWG. It finds each breaker, cable, CT, relay setting, busbar and dimension, with its place on the sheet. On a resubmission, it compares Rev B with Rev A and finds what changed.

  • Does not guess an unreadable rating. It flags it “cannot read” for the engineer
  • Reads only the submitted package
Load schedule checker

Reads the schedule of loads and recomputes maximum demand board by board. It uses the utility's diversity table (LDS-201 Table 4-1) and the circulars in force, such as the one that counts EV chargers at 1.00.

  • Does not change the consultant's numbers. It only flags differences
Rating matcher

Matches each device and cable on the drawing to the load it carries. The core rule is Ib ≤ In ≤ Iz. The load current must not exceed the breaker rating, and the breaker rating must not exceed the corrected cable rating. It also checks that the CT primary is at least 1.25 × Ib. Devices in series need a selectivity of at least 1.6, and breaking capacity must meet the fault level.

  • Does not size equipment for the consultant. It states what the clause requires
Clause checker

Runs each check in force for the load band. For each result it cites the clause and its revision, from LDS-201, LDS-305, LMS-110, LSR-02 and the circulars.

  • Never cites a superseded circular
  • Never invents a clause
Comment writer

Drafts the comment sheet, with one comment per finding. Each comment gives its location, the value found, the limit, the clause and the action. On a resubmission, it closes each earlier comment with the evidence or keeps it open.

  • Does not issue the sheet. Only the design approval engineer signs
Network plan updater

Adds each declared load to the substation and 11 kV feeder plan as pending, and commits it when the approval is signed.

  • Never commits capacity before approval
Design approval engineer

Accepts, edits or dismisses, then signs.

Ask in plain words

Questions about a device, a clause or a submission

Ask about a device, a clause or a submission in plain words. Each answer cites the sheet, the schedule row and the clause.

Why is the main breaker a must fix?

E-001 shows Q1 as a 400 A MCCB. The consultant's own schedule totals 360.4 kVA, which is a 520 A design current at 400 V. LDS-201 rev 7 §5.3.2 needs the incomer at or above the design current and at or below the cable rating. So the comment asks for a 630 A ACB, and C2 asks for a cable that can carry it.

Which submissions could miss their clock today?

Four are due today. A medical center is on Rev C with 1 must fix. The retail park is on Rev B with 2 must fix. The other two, the townhouse scheme (2 advisory) and the hotel, have no must-fix comment and are ready to approve.

Does the latest EV charger circular change the tower's load?

No. The circular in force counts EV chargers at a diversity of 1.00, unless a load-management system limits them. LS-02 already counts the 8 chargers at 7.4 kVA and 1.00, or 59.2 kVA, so that check passes. This circular replaced an earlier one that used 0.40, and the earlier one is not cited.

Is there headroom on the feeder for this tower?

Yes. The feeder has a firm capacity of 7.2 MVA. Of that, 4.9 MVA is the July peak, 0.9 MVA is approved but not yet connected and the tower's 0.36 MVA is pending. That leaves 1.04 MVA. Its substation runs at 36% with this tower, and at 77% if the neighboring tower's 410 kVA reservation is added.

The screens

The single line diagram with its bubbles, the load check and the comment sheet

From the working solution, on its sample data. Pick one to see it large.

Drawing reviewThe consultant's single line diagram, with each comment as a bubble on its device with its clause and severity. The view also shows the passed checks, the load thread and the comment rail.
SubmissionsEach open package with its load, revisions, review clock, what the agents found, status and reviewer.
How it was checkedThe six agents' steps on the package, with what each found and how long it took, ending with the engineer's decision.
Load checkThe schedule of loads recomputed with the diversity table, from connected load to design current, against the incomer on the drawing.
Each rating against its loadTry the incomer, cable and CT the comment asks for and see each rule re-run, device by device.
The earthing layoutThe earth electrode comment on E-201, with the measured value, the clause and the action for the consultant.
Compliance checklist31 checks in force for the load band, by section, each with its clause and its comment on the drawing.
Sign and sendThe return signed with the meaning of the signature and a PIN, beside the decision and the record.
The comment sheetWhat the consultant receives: each comment with its drawing location, clause and the action required.
Resubmission re-checkRev B against Rev A: five earlier comments closed with the evidence, one still open on a chiller feeder.
Network planDeclared loads rolled up to the substation and the 11 kV feeder, with firm headroom and the loads pending approval.
Standards and circularsThe versions in force, the clauses that return designs most and each clause the comments cite.
Review rulesReview clocks by load band, standards in force, the diversity table, severity and sign-off.
Governance

Clause citations and second signatures in electrical drawing approval

Each comment cites its clauseEach comment carries the standard, its revision and the section, for example LDS-201 rev 7 §5.3.2. It also shows the drawing location and the load-schedule rows behind it. Superseded circulars are kept for reference and are not cited.
An engineer decides and signsOnly a design approval engineer signs a Return or an Approve, with a PIN and the meaning of the signature. Agents read, check, cite and draft. They do not send a comment sheet.
A second signature where it mattersLoads over 1 MVA need a second signature from the Head of Network Connections. A must-fix comment can only be waived with a second signature and a reason.
An unreadable rating is flagged and never guessedWhen a rating on a drawing cannot be read with certainty, the drawing reader marks it for the engineer. The agents do not change the consultant's numbers or size equipment for them.
No capacity committed before approvalA declared load goes into the network plan as pending and is committed only when the approval is signed. The substation planner confirms the substation size and room.
Each step on the recordEach agent step and each human decision is on the record. That includes who accepted, edited or dismissed a comment and why, and who signed and when. The consultant sees only the signed comment sheet.
Configuration

Review clocks, standards in force and sign-off for drawing approval

The review clocks, the standards in force, the diversity table, severity and sign-off are all settings. The utility chooses them, and each change is saved as a new version.

SettingDefaultChoose from
Review clocks by load band1 · 3 · 5 working daysUp to 250 kVA · 250 kVA to 1 MVA · over 1 MVA or 11 kV supply, each in working days. The clock restarts at each revision and pauses while the package is with the consultant
Standards in forceLDS-201 rev 7, LDS-305 rev 4, LMS-110 rev 3, LSR-02 rev 5Plus Circulars 2026/07 and 2026/04 · superseded versions kept but not cited
Diversity table (LDS-201 Table 4-1)Apartments over 100 units 0.16Retail units 0.70 · EV chargers, no load management 1.00 · pumps and ventilation 0.60 · lifts 0.50 · common lighting and power 0.50
SeverityRatings below the load: must fixMust fix · Advisory. Earth resistance over the limit is must fix. Power factor below 0.95 and substation room access are advisory
Return or approveDesign approval engineerNamed design approval engineers
Loads over 1 MVA, and waiving a must-fix commentSecond signatureHead of Network Connections. A waiver also needs a reason
Substation size and roomConfirmed by substation planningNamed substation planner
Comment wordingOnWrite for the consultant (value found, limit, clause, action) · cite the revision of the standard · do not size the equipment. Each is On or Off
Connections

The connections portal, drawings, load schedules and the network plan

The connections portaleach design package checked the moment it arrives
LV/MV drawingssingle line diagrams, MDB schedules, riser diagrams, substation room and earthing layouts, in PDF or DWG
Load schedulesconnected load, diversity and maximum demand board by board, in a spreadsheet
Substation location and size requestsroom size, clear height, door and access for the transformer
Design regulations and circularsyour standards clause by clause, with the versions in force and the superseded ones
The network plandeclared loads by substation and 11 kV feeder: pending, committed, connected
What it changes

Fewer resubmissions per electrical design approval

Each figure carries its label: a target the solution is built to, an estimate, a typical published result, or a proven one.

target
Every
breaker, cable, CT and earth checked against its declared load before it reaches site
31 checks per package
each tied to its clause
target
1.4
submissions per approval, down from 2.7, so buildings are connected sooner
Today2.7 rounds
With agents1.4 rounds
target
Day 1
each comment out with its clause, inside a 3-working-day review clock
Returned on day 1
of a 3-working-day review clock

“demo” means seen in the working solution, on its sample data. “target” means the design goal, measured in the live solution. “estimated” means the baseline we set for the sample utility, and our split of its days. That baseline is 2.7 submissions per approval and 19 working days from first submission to approval. “typical” means published figures (NREL, 2023: automated plan review left residential solar projects 29 % less likely to fail inspection). For context, the Great Britain connections standard for LV/HV design approval is 90 % within 10 working days (Ofgem SLC15). The rule Ib ≤ In ≤ Iz comes from IEC 60364-4-43 §433.1 and BS 7671 §433.1.1. The standards LDS-201, LDS-305, LMS-110 and LSR-02 belong to the sample utility. Names on the screens are sample data.

Questions

Load checks, circulars and second signatures in LV design approval

What is electrical drawing approval software?

Electrical drawing approval software is for the utility engineers who approve a consultant's electrical design before a building is connected. Electrical Drawing Approval reads the single line diagram, layouts and load schedule as soon as they arrive. It checks them against your design standards and circulars. Then it drafts a comment sheet that cites each clause. A design approval engineer decides each comment and signs.

How does it check a drawing against the load schedule?

The load schedule checker recomputes maximum demand from the schedule with your diversity table. The rating matcher then checks each breaker, cable and CT against the load it carries. It applies Ib ≤ In ≤ Iz with the derated cable, and checks the CT ratio and selectivity. In the sample package, that is how a 400 A incomer on a 520 A load was caught in the first round.

Does it use our own design standards and circulars?

Yes. It checks against the standards and circulars you set as in force for each load band, and each comment cites the clause and its revision. Superseded circulars are kept for reference and are not cited.

How does it handle resubmissions?

When a revision arrives, the drawing reader compares it with the previous one. Only the checks the changes touch are run again. In the sample, Rev B of a business park closed 5 of 6 earlier comments and kept one open. That one was the chiller feeder cable, rated 287 A after derating, on a 315 A breaker.

Does it design or size the equipment for the consultant?

No. It states what the clause requires and the value found. It does not change the consultant's numbers or pick a product. The design stays the consultant's, and the decision stays with your engineer.

Who signs, and when is a second signature needed?

Only a design approval engineer signs a Return or an Approve. Loads over 1 MVA and any waived must-fix comment need a second signature. A dismissed comment needs a reason on the record. Agents read, check, cite and draft, and they do not sign or commit capacity.

Can we set our own review clocks, diversity table and severity rules?

Yes. You set the review clock for each load band, the standards in force and the diversity table. You also set which findings are must fix or advisory, who signs and the comment wording. Each change is saved as a new version that applies to new submissions.

What do we share to get started?

Share your design standards and circulars, your diversity table, your comment sheet template and a sample of past submissions. The Agentic Solution Engine builds and deploys the solution from those requirements and documents. It goes live once each quality gate has passed. We will walk you through it on your own design packages first.

Run electrical drawing approval
on your own past design packages.

We'll run Electrical Drawing Approval on a sample of your own past submissions and comment sheets.