- Before
- Reviews 6 to 8 packages a day, each with 5 to 12 drawings and a load schedule. Checks them against four standards and a stack of circulars. The breaker is on one sheet and the load on another, and that is where the mistakes hide.
- Now
- Opens each package with the comments already on the drawing. Each one quotes its clause and shows the load-schedule rows behind it. Decides each comment, then signs.
One apartment tower's design package, with a 400 A breaker on a 520 A load
A consulting engineer submits the design for one residential tower. It has 14 floors, 126 apartments, 6 retail units and 8 EV charging bays. It will run on a new 1000 kVA substation, fed from an 11 kV feeder, the supply line from the grid. Its load falls in the 250 kVA to 1 MVA band, so the utility has 3 working days to review it. Here is what happens, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
The queue, sorted by its clock
Design approval engineerThe engineer's Submissions list shows 23 open packages. Of these, 4 are due today and 6 are resubmissions. Over the last 30 days, the median time to first comments is 1 day. Each row shows the load, the revisions, the clock and what the agents found. A hotel passes each check, and a townhouse scheme has only 2 advisory comments. Both are ready to approve. A retail park is on day 3 of 3 with 2 must-fix comments.
“Review clock: 1 / 3 / 5 working days by load band · it restarts at each revision”
- 0208:52
Seven files in, each rating read
Drawing reader and Load schedule checkerRev A arrives through the portal as seven files. Five are drawings: E-001 single line diagram, E-002 MDB schedule, E-101 substation room, E-201 earthing and E-301 riser. The other two are the LS-02 schedule of loads and a 38-page calculation pack. The drawing reader reads 270 devices, cables and dimensions on the five drawings. The load schedule checker reads 42 rows and seven boards. Nothing is unreadable, so nothing is guessed.
“Six agents checked this package when it arrived at 08:52, in 4 min 12 s. Each step is on the record.”
- 0308:56
A bubble on the main breaker
Rating matcherThe single line diagram opens as a CAD sheet, with the comments placed on the drawing itself. Bubble 1 sits on the main incoming breaker, Q1. It is a 400 A MCCB, a moulded case circuit breaker, for a 520 A design current. The side panel shows what the drawing says and what the load schedule says. It also quotes the clause word for word and shows the comment the consultant will read. Ten passed checks show as green ticks on their devices.
“Rated 400 A for a 520 A load · LDS-201 §5.3.2 · Must fix”
- 04The load thread
The schedule is right and the drawing is wrong
Load schedule checkerThe load check recomputes LS-02 with the utility's diversity table. Diversity is the allowance for loads that do not all run at the same time. The connected load is 1,294.6 kVA. Take away 934.2 kVA of diversity and the maximum demand is 360.4 kVA. At 400 V, that is a 520 A design current. The consultant's own diversity factors and total match the recompute. But E-001 shows Q1 at 400 A, which is 120 A short.
“The consultant's total, 360.4 kVA, matches the recompute. The schedule is right; the drawing is not.”
- 05What if
Try the fix the comment asks for
Design approval engineerThe engineer tries the fix the comment asks for. The incomer becomes a 630 A ACB, an air circuit breaker. The incoming cable becomes 2 × 4C 240 mm², rated 704 A after derating. The metering CT becomes 800/5. Each dependent rule runs again. The load current (520 A) is now below the breaker rating (630 A), which is below the cable rating (704 A). The 800/5 CT also clears the 650 A minimum. Comment 4 stays open, because the retail feeder and its board incomer are both 250 A.
“C1, C2 and C3 would close · This is the fix in the comment sheet. C4 is on the retail board.”
- 06The other sheets
The earth and the substation room, checked too
Clause checkerOn E-201, note 6 records a measured earth electrode resistance of 2.4 Ω. LDS-305 §4.1 allows 1.0 Ω for an 11/0.4 kV substation. So the comment asks for an extended ring or more rods, a fall-of-potential re-test and the test sheet. On E-101, the substation door gives 1.2 m of clear space. A 1000 kVA transformer needs 1.5 m × 2.4 m. That comment is advisory, and it goes to substation planning.
“Earth 2.4 Ω, limit 1.0 Ω · LDS-305 §4.1 · Must fix”
- 0731 checks
All 31 checks in force for the load band
Clause checkerThe compliance checklist lists the 31 checks in force for the 250 kVA to 1 MVA band. They are grouped by section: incomer and protection, cables, metering, earthing, substation room, loads and power quality. Of the 31, 24 pass, 5 are must fix and 2 are advisory. Each line shows its clause and links to its comment on the drawing.
“31 checks in force for the 250 kVA to 1 MVA band · each tied to its clause and its place on the drawing”
- 0810:05
The engineer decides and signs
Design approval engineerThe engineer accepts the seven comments. Any comment could instead be edited, or dismissed with a reason that goes on the record. Then the engineer signs the return with a PIN and a statement of what the signature means. No agent can send the sheet.
Meaning of signature: “I have reviewed this design against the standards in force”
- 09Day 1 of 3
One comment sheet with each clause, on day one
Consulting engineerThe consultant gets one comment sheet from the utility's network connections team. Each comment gives its drawing location, the value found, the clause and what is required. It asks for a 630 A ACB with LSIG trip, 2 × 4C 240 mm² in parallel and a CT 800/5 class 0.5S. It also asks for a 125 A retail board incomer or a selectivity table, and an earth re-test at 1.0 Ω or less. Rev B will restart the 3-day clock, and the agents will re-check only what changed.
“Sent to the consultant, each comment with its clause, on day 1”
- 10Same morning
The real maximum demand, in the network plan
Substation plannerThe tower's 360.4 kVA appears on its substation as in review. That is 36% of the 1000 kVA transformer. A neighboring tower's 410 kVA reserve request would add 41% more. The 11 kV feeder from its primary substation has a firm capacity of 7.2 MVA. Of that, 4.9 MVA is the July peak, 0.9 MVA is approved but not yet connected and 0.36 MVA is pending. That leaves 1.04 MVA. The tower's load stays pending until the design is approved.
“After this tower, the feeder keeps 1.04 MVA of firm headroom. The neighboring tower's 410 kVA request fits, leaving 0.63 MVA.”