A 300 MW data center request through large load interconnection screening
The utility carries 14 open large-load requests for 3,855 MW. A developer's request for 300 MW at a 230 kV substation, complete for four days, is next to screen. Here is what happens, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
Fourteen requests, 3,855 MW asked, 875 MW ready
Large-load account managerThe queue is ranked by readiness, in queue order under the large-load tariff. Seven requests score 70 or more, for 875 MW; 2,170 MW scores under 50, with no site control, no deposit or duplicates. The developer's data center campus asks 300 MW by Q4 2028 and is waiting to be screened.
Planning should not spend a month on a request before anyone knows it is real.
- 02One click
The file read, checked and screened in about a minute
Six agentsThe account manager presses Screen request. The request reader takes 9 documents and 214 fields: 300 MW at the 230 kV substation, ramp 60 → 150 → 300 MW by Q4 2028. The readiness checker finds 6 pass, 3 pending and 3 short. The duplicate detector and the tariff terms checker follow, then the headroom screener, each step logged with its time.
Readiness checker: “site option ends before the study does; letter of credit $20.0M; no air permit for backup generators”
- 03The headroom screen
180 MW short in 2028, and a staged offer the network can serve
Headroom screenerOn the 2028 summer peak case, rev. 3 (N-1), the substation has 120 MW for new load from Q2 2028, after a contracted hydrogen load. The ramp is 30 MW above headroom in Q2 2028 and 180 MW short from Q4 2028, hatched red on the chart. The screener proposes three stages that follow the capital plan: 120 MW now, 240 MW with a second line in Q3 2029, 300 MW with a second autotransformer in Q3 2030.
“The network cannot carry 300 MW in 2028. It can serve the ramp in three stages as the planned upgrades come in.”
- 04Another substation
The same request, re-screened at a 345 kV substation
Headroom screenerClicking a nearby 345 kV substation on the map re-screens the request there: 360 MW of headroom at the end of 2028, but 350 MW held by requests ahead, so 10 MW free, and 18 km of new 345 kV line to reach it. An earlier 450 MW request at the first substation missed its site-control date, so it holds no capacity. The developer's own transformer order covers 180 MW in 2028.
“The developer's own transformer order covers 180 MW in 2028: the 300 MW step is ahead of its hardware.”
- 05Duplicate check
Same parcel, same 300 MW, another utility
Duplicate detectorThe shared large-load register shows a record for the same 212-acre parcel and 300 MW, filed earlier with a neighboring electric cooperative: a 0.94 match against a threshold of 0.85. The two site outlines differ by less than 20 meters. The developer's disclosure in Part 7 of the application says “none”. The detector recommends asking for an explanation and keeping the request in screening.
“The detector flags. It does not reject.”
- 06The scorecard
58 of 100: real enough to study, staged
Readiness checkerTwelve readiness checks and six tariff checks, each cited to its document and page. Site control: a purchase option on the parcel that expires before the facilities study ends. Financial security: a $20.0M letter of credit against $65.7M needed for 300 MW, or $26.3M for a 120 MW first stage. Backup generation: 24 × 2.5 MW diesel sets, air permit not filed.
“Real enough to study as a staged request, not as 300 MW in 2028.”
- 07Tariff terms
The large-load tariff applied line by line, for the staged offer
Regulatory and tariff analystEligible at 300 MW against the 75 MW threshold; study deposit of $450,000 received; billing demand floor 80 % of contract capacity at $11.40 per kW-month, a $1.09M minimum bill a month for stage 1. Security is 24 months of minimum bills because the guarantor is not rated investment grade: $26.3M before stage 1, so the developer is $6.3M short. The tariff analyst confirms the terms.
“Staging cuts the security needed now from $65.7M to $26.3M; the rest is due 90 days before each later stage.”
- 08Signed
The planner signs the staged offer
Senior transmission planning engineerThe account manager sends the staged offer to the planner with its basis, the 2028 summer peak case rev. 3 (N-1) and the capital plan, and a note: the developer asks 300 MW by Q4 2028; the substation has 120 MW. The planner signs. The signature reserves no capacity by itself: stage 1 is reserved when $26.3M of security is in place.
Only megawatts shown in the planning case go into the offer.
- 09Missing evidence
Four items, each with the clause that asks for it
Large-load account managerThe study agreement drafter has written the letter to the developer's project director from the short and pending checks: site control through the end of the study, security of $26.3M for stage 1, an explanation of the request to another utility, and the air permit application for the backup generators, with a reply due in 30 days. The account manager reviews it and sends it.
“Drafted by the study agreement drafter · the account manager reviews and sends · agents do not write to a developer.”
- 10Approved
A study agreement for the staged scope, three signatures in order
Director, grid connectionsThe facilities study agreement is drafted from the utility's template and the signed offer, with each clause that differs from the request marked: 300 MW by Q4 2028 becomes 120 MW in Q2 2028, 240 MW in Q3 2029 and 300 MW in Q3 2030; security before reservation falls from $65.7M to $26.3M. The planner signed first, the tariff analyst confirmed the terms, and the director approves.
“This agreement reserves no capacity by itself.”