- Before
- Carries 14 open requests for 3,855 MW, with a developer on the phone every hour asking “when?”, and chases missing documents by email.
- Now
- Screens a complete request in one click, sees who is real by readiness score, and sends a letter where every missing item cites its clause.
One 300 MW data-centre request, from the queue to a signed staged offer
Lumina Utilities carries 14 open large-load requests for 3,855 MW against a 6.4 GW system peak. On Tue 13 Oct 2026, Kestrel Bay Data Partners' request for 300 MW at Harrow Ridge 230 kV — complete since 9 Oct — is next to screen. Here is what happens, screen by screen, in the working solution.
- 01Morning
Fourteen requests, 3,855 MW asked — 875 MW ready
Amara Okafor · Large-load account managerAmara's queue is ranked by readiness, in queue order under Schedule LL-1 §4.3. Seven requests score 70 or more for 875 MW; 2,170 MW scores under 50, with no site control, no deposit or duplicates. LL-2026-041, Kestrel Bay's Harrow Ridge Campus, asks 300 MW by Q4 2028 and is waiting to be screened.
“Everyone wants 300 MW by 2028. I need to know who is real before planning spends a month on them.”
- 0210:02 · one click
The file read, checked and screened in about a minute
Six agentsAmara presses Screen request. The request reader takes 9 documents and 214 fields: 300 MW at Harrow Ridge 230 kV, ramp 60 → 150 → 300 MW by Q4 2028. The readiness checker finds 6 pass, 3 pending and 3 short. The duplicate detector and the tariff terms checker follow, then the headroom screener — each step logged with its time, from 10:02:06 to 10:03:15.
Readiness checker: “site option ends 31 Mar 2027; letter of credit $20.0M; no air permit for backup generators”
- 0310:03
180 MW short in 2028 — and a staged offer the network can serve
Headroom screenerOn the 2028 summer peak case, rev. 3 (N-1), Harrow Ridge has 120 MW for new load from Q2 2028, after the contracted Calder Valley Hydrogen load. The ramp is 30 MW above headroom in Q2 2028 and 180 MW short from Q4 2028, hatched red on the chart. The screener proposes three stages that follow the capital plan: 120 MW now, 240 MW with Harrow–Calder Line 2 in Q3 2029, 300 MW with autotransformer AT-2 in Q3 2030.
“The network cannot carry 300 MW in 2028. It can serve the ramp in three stages as the planned upgrades come in.”
- 04Why Harrow Ridge
The same request, re-screened at Calder
Headroom screenerClicking Calder 345 kV on the map re-screens the request there: 360 MW of headroom at the end of 2028, but 350 MW held by requests ahead, so 10 MW free — and 18 km of new 345 kV line to reach it. Ardent AI's 450 MW at Harrow Ridge is earlier in time but missed its site-control date on 29 Sep, so it holds no capacity. Kestrel Bay's own transformer order covers 180 MW in 2028.
“Kestrel Bay's own transformer order covers 180 MW in 2028: the 300 MW step is ahead of its hardware.”
- 05Duplicate check
Same parcel, same 300 MW, another utility
Duplicate detectorThe shared large-load register shows record CV-2026-0188: parcel HR-0417, 212 acres, 300 MW, filed with Corvane Electric Cooperative on 3 Aug 2026 — a 0.94 match against a threshold of 0.85. The two site outlines differ by less than 20 metres. Kestrel Bay's disclosure in Part 7 of the application says “none”. The detector recommends asking for an explanation and keeping the request in screening.
“The detector flags; it never rejects.”
- 06The scorecard
58 of 100 — real enough to study, staged
Readiness checkerTwelve readiness checks and six tariff checks, each cited to its document and page. Site control: a purchase option on parcel HR-0417 that expires 31 Mar 2027, before the facilities study ends. Financial security: a $20.0M letter of credit against $65.7M needed for 300 MW, or $26.3M for a 120 MW first stage. Backup generation: 24 × 2.5 MW diesel sets, air permit not filed.
“Real enough to study as a staged request, not as 300 MW in 2028.”
- 07Tariff terms
Schedule LL-1 applied line by line, for the staged offer
Priya Venkataraman · Regulatory and tariff analystEligible at 300 MW against the 75 MW threshold; study deposit of $450,000 received 2 Oct; billing demand floor 80 % of contract capacity at $11.40 per kW-month — a $1.09M minimum bill a month for stage 1. Security is 24 months of minimum bills because the guarantor is not rated investment grade: $26.3M before stage 1, so Kestrel Bay is $6.3M short. Priya confirms the terms.
“Staging cuts the security needed now from $65.7M to $26.3M; the rest is due 90 days before each later stage.”
- 0810:41 · signed
The planner signs the staged offer
Tomás Lindqvist · Senior transmission planning engineerAmara sends the staged offer to Tomás with the basis — the 2028 summer peak case rev. 3 (N-1) and the capital plan — and a note: Kestrel Bay asks 300 MW by Q4 2028; Harrow Ridge has 120 MW. Tomás signs at 10:41. His signature reserves no capacity by itself: stage 1 is reserved when $26.3M of security is in place.
“Don't promise a megawatt I haven't seen in the case.”
- 09Missing evidence
Four items, each with the clause that asks for it
Amara Okafor · Large-load account managerThe study agreement drafter has written the letter to Jonah Mercer, Kestrel Bay's project director, from the short and pending checks: site control through 30 Sep 2027, security of $26.3M for stage 1, an explanation of the request to another utility, and the air permit application for the backup generators — reply due Fri 13 Nov 2026. Amara reviews it and sends it herself.
“Drafted by the study agreement drafter · Amara reviews and sends · agents never write to a developer.”
- 1011:03 · approved
A study agreement for the staged scope, three signatures in order
Helen Strand · Director, Grid ConnectionsThe facilities study agreement is drafted from template SA-LL rev. 4 and the signed offer, with every clause that differs from the request marked: 300 MW by Q4 2028 becomes 120 MW in Q2 2028, 240 MW in Q3 2029 and 300 MW in Q3 2030; security before reservation falls from $65.7M to $26.3M. Tomás signed at 10:41, Priya confirmed the tariff terms at 10:52, and Helen approves at 11:03.
“This agreement reserves no capacity by itself.”