Large Load Interconnection Intake demo

Separate real megawatts from phantom load. 1:15

What the demo shows

A workflow solution for planners that screens data-center and large-load connection requests.

Six agents read every large-load request file, score its readiness, look for the same site asked of another utility and apply the large-load tariff. Then the request is drawn on a map of the network: its ramp schedule is plotted against the substation's headroom over time, with the planned upgrades marked. Where the ramp outruns the network, the headroom screener proposes a staged ramp the network can serve now, recalculates the security for it and sends it to the transmission planner to sign. The tariff analyst confirms the terms; the account manager sends the study agreement and the missing-evidence letter.

Transcript

  1. Large Load Interconnection Intake screens data center and Large Load Request for planners.
  2. Developers ask for hundreds of megawatts, often at several utilities at once.
  3. Kestrel Bay wants 300 megawatts at Harrow Ridge by late 2028.
  4. Amara runs the screening.
  5. Six agents read the file and check readiness and tariff.
  6. The same parcel was asked of another utility in August.
  7. The ramp exceeds Harrow Ridge's headroom by 180 megawatts in 2028.
  8. So the screener offers a staged ramp.
  9. 120 megawatts now, 300 after two upgrades.
  10. Tomas, the transmission planner, signs the staged offer.
  11. Real load is served two years sooner, and phantom load never reaches study.
  12. Built on Botminds: agents, data, screens, and governance on one platform.