One civils invoice, from the supplier portal to a settled notice
Brackwater Civils builds the Elm Vale Road LV reinforcement for Lumina Utilities under the Network Civils Framework, Lot 2. On Tue 13 Oct 2026 at 06:42 its September invoice arrives through the supplier portal: 16 lines, $204,436.00 before tax. Here is what happens next, screen by screen, in the working solution.
- 0106:51
The invoice opens already tied out
Leah Brennan · Contract administratorLeah checks 60-plus contractor invoices a month across four frameworks. BWC-2609-0418 opens on three columns: what the contract says, what the invoice claims and what the field shows, with each line wired to its rate on the left and its evidence on the right. Nine lines are matched, two are queried and five are held. Payable today: $178,879.00.
“I can check the rate. I can't check the 480 metres.” — Leah Brennan
- 0206:42–06:51
Nine minutes, every line checked
Seven agentsThe invoice reader takes the PDF from the supplier portal: 16 lines, totals agree, period September 2026. The rate checker maps every line to schedule of rates v3 and finds the clause 14.3 cap broken on line 10 and the clause 9.2 condition unmet on line 13. The field report reader adds up four handwritten site reports, 96 + 104 + 112 + 98 = 410 m. The duplicate and period checker compares nine earlier Brackwater invoices and finds line 3 already paid in August.
“Leah Brennan decides · 9 lines ready to approve · nothing is paid or sent until she does”
- 03Line 4
480 metres billed, 410 metres dug
Field quantity checkerBrackwater billed 480 m of footway trench at $186.50, the length of design rev B. Rev C, issued 3 Sep, stops the run at joint bay JB3 outside no. 41. The GPS as-laid survey measures 409.6 m from 164 points, the excavator track 411.2 m, and the crew's four daily reports 410 m. With a tolerance of 2% or 5 m, the most that can be paid is 418.2 m. The proposal: pay 410 m, $76,465.00, and short-pay 70 m, $13,055.00.
From the crew's own report of 10 Sep: “Route ends at JB3 per rev C.”
- 04Line 8
Six excavator days billed, four on hire
Plant and labour reconcilerThe 14 t excavator with operator is billed for 6 days at $1,240.00. Quarrell Plant Hire's telematics show 7.6, 8.2, 7.9 and 6.8 engine hours from 7 to 10 Sep, then 0.0 hours at the depot on 11 and 14 Sep. The machine was off-hired on 10 Sep at 18:10, and the foreman wrote “Ex 14t off hire 18:00”. Two days, $2,480.00, are held.
The ducts follow the trench: 2 × 410 m = 820 m, so 140 m of duct on line 6 is held too, $1,988.00.
- 05Lines 12 and 13
What needs a question, not a hold
Rate checkerClause 9.2 pays the night working uplift only where the Employer has instructed it in writing before the shift. No instruction is on file, and road permit RP-26-3318 allows working hours of 09:30–15:30 only, so three shifts, $3,540.00, are queried. On line 12, three weekly sheets are signed for 38 of the 46 overtime hours; the 8 hours on Sat 12 Sep have no signature, so $1,056.00 is queried.
On line 12: “ask Brackwater for the signed sheet, or Samir to confirm.”
- 06Decided
Sixteen lines decided, each by name
Leah Brennan · Contract administratorLeah accepts the proposals: 9 lines approved, 5 short-paid ($20,961.00) and 2 queried ($4,596.00). Each line now carries its decision, and line 4 reads “Short-paid by Leah Brennan · $13,055.00 to the notice”, with Undo beside it. She could query line 4 instead, or pay any line as billed with a reason that goes to the audit trail.
16 of 16 lines decided · payable after decisions $178,879.00 · AP run Thu 15 Oct · paid 12 Nov on 30-day terms.
- 0707:20
The notice goes with its proof
Query writerThe query writer has drafted the payment notice under clause 22.4, addressed to Gareth Pell, Brackwater's commercial manager. Each of the seven disputed lines lists the evidence attached: the paid August invoice and the road permit, the GPS survey, excavator telematics, daily field report and design revision C, the contract and the supplier invoices, the timesheets. Leah reads it and sends it at 07:20.
“Undisputed amount $178,879.00 is released to AP today and paid on 12 Nov.”
- 0811:05
The contractor agrees, from the supplier portal
Gareth Pell · Commercial manager, Brackwater CivilsGareth replies in the supplier portal: “Lines 3, 4, 6, 8 and 10: agreed, credit note to follow. Line 12: signed sheet for Sat 12 Sep attached. Line 13: withdrawn, the night shifts were our choice.” The query writer reads the reply: $24,501.00 agreed, and the signed sheet for line 12 matches Samir Haddad's diary. Releasing the $1,056.00 waits for Leah's approval.
“If you're short-paying, show me the measurement.” — Gareth Pell, before the notice
- 09The ledger
Every dollar stopped, with what showed it
Victor Lindqvist · Internal audit managerThe recovered-overbilling ledger now stands at $833,401 stopped before payment this year, 2.00% of contractor invoice value, with $20,961.00 added today from Brackwater. By cause, quantities over field evidence lead at $333,303, then labour hours and plant days. Each entry opens its evidence, for internal audit's quarterly sample and the report to the board.
“Show me the evidence behind every dollar we stopped — and every one we paid.” — Victor Lindqvist
- 10The pattern
The third time to the design length
Leah Brennan · Contract administratorBrackwater's billing record shows the share of each invoice payable without a query or a hold: 98.4% in July, 94.1% in August, 87.5% in September, against a target of 98%. Trench billed to the design length rather than as-laid has happened three times: Hallam Way 22 m in June, Ferris Lane 31 m in August, Elm Vale Road 70 m in September. Below 95%, the contract manager raises it at the quarterly review.
Patterns that recur: handling on materials at 15%, cap 8% — August and September invoices.