- Before
- Builds the renewal program in spreadsheets from a GIS export and last year's list, and can tell the board which pipes are oldest but not which will break.
- Now
- Draws a project on the risk-colored map and sees breaks avoided, customer-hours avoided, cost and its rank while drawing.
Water main break prediction after one burst, through a signed program
On a Monday at a large utility, the capital planner for water distribution is building next year's renewal program for the capital review board, with a budget of $64M. This year's program was ranked by age. On Friday a cast-iron main burst under a shopping street. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0105:30–05:40
The overnight refresh rescores each main
Likelihood modellerThe Break matcher reads 3 new repair work orders. The Likelihood modeller refits the 10 cohort curves (1970s cast iron now has a median life to first break of 41 years, down from 42) and scores each main for next year from age, soil, pressure swings, traffic and each pipe's own break history. Each main is rescored, and the Project drafter re-ranks 24 candidate projects.
“Back-test on last year's breaks · Top 10% of mains held 58% of breaks · threshold 45% · passed, scores published”
- 02Friday 02:40
Friday's burst, matched to its pipe
Break matcherThe repair crew supervisor's report on the work order reads: circumferential crack on DN200 gray iron, wall heavily graphitized, water through six storefronts; two valves shut at 03:05, supply back at 10:00. 1,840 customers were without water for 7 h 20 min. The Break matcher places the break on the street, picks the DN200 main over a DN100 service main because the crew measured 218 mm outside diameter, and gives the match 0.94.
“Conflict: the next pipe east is recorded as ductile iron, but the crew's photo of the trench end shows the same cast iron”: sent to the network engineer to decide
- 03Morning
Which mains break next year
Capital plannerThe capital planner opens the network map. Each main is colored by its chance of a break next year, from under 2% to over 50%, with last month's breaks marked and the general hospital, a dialysis center and a high school on the map. The cast iron in the old town is the darkest red. The list beside it reads the burst main at 82%, its neighbor at 76% and a main on a nearby lane at 75%.
“The cast iron on this street burst on Friday. Draw around it to see what renewing it buys.”
- 04One click
Seventies cast iron breaks first, at 41
Capital plannerBeside the map are the survival curves for each pipe cohort, material by decade laid: the share of pipe length that has not broken, against age. The planner clicks Cast iron, 1970s and its pipes light up on the map. 186 km of it is in the network, it breaks 38 times per 100 km a year, and only 28% of its length is unbroken at 52 years.
“Cast iron, 1970s: 186 km · median life to first break 41 years · 38 breaks per 100 km a year”
- 05The pipe
Why 82%: each driver, with its weight
Likelihood modeller and Consequence scorerThe burst main is cast iron, DN200, 268 m, laid 1972. Its cohort baseline is multiplied by corrosive soil (×1.70), 14 pressure swings over 3 bar a day from a nearby pumping station (×1.60), 5 breaks in 36 months (×4.21), buses and trucks on an arterial road (×1.25) and its age past the cohort median (×1.18): 1.72 expected breaks next year. If it breaks, 1,840 customers lose water between its two valves, and the shops and basements along the street flood.
Consequence 4 of 5 · about $196,800 a break · risk $338,000 a year
- 0610:02
A project drawn, and what it buys
Capital plannerWith Trace pipes, the planner clicks junctions along three streets, and the route follows the mains. The panel counts up during the drawing: 2.4 km, $3.6M, 11 breaks avoided a year and 68,600 customer-hours without water avoided. It also feeds the general hospital, weighted ×3.
3.08 breaks avoided per $1M: rank #1 of 31, against 1.16 for next year's program and 0.34 for an oldest-first plan
- 07Saved as a project
Renew before the road is resurfaced
Coordination checkerSaved, the cast-iron renewal costs $3,580,480 at next year's open-cut unit rates, for 9 pipes. The Coordination checker reads the city roads department's resurfacing plan and the electric utility's cable program. One road is resurfaced in May next year, then closed to digging for five years: renewing first saves about $410,000 of reinstatement. On another street, an 11 kV cable replacement opens the road in March and April, so the trench can be shared.
“Drafted a joint-trench request for the electric utility. Not sent: waiting for the planner”
- 08The program
31 projects, ranked by what each dollar buys
Project drafterThe renewal projects are ranked by breaks avoided per $1M, with a line where the $64M budget runs out. 31 projects fit: 44.1 km of mains, 74 breaks avoided a year and 377,000 customer-hours avoided. Planners drew 7 of the candidates; the Project drafter proposed 24, each a contiguous run that can be built valve to valve under one street-works permit.
Projects below the $64M line wait for the following year.
- 09Same budget
The same $64M, three ways to choose the pipes
Capital plannerOldest first, as this year, renews 42.6 km and avoids 22 breaks a year. Most breaks first avoids 46. Risk removed per dollar avoids 74, and 377,000 customer-hours without water against 86,000. Over ten years at the same budget, network breaks in the tenth year fall to 117 against 181 for oldest first, and 357 with no renewal. At the sample utility's $82,000 all-in per break, the 52 more breaks avoided a year are worth about $4.3M.
“3.4× the breaks avoided for the same $64M.”
- 10Signed · 15:05
A cited board paper, signed for the board
Head of Water Asset ManagementThe Programme writer drafts the paper for the capital review board (recommendation, why the ranking changed, the largest project, the top six and the risks) with 6 citations to the scenario run, the back-test and the work order, and checks each total against the project list. The capital finance partner confirms the unit rates and phasing at 11:40, and the planner sends it at 11:52. The Head of Water Asset Management signs with the meaning “approved for the Capital Review Board”.
“Agents draft and check. Only the Head of Water Asset Management can approve the program, and only the board can release the budget.”