Turnaround data migration for two batches of job packs, gate to signature
A refinery is moving six turnarounds of records into a new turnaround management system: 418,930 documents in 42 batches. This morning the newest job packs reach the gate, and the batch before them waits on the client’s last sampled record.
demoThe refinery, the people, the records and the counts are sample data.
- 0108:00
One exchanger’s job pack, joined to the template with a rule on each line
Data migration leadFields read from the page sit on the left, the sample template’s work package fields on the right, and a rule chip on each line between them. 19 of 22 lines are signed. The mapping agent has three new proposals waiting, among them how to shorten long job titles at a word break, and it says what each would change before anyone approves.
- 0208:10
A cost center open on the ERP list stays as read; a retired one moves on
Data migration leadClicking the cost center line opens its rule. A cost center that is still open in the ERP stays as written on the page. A retired one moves to its successor only when the ERP list names one, and otherwise the record is held. The rule shows its version, the records it touches, who approved it and who checked it.
- 0309:12
The gate holds 472 records and writes nothing
Data migration leadTen fixed checks run over the newest job pack batch: 32,058 records. 31,586 would pass and 472 are held, and 0 are written. The largest group is 187 tags not in the live asset list, then 96 cost centers and 74 dates that cannot be told apart. The rework agent has already looked for a sourced fix on each held record.
- 04Rework
An old tag, copied from an older pack, mapped by the retagging register
Turnaround plannerOne held record opens beside its page. Its equipment tag is missing from the live asset list because the pack was copied from an older one and kept the old tag. A retagging register maps it to today’s tag, and the agent is 96% sure. The planner approves; the page itself never changes, and the fix waits for the migration lead’s second check.
- 05Lock and trial
28,699 of 28,699 accepted on a test copy, in 47 minutes, then rolled back
System implementation consultantThe previous turnaround’s job packs cleared the gate with 0 held. The file was locked and fingerprinted, and the whole batch went through a trial load on a test copy of the target, then came back out. Only then did the sampling agent draw 315 records, with the draw number and a limit of 7 wrong fixed at the draw.
- 06Spot check
Record 315 of 315, and its cost center lit at line 8 of page 1
Client data reviewerThe client’s reviewer is on the last sampled record: job pack JP-24-0417, the hydrocracker’s reactor effluent exchanger. She clicks the cost center and the scanned cover sheet opens with that line lit. The rule checked it is open on the ERP list, so it stays as read. The other cells already carry her marks, so she reads this one against the page and marks it right herself.
- 07Sign
2 wrong of 315 means no more than 2.0% wrong, with 95% confidence
Client data reviewerThe sign box states what she is agreeing to: 315 records, each cell checked against its page, 2 wrong against a limit of 7, and 0 wrong critical cells. That bounds this batch at about 570 wrong records. The 2 wrong and the 41 like them go out as a correction batch through the gate, so the locked file never changes.
- 08Reconcile
614,188 files in, 418,930 documents to migrate, each step counted
Data migration leadThe trail starts with the files that arrived, then subtracts what splitting, duplicates and retirements took out, ending at the documents that migrate. Beside it the target’s load log is held against the signed file, batch by batch, and a mismatch stays open until a person answers it. People’s time is shown as our estimate, with second checks and trial loads counted in.
- 09Board
Oldest turnaround first, and job packs before what points at them
Data migration leadThe board shows all 42 batches by document type and turnaround: loaded, signed, in progress or not started, and who each one waits on. Because the oldest turnaround goes first, a recurring pack links back to one already loaded. Within a turnaround, job packs load before work orders, take-offs and cost records that carry their key.