Clean, pull bundle and IRIS on one exchanger are one opening and one crew.
Turnaround scope development, from three requests to one job
A refinery is building the worklist for a turnaround of all 14 units. 9,418 requests have come in from six sources, and the list goes to the scope challenge in a little over two weeks.
demoAll units, names and request counts in this sitting are invented for the sample.
- 01Morning
Clean E2417, pull bundle E-2417A, IRIS 2417-A: one job
Scope coordinatorSix streams flow into the list: 4,126 from the maintenance backlog, 2,087 from inspection, 1,312 from operations, and the rest from plant changes, capital tie-ins and past deferrals. Where streams join, the real requests show. Three wordings from three sources land on one reactor effluent exchanger: one opening, one crew, one outage window.
- 02Morning
A coke drum asked for by inspection, maintenance and an old deferral
Scope coordinatorThe join works across sources and years. An external survey of a coke drum from inspection, bulge repairs from the maintenance backlog and a repair carried over from the last turnaround become one job. Each keeps its own words and source. 3,252 requests have been folded this way, leaving 6,166 distinct items.
- 03Morning
88% sure, under the line, because the agent had to fix the tag
Scope coordinatorThe job opens with all three requests as written. The operations request named no shell letter; the pressure drop log shows the rise on the A side only, so the tag fixer chose A and says why. IRIS needs clean tubes and this bundle is cleaned on the pad, so it is one opening. The pack’s test step must change.
- 0409:07
An inspection request inside a merge needs the inspection planner
Inspection plannerThe coordinator agrees the three are one job, with the reason: same equipment, same opening. Because one request is an inspection request, the merge cannot stand on his name alone. The inspection planner countersigns, and the IRIS request keeps its exact words on the item. Merges signed now stand at 1,643 of 2,318.
- 0509:12
A relief valve due four months after oil in, on nobody’s list
Scope coordinatorThe due-work scout reads due dates as well as requests. A relief valve on the same exchanger has a three-year test interval and falls due four months after oil in. The inspection list sent to this turnaround stops at oil in, and the maintenance plan raises its order 90 days ahead, so no source carried it. The next window is years away.
- 0609:16
The 38th item nobody asked for, and the list reaches 6,204
Scope managerThe coordinator adds the valve with a reason: it falls due before the next event and needs the unit down. The scope manager countersigns. It is the 38th item added that no request carried. Other proposals stay open or are left out with a reason, such as work that can be done on the running unit.
- 07Morning
History on each item, and 143 gaps left open for the records lead
Turnaround records leadThe history puller attaches past work orders, findings, hours and cost to each item from the turnaround records. 2,648 items are first-time jobs. Where it is not sure a record is the same equipment, under an old tag or a typed one, it leaves the gap open and asks the records lead to link it or say none match.
- 08Afternoon
6,204 items by equipment, each in clean words with its requests on it
Scope coordinatorThe worklist reads by unit and equipment: the job in clean words, how many requests it carries, and where it stands. Some merges still need a person, some sit in sampled batches, some wait for a second name. Nothing goes to the scope challenge until the gates on the freeze screen pass.