Power purchase agreement software on one contract year's settlement
A utility buys power from an 1,800 MW combined-cycle gas plant under a PPA changed by Amendment 2. Contract Year 4 has just ended. The plant has declared 95.3 % availability, against a 95.0 % guarantee. Here is what happens, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Tuesday morning
The clause list opens on the breach
Contract managerThe contract manager owns the utility's five PPAs. This plant's list holds 63 duties read from 214 pages. Each shows its contract limit, the measured value, a 12-month trend and the penalty or bonus so far. Clause 11.3 is open. It shows what the contract says, what the plant data shows and what follows.
“1 guarantee breached. $1,565,148 to recover. Notice due at the plant by the end of the month · 17 days.”
- 0206:10, replayed
Worked out again from plant data, step by step
Six agentsThe contract reader read the PPA, Schedules 6 and 7 and Amendment 2. It used Schedule 6 para 3.5 as amended. The plant data reconciler matched 8,760 hourly reports with the event log, dispatch log, meters and grid frequency. Four events differ. The availability calculator applied clauses 1.1 and 10.4 and Schedule 6 paras 3.5 and 3.7. Pressing Run again replays it. The figure falls from 95.3 % to 94.6 % and the penalty counts up.
“Schedule 7 para 2: 0.40 points × $3.0M · $1,200,000”
- 03Hour by hour
Each day of the contract year, and four events read differently
Plant data reconciler and availability calculatorThe availability page shows all 365 days of Contract Year 4 as a calendar. It marks available days, reduced output and faults as the plant coded them. It also shows the approved planned outage, hours dispatched but not delivered, recoded outages and late starts. Below are the four events the contract reads differently. They are a gas turbine trip, 612 hours dispatched but not delivered, an outage that ran past its window and 9 late starts. Together they add 61.3 equivalent hours.
Result, by the contract: 94.60 % · 473.0 of 8,760 hours unavailable · shortfall 0.40 points
- 04One afternoon, 14:20
Coded as a grid event, with no dispatch instruction behind it
Dispatch shift leadThe plant coded the gas turbine trip as a Grid System Event. Clause 1.1 needs one of two things for that. The grid operator must have told the plant to cut output, or the grid frequency must have left the 49.5 to 50.5 Hz range. The control center's dispatch log, kept by the dispatch shift lead, has no instruction to the plant from 12:00 to 24:00. Frequency stayed between 49.96 and 50.03 Hz. The plant's own log shows a fuel gas control valve failed closed at 14:20:07. Under the contract, it is a forced outage, a plant fault.
Plant event log: “14:20:07 fuel gas control valve position fault · 14:20:09 gas turbine trip, flame out”
- 05What if
The contract as a working calculator
Contract managerFor each disputed event, the contract manager can switch between the contract's reading and the producer's. Accepting the plant's coding of the trip alone gives 94.76 % and $731,963 of penalty. The month's deduction falls to $1,097,111. Only the contract manager may override a coding, and the reading goes back to the contract afterward.
“Each event is read with the contract wording as amended. Accept the plant's coding on any event to see what it would cost.”
- 06Invoice day
The month's invoice, line by line
Settlements analyst, FinanceThe invoice claims $78,527,388. The settlement checker works out each line again. A capacity test showed only 1,772 MW, and the retest passed 14 days into the month. So the capacity charge falls by $365,148 (28 MW × 14 days × $931.50). Energy matches the meters, fuel is billed at the agreed 6,950 kJ/kWh and 6 start-ups match the dispatch log. After the $1,200,000 set off under clause 18.6, the amount to pay is $76,962,240.
“The settlement checker never approves a payment. The settlements analyst in Finance approves, and the deductions go with their evidence.”
- 0706:14
The notice drafted under clause 11.3(d)
Notice drafterThe notice is drafted on the utility's letterhead, to the plant's Managing Director. It goes by courier and email, as clause 27.2 requires. Each paragraph has a note in the margin with its source: the amended Schedule 6, the hourly data, the event and dispatch logs. It encloses 14 exhibits. The clock shows 17 days until the notice must reach the plant.
“Contract year ended · clause 11.3(d): a late notice waives the claim”
- 08Before noon
Confirmed, reviewed, signed
Director, power purchasingThe contract manager confirms the calculation, and the audit trail records it. Legal review comes back with no changes at 10:58. The notice is over $1M, so the director signs it at 11:20. The signature needs a password and records what the signature means. Only then can the notice be sent.
Meaning of signature: “I approve this notice under clause 11.3(d)”
- 09Ready if disputed
The evidence file, before the plant replies
Dispute pack builderIf the plant disputes the figures, clause 29 gives 30 days for senior executives to meet. After that, an independent expert decides within 45 days. The file is already built. It holds a timeline, 14 exhibits each taken from a source record, the $1,565,148 at stake, and the strongest and weakest points. In Contract Year 3, the expert upheld the same reading of clause 10.4, and $640,000 was recovered.
Weakest point: “Late starts: 2 of 9 within 5 minutes of the limit”
- 10Next
Fuel use is inside its limit, and on watch
Availability calculatorHeat rate is how much fuel the plant burns for each unit of power. Clause 12.1 guarantees 6,950 kJ/kWh, with a 1.5 % band. The corrected measurement is 7,031 kJ/kWh, 1.17 % higher. So fuel is still paid at the contract rate, with no penalty. The list marks it Watch and offers to warn the contract manager before it crosses the band.
“At this drift the band is crossed in about 4 months.”