- Before
- Codes 60–70 events a quarter across 6 units and chases shift managers for what happened at 02:00. “The breaker tells me when. The log tells me why. I spend my week joining them.”
- Now
- Works a queue of events biggest lost energy first, each with the log lines, the work order and a proposed code with its reasons — and confirms or changes each one.
One forced outage, from the breaker to a checked quarter
Lumina Utilities runs six units, 1,700 MW: Harrow Point 1–4 (steam), Kestrel Bay CC 1 (combined cycle) and Brannock Solar. On Sunday 20 September 2026 at 02:47, Harrow Point 3's generator breaker opens on a waterwall tube leak. Three weeks later, with the Q3 file due on Monday 16 November, here is how that outage — and the rest of the quarter — gets coded, checked and signed, screen by screen, in the working solution.
- 01Tue 13 Oct, morning
The year on one strip, the quarter in one line
Ines Okafor · Availability analystInes codes the fleet's events. Each unit's 2026 is one strip of states — in service, planned, maintenance and forced outages, derates drawn by MW lost, reserve shutdown — with each row's equivalent availability and forced outage rate at the end. The Q3 bar reads 62 events, 55 coded, 3 checks to fix, 34 days left. The biggest uncoded block, first on the To code list, is Harrow Point 3.
“To code · Biggest lost energy first · every proposal waits for you”
- 0202:25 to 02:47, 20 Sep
The event built from the signals, the log pinned to its minutes
Event builderThe event builder turned the breaker and output signals into one event: Sun 20 Sep 02:47 to Wed 23 Sep 19:15, 88.5 h, 330 MW, 29,194 MWh. On the signal chart, feedwater minus steam flow climbs to +18 t/h — the leak shows 22 minutes before the breaker opens — and each shift log entry is pinned at its minute.
Limit: never invents a start or end time; signals that disagree go to the analyst.
- 03The agents read
What the control room wrote, and what the boilermakers repaired
Log reader and Work order matcherThe log reader picked out seven entries from 01:58. Sara Duarte at 02:31: “Feedwater flow 18 t/h above steam flow.” At 02:38: “Acoustic leak alarm ch 7, furnace front wall el. 38 m.” Joel Mbeki, shift manager, at 02:47: “Waterwall tube leak suspected, front wall.” The work order matcher linked WO-3-55812: tube 114 pinhole leak, tube 115 steam-cut, front wall, el. 38.2 m, radiography 100 % accepted.
Limit: the log reader quotes the log and never paraphrases a cause the log does not state.
- 04Code proposed
U1 · 1000 Waterwall (furnace wall) tube leaks, at 94 %
Cause coderThe cause coder proposes the type from the timing and the code from the failed part. The unit came off at once on the shift manager's order, so it is an immediate forced outage, U1. The code is 1000, citing the log and the work order, and it notes this is the third front-wall leak on the unit this year. Two alternatives are kept: 1040 Waterwall, fireside slagging or fouling at 4 %, and 1999 Boiler, miscellaneous at 2 %. The record already passes 9 of 9 checks.
“Pick one, or any code in the library; your choice and the reason are kept with the record.”
- 05One click
Ines confirms; the strip updates
Ines Okafor · Availability analystInes confirms U1 · 1000. The lens now shows the code on file, “Confirmed by you just now”. On the To code list, Harrow Point 3 is greyed out as coded by her, and the Q3 count falls to 6 left. Undo is beside the confirmation, and Next to code moves her to the next-biggest event.
“Filed into the Q3 record with its rationale. 6 left to code.”
- 06Outside the plant
A gas curtailment kept off the plant's record
Work order matcher and Cause coderKestrel Bay CC 1 lost 160 MW for 8.8 h on Tue 4 Aug. The log reader found Farah Quist's 12:58 entry: curtailment notice CN-2026-118 from Corran Gas Transmission, offtake pressure held at 24 bar from 13:15. There is no plant work order, so the matcher attached the supplier's notice instead. The proposal is D1 · 9130 Lack of fuel (outside plant control), at 88 % — and it still waits for Ines.
“Output was held by supplier gas pressure, not by plant equipment.”
- 07Nightly, 06:00
Twelve rules on every record before filing
Report checkerThe report checker ran the 12 rules from the reporting instructions and Lumina's coding rules on all 62 Q3 events: 8 of 12 pass. It caught three records. A 36 h maintenance extension on Harrow Point 1 was for a crack found during the outage, not in the scope. A Kestrel Bay gas-turbine flame-out on 23 Jul carries 4260, a steam turbine code; the cause coder proposes 5130 Gas turbine combustor. And an 18 MW Brannock tracker stow is under the 20 MW solar threshold.
Limit: the report checker proposes a fix for each failure and never changes a record on its own.
- 08The honest number
The extension recoded as a forced outage
Ines Okafor · Availability analystUnder rule ER-3, Ines recodes the Harrow Point 1 extension as U1 · 1400, with WO-1-40227 behind it. Rule 03 now passes — 9 of 12 — and the quarter has 8 left to clear. In the Q3 report, Harrow Point 1's forced outage rate moves from 0.4 % to 2.1 %, and the fleet's from 2.2 % to 2.4 %.
“Harrow Point 1’s Q3 forced outage rate rises; that is the honest number.”
- 09The report
The Q3 tables and the board summary, drafted for sign-off
Report writerThe report writer computes service, planned, maintenance, forced and reserve hours, equivalent availability, forced outage rate and forced MWh by unit: fleet equivalent availability 97.2 %, capacity-weighted. It drafts the board summary for Margit Halvorsen, the reporting lead. Send for sign-off stays blocked until every record is coded and passes all 12 checks.
“Every figure links to its events. Drafted by the report writer from the coded records; Margit Halvorsen signs.”
- 10The pattern
Three leaks, one problem
Callum Reyes · Performance engineerCoded to the failed part, Harrow Point 3's three waterwall leaks — 3 Mar, 14 Jun and 20 Sep — add up to 201.8 h and 66,610 MWh, the largest cause in the fleet. The tube map shows all three on the front wall within 2 m of each other, near burner row 3. Ines sends the pattern to Callum, who decides whether to survey the front wall at the November maintenance outage.
“Coded to the failed part, the three outages read as one problem, not three bad nights.”