- Before
- Codes 60–70 events a quarter across 6 units and chases shift managers for what happened at 02:00. The breaker gives the time, the log gives the reason, and the week goes on joining them.
- Now
- Works a queue of events, biggest lost energy first, each with the log lines, the work order and a proposed code with its reasons, and confirms or changes each one.
A waterwall tube leak at 02:47, coded and checked before the quarter closes
A utility runs six units: four steam units, one combined-cycle block and a solar plant. One Sunday at 02:47, the generator breaker on steam unit 3 opens on a waterwall tube leak. Three weeks later, with 34 days left before the Q3 file is due, here is how that outage, and the rest of the quarter, gets coded, checked and signed, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Three weeks later, morning
The year on one strip, the quarter in one line
Availability analystThe analyst codes the fleet's events. Each unit's year is one strip of states (in service, planned, maintenance and forced outages, derates drawn by MW lost, reserve shutdown) with each row's equivalent availability and forced outage rate at the end. The Q3 bar reads 62 events, 55 coded, 3 checks to fix, 34 days left. The biggest uncoded block, first on the To code list, is steam unit 3.
“To code · Biggest lost energy first · every proposal waits for you”
- 0202:25 to 02:47, the night of the trip
The event built from the signals, the log pinned to its minutes
Event builderThe event builder turned the breaker and output signals into one event: Sunday 02:47 to Wednesday 19:15, 88.5 h, 330 MW, 29,194 MWh. On the signal chart, feedwater minus steam flow climbs to +18 t/h, so the leak shows 22 minutes before the breaker opens, and each shift log entry is pinned at its minute.
Limit: no start or end time is invented; signals that disagree go to the analyst.
- 03The agents read
What the control room wrote, and what the boilermakers repaired
Log reader and Work order matcherThe log reader picked out seven entries from 01:58. A control-room operator at 02:31: “Feedwater flow 18 t/h above steam flow.” At 02:38: “Acoustic leak alarm ch 7, furnace front wall el. 38 m.” The shift manager at 02:47: “Waterwall tube leak suspected, front wall.” The work order matcher linked the repair work order: tube 114 pinhole leak, tube 115 steam-cut, front wall, el. 38.2 m, radiography 100 % accepted.
Limit: the log reader quotes the log and does not paraphrase a cause the log does not state.
- 04Code proposed
U1 · 1000 Waterwall (furnace wall) tube leaks, at 94 %
Cause coderThe cause coder proposes the type from the timing and the code from the failed part. The unit came off at once on the shift manager's order, so it is an immediate forced outage, U1. The code is 1000, citing the log and the work order, and it notes this is the third front-wall leak on the unit this year. Two alternatives are kept: 1040 Waterwall, fireside slagging or fouling at 4 %, and 1999 Boiler, miscellaneous at 2 %. The record already passes 9 of 9 checks.
“Pick one, or any code in the library; your choice and the reason are kept with the record.”
- 05One click
The analyst confirms; the strip updates
Availability analystThe analyst confirms U1 · 1000. The lens now shows the code on file, “Confirmed by you just now”. On the To code list, steam unit 3 is grayed out as coded, and the Q3 count falls to 6 left. Undo is beside the confirmation, and Next to code moves on to the next-biggest event.
“Filed into the Q3 record with its rationale. 6 left to code.”
- 06Outside the plant
A gas curtailment kept off the plant's record
Work order matcher and Cause coderThe combined-cycle block lost 160 MW for 8.8 h on a Tuesday in August. The log reader found the operator's 12:58 entry: a curtailment notice from the gas transmission company, offtake pressure held at 24 bar from 13:15. There is no plant work order, so the matcher attached the supplier's notice instead. The proposal is D1 · 9130 Lack of fuel (outside plant control), at 88 %, and it still waits for the analyst.
“Output was held by supplier gas pressure; no plant equipment failed.”
- 07Nightly, 06:00
Twelve rules on each record before filing
Report checkerThe report checker ran the 12 rules from the reporting instructions and the utility's coding rules on all 62 Q3 events: 8 of 12 pass. It caught three records. A 36 h maintenance extension on steam unit 1 was for a crack found during the outage, outside the original scope. A gas-turbine flame-out on the combined-cycle block carries 4260, a steam turbine code; the cause coder proposes 5130 Gas turbine combustor. And an 18 MW tracker stow at the solar plant is under the 20 MW solar threshold.
Limit: the report checker proposes a fix for each failure and never changes a record on its own.
- 08The honest number
The extension recoded as a forced outage
Availability analystUnder the extension rule, the analyst recodes the steam unit 1 extension as U1 · 1400, with its repair work order behind it. Rule 03 now passes, 9 of 12, and the quarter has 8 left to clear. In the Q3 report, steam unit 1's forced outage rate moves from 0.4 % to 2.1 %, and the fleet's from 2.2 % to 2.4 %.
“Steam unit 1’s Q3 forced outage rate rises; that is the honest number.”
- 09The report
The Q3 tables and the board summary, drafted for sign-off
Report writerThe report writer computes service, planned, maintenance, forced and reserve hours, equivalent availability, forced outage rate and forced MWh by unit: fleet equivalent availability 97.2 %, capacity-weighted. It drafts the board summary for the reporting lead. Send for sign-off stays blocked until each record is coded and passes all 12 checks.
“Each figure links to its events. Drafted by the report writer from the coded records; the reporting lead signs.”
- 10The pattern
Three leaks, one problem
Performance engineerCoded to the failed part, steam unit 3's three waterwall leaks, months apart, add up to 201.8 h and 66,610 MWh, the largest cause in the fleet: 38 % of the year's forced energy lost. The tube map shows all three on the front wall within 2 m of each other, near burner row 3. The analyst sends the pattern to the performance engineer, who decides whether to survey the front wall at the next maintenance outage.
“Coded to the failed part, the three outages read as one problem.”