- Before
- Starts at 07:00 with the overnight report across five units, reading deviations in kJ/kWh and percent. Then chases whichever looks biggest. Nothing is in alarm, and the fleet still burns an extra 8,800 GJ a day.
- Now
- Opens a loss tree priced in dollars a day, with the cause already tested and the fixes compared. Raises the work order from the same screen.
A fouled condenser, from the morning loss tree to an approved load window
A utility runs five units at two stations, with a sixth in planned outage, on gas at $17.60 per GJ. One is a 620 MW gas-fired reheat steam unit that also supplies extraction steam. Here is what happens on a Tuesday morning, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0107:10
The morning starts on a loss tree priced in fuel
Performance engineerThe performance engineer opens the loss tree for the overnight report. The steam unit's corrected net heat rate is 9,982 kJ/kWh against an expected 9,640. That is +342 kJ/kWh, or 3.5%, and $73,680 a day of fuel. The tree splits the gap into the turbine cycle and condenser ($56.7K a day) and the boiler ($16.4K). The most expensive loss comes first. At the top is condenser vacuum, 128 against 89 mbar(a), at $46,100 a day.
“$73,680 a day of fuel above the expected heat rate · 4,186 GJ of gas · 235 t CO2. Fix order by money, most expensive first.”
- 02One click
In alarm view, each node is green
Performance engineerThe same tree in alarm view shows 0 alarms on the unit, and each loss reads “In band”. Condenser pressure is 128 mbar(a), and its alarm is at 160. The HP heater 6 terminal temperature difference is 7.9 °C, with an alarm at 15. This is what the control room sees, and why nobody called the performance engineer.
“No alarm. 128 mbar(a) is inside its band. The alarm is at 160. What it burns is below.”
- 0305:00 to 05:06
Each unit corrected before anyone arrives
Data checker and Heat rate correctorOvernight, the Data checker read 2,184 tags for five units. It flagged the feedwater flow transmitter reading 0.8% high against the condensate flow balance. So it used condensate flow plus heater drains instead, and labeled the substitution. The Heat rate corrector then applied model v4.1. Load was 510 MW against 620, cooling water was warmer than design, extraction was 62 t/h and gas was 38.9 MJ/Sm³. Design heat rate is 9,367 kJ/kWh, and with corrections the expected value is 9,640.
The Data checker never fills a gap or replaces a value without labeling it.
- 04Replaying the weeks before
The day scrubber shows when the drift began
Performance engineerThe performance engineer drags the day scrubber back. Early in the drift, the unit was costing $24,340 a day and the condenser only $10,990, at 98 mbar(a). Pins on the scrubber come from the shift and maintenance logs. An intake screen trip let shell debris into the cooling water. Two days later, tube cleaning ball recovery fell to 38%. From there the condenser node grows each day.
“log: Tube cleaning ball recovery falls to 38%”
- 05Open the loss
Fouled tubes, with the other causes ruled out
Loss diagnosticianThe loss page plots condenser pressure against the expected pressure from the heat balance. It is corrected to the day's load and cooling water. The loss has cost $561K of fuel since the drift began. The Loss diagnostician tested four causes. Tube fouling is confirmed. Air in-leakage, low cooling water flow and instrument error are each ruled out, with the reading that rules them out.
“The intake screen tripped and let shell debris into the cooling water. Two days later the tube cleaning balls were no longer recovered (38%), so the tubes fouled with nothing to keep them clean.”
- 06The evidence
Eight readings, each linked to its source
Loss diagnosticianThe cleanliness factor by the HEI method is 66%, against 84% after the last clean. Terminal temperature difference is 9.8 °C against 4.1. Cooling water temperature rise is normal, at 9.6 °C against 9.4. Vacuum pump air flow is 14 kg/h, where normal is below 20. Condensate dissolved oxygen is 6 ppb. Tube cleaning ball recovery is 38%, where normal is above 90%.
The Loss diagnostician never states a cause without the tests that rule out the others.
- 07Run it again
Three ways to fix it, priced and compared
Action plannerThe performance engineer re-runs the diagnosis step by step and gets the same answer as at 05:05. The Action planner compares three options, at $215 a day per kJ/kWh on this unit. Restoring ball cleaning alone recovers $5,390 a day. A full clean at the next planned outage costs $31,000. But it lets the loss run another 132 days, about $6.4M. Cleaning half the condenser at a time while running recovers $38,780 a day for $59,400. It pays back in 1.5 days.
“Recommended: the best payback, and no outage.”
- 08Raise
The work order is drafted, and the engineer raises it
Performance engineerThe work order is ready for the maintenance planner. The tube cleaning contractor cleans the tubes half by half and repairs the ball recovery strainer, at its quoted price. A permit covers isolating water box A, then B. The load limit holds the unit at 400 MW from Thursday 22:00 to Friday 10:00, as two 6-hour blocks. The justification carries the cost, the cause and the payback.
“Drafted by the Action planner at 05:06. You raise it. Nothing is sent until you do.”
- 09Approved
Operations approves the 400 MW window
Operations managerRaising the work order asks the operations manager for the load window. The operations manager approves any fix that takes a unit below its dispatch. The window is approved, and the work order moves on. The performance engineer raised it and the operations manager approved the window. The maintenance planner schedules Thursday 22:00. The last step stays open until the saving is measured.
“Load window approved by the operations manager · Thu 22:00 to Fri 10:00 at 400 MW”
- 10In the register
The saving is measured before it counts
Savings verifierThe cleaning joins the action register, where each fix is ranked by what it recovers for what it costs. If all open actions were done, they would recover $81,840 a day. The Savings verifier counts a saving only on measured, steady data. For example, an offline compressor wash on a gas turbine at the combined-cycle block was forecast at 55 kJ/kWh and measured at 57. That is $18,300 a day, on ten days of steady data.
The Savings verifier never counts a saving before 3 days of steady data.