- Before
- Collects twelve decks by Tuesday 17:00, chases the late ones and writes Thursday's brief by hand — and everything is green until the week before go-live.
- Now
- Opens a wall where every workstream already carries the colour its evidence supports, decides the four that differ, and reviews a drafted brief.
Week 6 of Project Harbor, from twelve decks to a signed brief
Northwind Bio closed its $8.4B acquisition of Calderra Biosciences on Sep 1. It is Wednesday Oct 7 — Day 37 of 100, with the Wave 1 ERP go-live on Nov 2 and the steering committee on Thursday at 08:00. Here is the week, screen by screen, in the working solution.
- 01Wednesday morning
The workstream wall, with both colours
Lena Ortiz · IMO leadEleven of twelve reports arrived by the Tuesday 17:00 deadline. The leads reported 8 green and 3 amber; on their own evidence, 5 are green, 5 amber and 1 red. Four workstreams are flagged — IT & systems, Commercial, Regulatory and Legal & contracts — and four colours wait for her decision before the brief.
“Each card takes the colour its own plans, test results and deadlines support, not the colour in its report. Where they differ, it is flagged and you decide.”
- 02One click
“Re-check all reports”, workstream by workstream
The agentsEach workstream shows Checking while its report is read again and set against its own trackers. Where the evidence differs from the report, the workstream is flagged. Communications sent its deck at Wed 08:12, after the deadline, so it shows as late and waits to be read.
The same rule, playbook 4.3, is applied to every workstream.
- 038.6 seconds
IT says green. Its own plan says amber.
Evidence CheckerSam Patel's deck says “Overall status: green. ERP Wave 1 cutover remains on track for November 2.” The cutover plan shows three of eight critical-path tasks late — the customer master load, the open AR/AP conversion and the EDI link to the Memphis warehouse — with 4 working days of float to go-live. Mock cutover 2 matched 91.4% of 13,980 ship-to records against an exit criterion of 99.5%; the deck calls these “minor data issues”.
Playbook 4.3: “Two or more critical-path tasks late, or an exit criterion missed, with under 10 working days of float to the next go-live.”
- 04Her decision
Amber goes into the brief, and the risk is raised
Lena Ortiz · IMO leadShe can use the evidence colour, keep the lead's colour with a note for the committee, or ask Sam first. She chooses amber, with the note “Mock 2 missed its exit criterion; go/no-go Oct 20 with Nov 30 fallback.” The Risk Register Keeper adds R-019 — Wave 1 ERP cutover at risk, customer master below exit criterion.
“Your decision is recorded with your name and time.”
- 05Legal & contracts
Amber on the deck, red on the contract clock
Milestone WatcherHannah Osei reports amber: 12 of 31 change-of-control consents received. Clause 18.3 of the Ridgefield supply agreement lets the CMO terminate within 60 days after the change of control — that is Oct 31 — and the consent request has had no reply since Sep 4. Ridgefield is the only approved drug-product site for Corventa.
Playbook 4.3 red: “A go-live date, legal deadline or regulatory clock will be missed without a decision from the steering committee.”
- 06Synergies
$162.4M planned, $18.4M confirmed, three flags
Synergy Evidence ValidatorFifteen initiatives make up the Year-1 run-rate plan of $162.4M; $63.8M is evidenced or better and $18.4M is confirmed by Finance. The evidence check flags three: S-02 shares a contract with S-09, S-04's ERP licence exit depends on the Wave 1 cutover, and S-13 was marked Evidenced without a signed contract.
Playbook 6.2: a saving moves to Evidenced only with a signed contract or decision and an effective date.
- 07S-02 and S-09
The same $4.1M, claimed twice
Synergy Evidence ValidatorProcurement's CRO preferred-provider panel (S-02, $14.5M) and R&D's monitoring rate harmonisation (S-09, $6.2M) both draw on Brightline amendment 4, which cuts monitoring and site-management rates by 12%: $34.2M of monitoring spend × 12% = $4.1M in both claims. The proposal books it once, to S-02, because Procurement owns the contract; S-09 keeps $2.1M from in-house monitor rates.
“Year-1 plan restates from $162.4M to $158.3M.”
- 08Signed and countersigned
Proposed by the IMO, confirmed by Finance
Lena Ortiz and Omar HaddadLena signs with the meaning “I reviewed the cited evidence and propose this booking against the locked baseline.” Omar Haddad, the synergy controller, countersigns. S-02 is confirmed at $14.5M, S-09 is restated to $2.1M, and both are recorded in the audit trail.
No saving moves to Confirmed without Finance.
- 09The register
R-019 lands at the top, with its source
Risk Register KeeperR-019 is scored likelihood 4 × impact 5 = 20 and marked new today. The register now holds 13 open risks and issues, three of them scoring 15 or more — those go to the steering brief. Every one links the passage it came from. Only its owner, or the IMO lead on the owner's behalf, closes it.
- 10Thursday 08:00, drafted Wednesday
One page, every number cited, for the sponsor to approve
Steering Brief WriterThe brief leads with the integration amber on evidence — 5 workstreams amber and 1 red, where the leads' own reports show 3 amber and no red — and Wave 1 at risk. Colours not yet decided go in marked “proposed — not yet decided”. It asks the committee for three decisions: the Ridgefield consent, the Wave 1 go/no-go gate and a local entity in Brazil. Lena reviews it and sends it to Rebecca Lang, the sponsor, before it goes to the 9 committee members.
“Clean-team data from Project Lark is never used in this brief.”