Construction claims management on a 41-day event that moved the finish 12
A marine terminal expansion finished 147 days late, and the contractor’s final claim asks 112 days and $148.6M on 23 delay events. This is the day the owner’s side settles the largest one, with 15 days left on the response clock.
demoTerminal, companies, people, dates and dollars in this walk are sample data, made up for it.
- 0115 days left
112 days claimed, and a draft position of 52 before anyone signs
Contract claims leadThe ribbon draws the job in 14 windows, cut at the schedule updates, with the critical path as it really ran across the jetty, tanks, compressors, pipe rack and piping. Each delay event sits where it happened. The agents’ draft reads 52 days and $13.1M, not signed. Her next step is the compressor vendor data event, which counsel has to read first.
- 02The event
Drawings 41 days late, and only the first 12 moved the finish
Contract claims leadThe event file lines up what the record shows, each entry cited: the owner had to furnish certified compressor foundation drawings by a set date, and they arrived 41 days late. The compressor path held the finish for 12 of those days. Then inspection failed welds on rack modules, and the rack took the path. The draft is 12 days with money, $3,990,000.
- 03The decision
She cannot decide yet, because counsel has not read the notice point
Contract claims leadThe notice looks late: day 31 of 28 counted from the drawings’ due date, but day 28 counted from the minutes where the contractor said it would assess the effect. No agent calls a claim time barred. When the claims lead tries to agree 12 days, the screen stops her: the legal point is with counsel, and deciding now would settle it before he has read it.
- 04Counsel
Counsel reads the notice point, and his reading stays privileged
Legal counselCounsel sees the two counts and the owner’s own conduct: it acknowledged the notice and reserved rights without calling it late within the 14 days the clause allows. His choices are to keep the days and reserve rights, rely on a time bar, or ask back. He keeps the days. His reading is marked privileged and stays out of exports and the response.
- 05The decision
12 days with money, decided after counsel, with a reason
Contract claims leadWith both legal points read, the claims lead agrees the proposal: 12 days and $3,990,000, with the records and the windows as her reason. She cannot be the one who checks it. The event goes to the commercial manager, and the trail shows counsel read first.
- 06The check
The commercial manager must open three sources before she can sign
Commercial managerThe check panel lists what she must open herself: the two schedule updates that show the path leaving the compressors, and the notice letter. She opens each record herself, after the decision. Only when all three are opened does check and sign become live. An open by anyone else does not count for her.
- 07After
The event is signed, and the ribbon still reads draft
Commercial managerBack on the ribbon, under her own name, the event shows signed. The position stays a draft, 52 days and $13.1M before damages, until each event is decided and checked and the position itself is proposed and signed. The response clock still reads 15 days.