Construction change order management on a request for 486 added pipe supports
On a re-measured EPC contract for an offshore processing platform, the contractor asks $3,859,990 for pipe supports above the quantity in the basis of estimate. Here is how the owner’s team answers it, with 14 of its 30 days left.
demoThe contract, the platform, both companies and every amount are sample data.
- 01Morning
1,284 requests on one contract, 15 past the limit and 317 not priced
Contract engineerThe register holds every change request the contractor has raised: 512 signed, 268 found not to be a change, 62 withdrawn, 107 in review, 317 unpriced and 18 held as possible claims. Each priced request must be answered within 30 days, and 15 are already past it. The agents mark 3 as unsure, and 37 wait on the contract engineer.
- 0209:57
Not fixed scope, no instruction, and only partly design growth
Contract engineerThe entitlement tree walks the request through five questions, each answered from its clause. Supports are named in the scope exhibit, but the basis of estimate sets the quantity, so it is not fixed scope. No numbered instruction covers the extra supports. The basis of estimate carries 12 percent growth per family: 340 of the 486 added supports sit inside it.
- 0309:58
$2,720,000 already priced, and $1,139,990 owed at contract rates
Contract engineerNotice came on day 21 of 28, so it is on time. The nearest earlier change paid for scaffold only, and the agent finds no approved change that covers these supports. The walk ends in two leaves: 340 supports already priced inside the allowance, and 146 beyond it, owed at the schedule rates. Each family is measured on its own; allowances never net against each other.
- 0410:15
Six spring supports the agent called growth, at 71% sure
Contract engineerOn the split, line 4b holds six spring supports on a new header run. The agent counted them as design growth but marked its doubt: the title block is a poor scan. The stress isometric’s revision note, shown beside the line, says per a company instruction, so the contract engineer opens the instruction itself. It moved the heating medium header tie-in to another frame.
- 0510:21
She moves the line, owed rises to $1,268,990, and notice is asked again
Contract engineerShe moves line 4b to owed, naming the instruction as her reason. Owed rises to $1,268,990 and already priced falls to $2,591,000. The agents then ask the notice question again for that line: from the instruction’s date, notice came on day 77 of 28, but on day 21 from the isometric revision that first showed the supports.
- 0610:24
Priced 385 days after notice, against 60 days in the contract
Contract engineerThe request itself shows the contractor held pricing until the last batch of stress isometrics. What the agent took from it sits beside the letter: event, notice and priced dates, and a flag that pricing came 385 days after notice where the contract gives 60, or a written reason. The reason is on file.
- 0710:27
Each rate looked up in the schedule, and each sum done again
Cost engineerThe cost engineer sees each line’s asked rate beside the schedule rate, the amount and the result. No rate here is above the schedule, there is no escalation, and no time is asked. The sum for the five owed lines is $1,268,990. Confirm the price or send it back.
- 0810:30
The commercial manager rules on notice for one line before countersigning
Commercial managerCountersign waits for one decision. The commercial manager opens the instruction and the isometric herself, then rules on line 4b’s notice: on time from the revision that first showed the supports, or time barred, which would send the line back. Her ruling and what she opened go on the trail.
- 0910:42
The change order is drafted, and above $1,000,000 the director signs
Project directorThe draft answer agrees $1,268,990 at schedule rates, line by line, and lists the lines not accepted and why. The contract value now, and what this would add, sit beside it. Three signatures are already on it, from the contract engineer, the cost engineer and the commercial manager. The project director reads it and signs, sends it back, or rejects it.
- 1010:45
$2,591,000 stays in the lump sum
Project directorWalked again after signing, the tree ends where the people left it. The notice question reads on time, with the ruling’s reason, and the leaves read $2,591,000 already priced and the owed lines at contract rates. Change order and signatures sit one click away.