Operational readiness drill on the export compressor, day 12 after first gas
A new offshore central processing platform is 38 weeks from first gas. Its export compressors have not been drilled yet, because the maker’s spares list only just arrived. Here is the morning the asset manager runs the drill.
demoThe platform, the crews, the people and the dollars are sample data.
- 01Morning
2,146 items on one runway, and 188 land after first gas
Asset managerEach readiness item sits in its week, read from the date in its own record: training, procedures, spares, maintenance plans, contracts, systems and data, and safety. 586 have landed and 1,339 land before the line. 188 land after first gas, and 33 have no date at all. Next to his name, one next step: the first export compressor has not been drilled.
- 02The drill
A dry gas seal fails on day 12, and 3 of 6 links break
Asset managerHe picks the machine, its most likely failure from the maker’s data, and day 12, which falls in the second crew’s hitch. The agent walks six links: detection, spare, maintenance plan, procedure, qualified people and service contract. Detection, plan and procedure hold, each with its record. The spare, the people and the contract break.
- 03The spare
The seal cartridge is on order, promised nine weeks after first gas
Asset managerOpening the spare link shows the purchase order line itself: one tandem dry gas seal cartridge set, common to both compressors, ordered at a quoted 48 weeks and promised 9 weeks after first gas. On day 12 that is 51 days away. A tracker that counts on order as done would show this item as fine.
- 04The crew
Two technicians can change the seal, and both are on the other crew
Operations training leadCounted by crew, the picture changes. Dry gas seal change-out needs 2 qualified people per crew. The first crew has 2; the second crew, on board on day 12, has none. Two of its three technicians are booked on the maker’s course, which starts after first gas, and the third is not booked. Counted across the workforce, this would read as covered.
- 05The cost
55 days short on one export train, from the late spare alone
Asset managerThe cost box sets out its sum. Fifty-one days waiting for the spare plus four to change the seals is 55 days with export gas short by one of two trains, about $18.8M of sales pushed later at the sample gas price. It is labeled a sample estimate and leaves out what the two other breaks add.
- 06Assign
Each break gets an owner, a date and what closes it
Asset managerAssigning is his job, not the agent’s. He picks the maintenance readiness lead for the spare, a date six weeks before first gas, and what closes it: a promised date before first gas on the order, or an exchange cartridge on site. The owner must accept, and the link closes only when its record shows the proof and he signs it.
- 07Assign
The runway redraws, with each owner’s date before the line
Asset managerHe assigns the crew training to the training lead and the contract to the readiness manager. On the runway, each owner’s date now sits before first gas, joined by a dashed line to the item it fixes: the spare and the training after the line, the contract in the no-date bin. The items stay where they are until their records change; the runway never moves an item on a promise.
- 08Accept
The owner accepts, or sends it back with a reason
Maintenance readiness leadThe maintenance readiness lead opens the action in her own queue: what must land, where it stands today, the machines it covers, the due date and what closes it. She accepts. Sending back is the other choice. Either way it goes on the trail with her name.