- Sees
- The wall, the package read and the claims below the team’s score
- Signs
- Sends threads and drafts holds; never votes
Stage gate review of a $2.4 billion offshore development at its last gate
An oil development with 28 new wells, a wellhead platform and a processing platform comes to its last gate before the board’s investment decision. The team recommends Go. Here is the gate, from the morning read to the panel’s signatures.
demoThe field, the project team, the panel and every figure here are sample data.
- 01Morning
186 assumptions tied across the package, and three strings frayed
Gate coordinatorThe wall draws each key assumption on the left and the deliverables that use it on the right, one string for each use. Most agree. Five were re-tied after team replies. Three are frayed: the water cut in the design, the produced water design rate and the electrical peak load. All three come from one document, filed after the freeze.
- 02Morning
3,771 of 3,812 deliverables read, and the 41 that could not be are named
Gate coordinatorBy hand, reading the package is 1,906 hours at 30 minutes each, so panels sample. Here the agents read every deliverable they could open, discipline by discipline. The 18 files they could not open, process simulation and 3D model files among them, and 23 register entries with no file are listed, each with a button to ask for it. Nothing unread is guessed at.
- 03Morning
The team claims 201 criteria met, and the pages prove 168
Gate coordinatorEach square is one gate criterion, claimed on the top row and read on the bottom. The team says 201 met, 13 partly, none not met. The pages prove 168, with 23 partly, 18 not proved and 5 contradicted. Of 33 claims read below the team’s score, 28 were settled by replies and 5 stay open.
- 04Morning
35% water cut in the design, 58% by year six in the new forecast
Gate coordinatorPulling the water cut string lights every page it touches. The design basis, the heat and material balance and the basis of estimate all use 35%, the year-three figure. The reservoir forecast, reissued after the freeze and the first revision to run past the plateau, reaches 58% by year six.
- 05Morning
The water train takes 60,000 barrels a day, and the peak is 92,000
Gate coordinatorThe thread sets out the sum step by step. At year three the design gives about 60,000 b/d of water. At year six the forecast gives about 92,000. If water stays capped at the train’s rating, oil has to be choked back. The agent never picks the right value; the forecast’s owner does, so the thread goes to her first.
- 069:16 am
The subsurface lead opens her forecast and confirms it stands
Subsurface leadShe opens the reservoir forecast page herself and confirms it: 58% water cut by year six. Under the thread, the note changes: the forecast stands, and five claims need holds before the panel can sit on them.
- 079:18 am
Three holds drafted, each with an owner, a date and what it stops
Gate coordinatorThe holds come as drafts from the confirmed gaps: resize the produced water train, reprice the fix and restate the estimate class, recheck the power balance at peak water. Each names its owner and date, and what it stops: release of the record, the produced water package order, the generator set order. A draft stops nothing until the chair confirms it.
- 089:26 am
The chair opens each hold and confirms it
Gate panel chairThe independent panel chair opens each hold, reads its owner, date and the claims it covers, and confirms it. Below the holds, what they stop is checked where the work happens: the water package order and the generator set order now wait on their holds.
- 092:04 pm
Go becomes Go with Holds, in the chair’s own words
Gate panel chairAt the sitting the chair accepts the 41 unread deliverables by name and moves the recommendation from Go to Go with Holds. Her reason is typed in her own words: the water train is sized for year three, not the peak the forecast now shows. The record beside her still reads not yet decided; it takes her words when she signs as chair.
- 102:08 pm
A second panel member reads the record and signs
Independent panel memberThe second signature comes from an independent panel member, who opens the record before signing. The record now carries two signatures. Release to the board stays stopped while the three holds are open. The agents read and cite; they never vote.