- Before
- Opens 40–60 new packs a week, ticks a 14-item checklist by hand and phones installers. Mornings go on finding a missing stamp, and the feeder question waits for the engineer.
- Now
- Opens each pack already checked, with each gap on its page and the feeder answer beside it, and sends one notice with everything missing and the routes that fit.
A 2 MW solar-plus-storage pack with three gaps and a feeder 600 m north
The utility runs interconnection for one district: 3 substations, 9 feeders, 186 open applications. At 08:06 one morning, a solar installer submits a 2,000 kW solar and 1,000 kW / 2,000 kWh battery project for a cold storage warehouse. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0108:06
The queue map opens on capacity after the queue
DER interconnection coordinatorThe coordinator's home is the district's network drawn as a map: nine feeders colored by the capacity left after each queued application, each open application a numbered pin in queue order. The new pack waits in the tray: 2,000 kW solar plus battery on the site's feeder. The rail already shows that feeder: hosting capacity 4.6 MW, existing generation 2.1 MW, seven in the queue, 1.4 MW left.
“1.4 MW left after the queue of 7”: the number a hosting-capacity map alone does not show
- 02One click
Check and place: the pin drops and seven agents start
Application pack readerThe coordinator clicks Check and place. The pin drops onto the feeder at queue place 8, and the run plays in the rail. The application pack reader reads 10 documents, 25 pages (the form, single-line sheets E-1 and E-2, three spec sheets, site plan, site control document, insurance certificate and fee receipt) and records the page for each value it extracts.
Pack reader: marks anything unreadable for a person instead of guessing
- 0308:11 · 08:12
0.6 MW short on the site's feeder, and room 600 m north
Capacity screener and Connection finderThe capacity screener nets the queue: 4.6 MW hosting − 2.1 MW existing − 1.1 MW queued in 7 ahead = 1.4 MW left. The project asks 2.0 MW, so it is 0.6 MW short and 3 of 6 screens fail. The connection finder searches 4 feeders within 1 km and draws a dashed route on the map to a feeder 600 m north along the same road, with 3.0 MW free.
“Nearby feeder, 600 m north: 3.0 MW free · no upgrade” · Connection finder, 08:12
- 046 minutes after arrival
11 of 14 pass, and three gaps, each on its page
Completeness checker and Account and meter verifierThe pack opens with the form beside the 14-item checklist. The meter, the address and the 2,500 A service match the account. But the form names the business that occupies the site, while the account is held by the building owner's holding company, with no letter of authorization. Each item carries its evidence and page: Form p.1, Sheet E-1, Spec p.1.
Completeness checker: never marks an item complete without the evidence on the page
- 05Sheet E-1
The single-line shows 17 inverters where the form says 16
Completeness checkerThe single-line diagram carries a licensed professional engineer's stamp and signature, so that item passes. But sheet E-1 draws 17 inverters at 125 kW each, 2,125 kW AC, while the form says 2,000 kW from 16 inverters. The margin note says what fixes it: correct the single-line, or state an export limit of 2,000 kW.
“17 inverters × 125 kW = 2,125 kW AC. The form says 2,000 kW (16).”
- 06Spec p.1
The model family is on the list, but not this model or firmware
Equipment list matcherThe spec sheet is for an inverter on firmware 2.8, certified to UL 1741 SA and IEEE 1547-2003. The utility's approved equipment list, in its current revision, carries only the same model with a -B suffix on firmware 3.2 or later, listed to UL 1741 SB, IEEE 1547-2018 and IEEE 1547.1-2020. A suffix or a firmware difference is a mismatch; the matcher names the closest listed model.
Equipment list matcher: never accepts an unlisted model or firmware
- 07The upgrade route
Route C: stay on the site's feeder at 2 MW, and pay for it
Distribution planning engineerScreens and routes puts three routes side by side. Route C keeps the full 2,000 kW on the site's feeder: generation on the line section reaches 3.2 MW against a 15 % limit of 3.15 MW, and voltage rise at the connection is 2.6 % against 2.0 %. It fails 3 of 6 screens and needs a voltage regulator, 0.9 km of reconductoring and a supplemental review: an estimated $410,000 and 9–12 months.
“screening only: the engineer's study decides”
- 0808:24
The engineer chooses route B, the nearby feeder
Distribution planning engineerRoute B connects to the nearby feeder, 600 m north along the same road: 2.0 of 3.0 MW, a line extension estimated at $96,000 and 3–4 months, full export with no curtailment, and all 6 screens pass. Route A stays on the site's feeder with export held to 1,400 kW, using the battery for the midday surplus. The engineer chooses B, and the notice now recommends it and offers route A as well.
“Moving the connection 600 m avoids the $410,000 upgrade that route C needs, and keeps the full 2,000 kW export.”
- 0908:31
One notice with each gap, and where the project fits
DER interconnection coordinatorThe deficiency notice writer has drafted the letter in plain words: the account holder, the AC rating and the inverter model, each with what to send and its page, then “Where your project fits” with the two routes. The coordinator reads it and sends it to the developer at 08:31, 25 minutes after arrival, on day 0 of 10. The clock pauses and queue place 8 is kept.
“The notice writer drafts; only you can send. Sending pauses the clock and keeps queue place 8.”
- 10This week
46 of 46 inside the completeness clock
Manager, DER interconnectionThe manager owns the clocks. The Clocks screen counts business days on each one, paused while an application is with the applicant, with holidays from the utility's calendar: 46 of 46 answered inside the 10-day completeness clock, a median of 6 minutes from arrival to verdict, and 0 past any clock. The longest took 1.2 days, a hand-drawn single-line that the coordinator read in person.
Screening clock: 15 business days from complete, closest to the limit first