- Before
- Starts each day with a queue of scanned redlines and redraws 6 to 10 sheets by hand. Spends the day on someone else's pen strokes.
- Now
- Opens each sheet already laid over the map with its edits drafted. Accepts them one by one, and signs a version only after the checks pass.
As-built redline processing for one sheet, from depot scan to the control room's map
At the end of the week, a crew switched on an 11 kV cable extension for a new housing phase. It is fed from a primary substation. On the next Tuesday at 07:52, the depot scanned sheet 2 of 3 of the foreman's construction print. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
The queue, ranked by days since switch-on
GIS technicianThe technician posts network records for the depot. The queue holds 1,240 sheets, averaging 46 days from switch-on to the map. Of those, 113 are over 120 days, and the oldest has waited 214 days for a clearer scan. The agents read each sheet as soon as it is scanned. Of all the sheets, 1,186 are ready for a technician, 31 need a clearer scan and 23 wait for a missing sheet. The new cable extension, switched on 4 days ago, is first.
“Today: 1,240 sheets, 46 days on average from switch-on to the map. The oldest is 214 days.”
- 0207:52 · 2 min 40 s
Six agents read the sheet as soon as it is scanned
Sheet registrar, Redline reader and Edit drafterThe registrar lines up the 400 dpi scan with the map using 4 grid ticks, the curb lines and the ring main unit. The error is 0.6 m. The reader finds 11 marks, and reads 10 of them above 0.75 confidence. The drafter turns them into 9 proposed edits, each pen line snapped within 2.0 m. The design comparer finds 3 changes from design revision C. The closeout tracker sees sheet 3 of 3 is not scanned yet and reminds the foreman at 09:00.
Redline reader: “RMU way reads 3 or 5 (0.61), so you decide”
- 0309:14
The crew's print, laid over the network map
Crew foreman, underground cableThe foreman's red ink sits exactly over the street. The designed route on the south verge is crossed out, and a new one runs along the north verge: “ran N side 186m”. Other marks read “TX moved 14m E”, “JT @ 92m” and “LP NEW”. The overhead span is removed and its pole recovered. A slider fades between paper and map. Each mark has a number that matches an edit in the list beside the map.
The foreman's note on the sheet: “c/o gas main conflict, ran N side”
- 04Each mark
The sheet, read, with a confidence for each mark
Redline readerThe sheet view shows each mark the agents found, what they read and how confident they are. The joint reads at 0.88, the spare ducts at 0.81 and the transformer move at 0.97. The reason note and the foreman's signature and date are read too, and matched to the work order. Below 0.75, a person decides.
“11 marks · 9 edits · 1 reason note · 1 signature”
- 05One click
The shaky pen line becomes a clean cable
GIS technicianEdit 1 proposes a primary 11 kV cable, 3×1c 300 mm² Al XLPE. It runs 186 m against 172 m designed, from the ring main unit to the new transformer on the north verge, at 0.9 m depth. The route and length differ from the design. But they sit inside the +10 % rule and the sheet gives a reason, so they are recorded. The technician accepts. The line snaps onto the verge and joins the two assets it meets.
“Edit 1 accepted: the cable snaps to the ring main unit and the transformer”
- 06Read 0.61
Way 3 or way 5: the switching schedule says 3
Connectivity checker · the technician decidesThe foreman circled the ring main unit and wrote “fed way” with a digit that reads as 3 or 5. At 0.61 it is below the line, so the technician decides. The feeder's switching schedule shows way 3 spare and planned for the new transformer. Way 5 already feeds a neighboring ring. Recording way 5 would put two feeds on one way and fail the trace. The technician picks way 3, then accepts the checked edits in one go.
“Way 3 matches the switching schedule. Edit 9 accepted”
- 0709:15
The new link pillar, approved from the comparison
Design engineer, distributionThe Design vs as-built screen puts the design, the crew's redline and the work order's materials side by side. Of 8 items, 5 match. Two field changes are recorded inside the rules. The new link pillar is not on the design. The design comparer drafts the question, and the technician sends it. The materials agree with the pen: a 200 m drum issued, 186 m laid and 14 m returned.
The design engineer approves. Plot 23 moved off the overhead span, so the pillar replaces the pole supply. Revision D follows for the record.
- 08Before posting
The checks pass, then the technician signs
Connectivity checker · the technician signsThe posting package holds the 9 accepted edits as one version. The feeder trace runs from the primary substation through way 3 of the ring main unit and the 186 m cable to the new transformer. The neighboring ring is unchanged. There are no loose ends and no duplicates with sheet 1. All 9 features carry asset id, size, install date, crew and source mark. The technician signs with a statement.
“I checked each edit against the crew's redline and accept them as built.”
- 09Posted
The control room's map matches the street
Control-room operatorThe version is on the network map, and the control room is told. A new 11 kV cable runs from way 3 of the ring main unit to the 500 kVA transformer on the north verge. It was switched on at the end of the week. There is a new link pillar, and the overhead span is removed. Switching diagrams for the feeder update at posting. The map caught up 4 days after switch-on.
A “map change” notice, naming the feeder and its assets, goes to the control room on shift, the outage desk and depot planning
- 10Closeout
The work order moves toward closed
Construction closeout coordinatorThe work order is $412,600 of construction work in progress. It moves from “Redline in · map not posted” to “Map posted · materials to reconcile”, and sheet 3 of 3 is still to come. Across the sample utility, finished work worth millions waits on as-builts. The closeout tracker shows why. There are 87 jobs built with no redline scanned, and 447 read and waiting for a technician. There are also 31 open design questions, 29 contractor packages sent back and 17 scans too poor to read.
By our estimate from the sample inputs, finished work waiting on as-builts moves onto the books as working equipment about 6 weeks sooner. Only the coordinator closes a work order.