Well program review that proves whether each hazard from the offset wells reached a step in the program, and leaves each section's signature to the technical authority.

Follow the dangling G30 hazard to a signed section ↓
The problem

Offset well hazards that never reach a step in the program

A drilling program runs to hundreds of pages, and the offset study behind it to thousands of daily reports. The people who sign it have days, so they read the summary and the sections they know are risky.

A lost-circulation event in a depleted sand can sit in one offset's report, get a line in the summary, and still never become a step. When a revision lands, the review starts over, and sections already signed get read again from the top.

Built forDrilling engineersDrilling technical authoritiesWell control specialistsSubsurface leadsAssurance reviewers

The Problem Today

A long program is checked by a few busy people, and nobody can prove each offset hazard reached a step.

0.5 ppg
Offshore rule: mud this far under the fracture gradient published

Checked by hand today

  • Programs
  • Offsets
  • Standards
  • Sums
  • Offsets read by summaryThousands of reports, and few are read in full
  • One change, full restartA new revision reopens signed sections

The Solution

  1. Read everythingThe whole program and each offset daily report, handwriting included
  2. Trace by depthEach event lined up by formation and joined to the step dealing with it
  3. Do the sumsMargins and kick tolerance redone against what the offsets saw
  4. Send what is openHazards with no step, and deviations, are routed to a named owner

Built-in controls

  • Each new step is checked by someone else
  • Agents never write into the program
  • A section is signed on one revision only

What You Get

Technical authorities sign sections knowing which hazards reached a step, and which still wait on a person.

422
hours to read the sample's offset reports, three minutes each our estimate
$300K
for one offset's 20 lost hours, at a sample rig day our estimate
  • Dangling hazards in plain viewA hazard with no step shows as a loose line
  • Sums redone against the offsetsMargins and kick tolerance from what the wells saw
  • Signed section by sectionA change reopens only the section it touches
One revision, one dangling line

A well program review of 14-153: the G30 sand nobody planned for

An extended reach well, a 380-page program and 18 offset wells chosen by rock. Most hazards trace cleanly to a step. Three do not.

demoThe well, its offsets, the people and the program are sample data, including the depths.

  1. 01Review

    88 hazards from 18 offset wells; 85 reach a step and 3 dangle

    Drilling engineer

    A depth scale runs down the middle: each event from an offset well on the left, the program's sections on the right, and a line from each event to the step that deals with it. Three lines end in the middle of the screen. The engineer starts with the one in his own section.

  2. 02Review

    380 bbl lost in the depleted G30 sand, and no step covers it

    Drilling engineer

    The hazard page quotes the offset's drilling report: lost returns at 7,640 ft with 10.6 ppg mud, two LCM pills, losses cured after 11 hours. Five reports from four wells say the same. The sum beside them puts the program's mud 0.4 ppg over the loss point, against a company limit of 0.5 under it.

  3. 03Review

    He drafts step 3.9: drill the G30 at 10.4 ppg and test it to 11.8

    Drilling engineer

    He starts the step from the agents' facts, then sets the test himself. In the new step the G30 is drilled first, strengthened, and tested to 11.8 ppg before the J shale. With the G30 as the weak point, kick tolerance works out at 41 bbl. Nothing goes into the program until he adds it under his own name.

  4. 04Review

    Added to Rev D, and the line now waits for someone else to check it

    Drilling engineer

    Back on the trace, the G30 line runs to step 3.9 and the counter reads 85 connected, 1 to check. The engineer cannot check his own step. The next step bar names who it waits for: the well control specialist.

  5. 05Check

    The specialist agrees the new step covers the hazard

    Well control specialist

    He opens the hazard page, reads the engineer's step against the offset reports and the sum, and agrees with a stated reason: it covers the hazard. The page now reads connected, checked, with the step quoted beside the passages it answers.

  6. 06Sign-off

    She agrees the link herself before it can count in her section

    Drilling technical authority

    The technical authority opens the same hazard and agrees the link in her own name. New and changed links come first in the sample she must open, so a fresh step is never waved through on the specialist's check alone.

  7. 07Sign-off

    The margin breaks the standard, so it is a deviation with a condition

    Drilling technical authority

    The mud still sits over the G30's loss point, so DV-1 goes to her as a deviation. She accepts it with a condition: the rig stops if the test fails. With DV-1 and DV-4 both accepted with conditions and all six sampled links agreed, nothing stops Section 3.

  8. 08Sign-off

    Section 3 signed on Rev D, after opening 6 sampled links

    Drilling technical authority

    Her signature belongs to one section on one revision. Sections 1 and 5 still have hazards to clear, and the release of Rev D to the rig needs every section signed plus the well control specialist's concurrence. A later change to Section 3 would withdraw the release.

  9. 09Sign-off

    86 of 88 now reach a step; the last two wait on named people

    Drilling technical authority

    The trace shows what is left: a shallow gas-cut flow waiting on the well control specialist and a hydrogen sulfide reading on the subsurface lead's desk, each with a due date. No section holding one of them can be signed until it is answered.

The G30 sum, from the offset reports to the program's mud

The standards checker redoes the sum from the reports, not from the summary.

CheckValue
G30 pressure, from the 10.6 ppg mud and 1,400 psi overbalance7.1 ppg
Loss point, returns lost on the offsets10.5 ppg
Program mud for the J shale, same open hole10.7 to 10.9 ppg
Margin under the loss point, company limit 0.5 ppg-0.4 ppg
Overbalance on the sand at 10.9 ppg1,510 psi

demoSample data, from the working solution. The mud the J shale needs breaks the G30, so the new step tests the sand to 11.8 ppg before the shale is drilled.

Around the sign-off

Offsets, standards and design basis behind well design assurance

The rest of what the engineer, the specialist and the authority read before a revision goes to the rig.

All 88 hazardsOne row per event in an offset well, with the report, the depth reported and as lined up on the new well, the formation, the step and its state.
18 offset wellsChosen by rock, not distance, in the signed offset study. 8,445 reports of seven kinds, with thin and handwritten files marked.
The program, Rev D380 pages read into 31 steps by section, with the hazards that end at each step listed beside it.
Design basisThe mud window against depth, as written and with the offsets, and each design sum redone: pressures, margins and kick tolerance.
Company standards40 rules checked: 34 pass and 6 raise deviations, each with a named signer. The standards text is the company's own copy.
Audit trailEach read, link, agreement and signature with its revision, kept for years after the well is abandoned. The record exports for assurance.

demoSample data, from the working solution.

Four people, and none of them checks their own step

Each reads a different part first.

Drilling engineer
Sees
Dangling hazards and the sums against his program
Signs
Adds steps; never checks them
Well control specialist
Sees
New steps on kicks, losses and well control
Signs
Checks each change and concurs with the release
Subsurface lead
Sees
Pressure and fluid hazards from the offsets
Signs
Answers the hazards routed to the subsurface
Drilling technical authority
Sees
A sample of links, new ones first, and each deviation
Signs
Agrees links, accepts deviations, signs each section on one revision
Who reads the program

Six agents read the program and the offsets, and none of them writes a step

They find, quote and redo sums. People write and sign.

Program reader

Reads the program's pages into its steps.

  • Never rewords a step
Offset reader

Reads the offset study's reports, handwriting too.

  • Never guesses a depth
  • Never reads silence as safe
Depth aligner

Lines events up by formation and rig floor height.

  • Never hides the raw depth
Hazard tracer

Quotes the step that deals with each hazard at that depth.

  • Never connects on a word match
  • Never writes into the program
Standards checker

Checks the company's rules and redoes the design sums.

  • Never waives a rule or accepts a deviation
Review router

Names the person for each open item and picks the sign-off sample.

  • Never signs
  • Never relaxes a sample

What technical authorities ask about well program review

What is a well program review?

A well program review checks a drilling program before it goes to the rig. This well program review traces each hazard from the offset wells to the step that deals with it, redoes the design sums, checks the company's standards, and leaves each open item and each section's signature to a named person.

Does it grade the program?

No. It shows whether each known hazard reached a step, quotes that step, and leaves loose any hazard with no step. Judging the plan stays with the engineer, the specialist and the technical authority.

Does it replace a well engineering peer review?

No. A peer review relies on the reviewers' reading. Here every offset report is read first, so the reviewers start from the hazards that have no step and the sums that break a standard.

What happens when a new revision is issued?

Only the sections a change touches reopen. A signed section stays signed on its revision, and a change to it withdraws the release.

Can the agents add a contingency to the program?

No. They gather the facts and the sum; the drilling engineer writes the step, someone else checks it, and the technical authority agrees the link.

Where do the offset wells come from?

From the signed offset study for the well, chosen by rock rather than distance. The review reads every report from those wells.