Failed 8 times on six rigs. Each time the crew kept circulating while the part came out, so the hours never showed as repair.
31.5 hours typed as circulating: one NPT analysis ruling, start to credit
A platform rig reaches section total depth at 9,870 ft and starts circulating the hole clean. Ninety minutes later the top drive faults, and the rig waits on a part from the shore base.
demoRigs, wells and contract terms are sample data, and so is each number.
- 01Review
As typed, 11.8% lost time; as read, 17.4%; signed so far, 14.2%
Drilling performance engineerThe year opens as the drilling team draws it: each well's days against depth, plan against actual. The engineer sees three numbers side by side and knows only the signed one counts. On 14-151 the actual curve took 58.9 days against a plan of 45.3, and the rings show where the rig called flat time normal work.
- 02Review
The proposal keeps the first 1.5 h as planned cleaning and calls 30.0 h repair
Drilling performance engineerTen report lines open with the marked ones in yellow, beside the agents' proposal: code 8 repair rig, lost rig equipment, 96% sure, with each step of the reading. Only the first 1.5 h stay as planned hole cleaning at section total depth. A contract box shows what a signed ruling would do, and says no agent decides who pays.
- 03Review
The company man and the contractor get the same ten lines
Drilling performance engineerThe engineer sends it to both sides at once. Each has five working days to answer, and the superintendent is told when a clock runs out. Sending the same evidence to both is what stops the usual argument, where the operator quotes the morning report and the contractor quotes its own tour sheet.
- 04Answers
The rig's own representative opens the marked lines and agrees
Company representativeThe company representative opens the 03:00 remark and the 06:00 tour line that puts the top drive back in service at 09:00. He agrees with 30.0 h as repair. His answer is one of two; it does not settle the hours on its own.
- 05Answers
The contractor disagrees once: 27.5 h, because some circulating was planned
Rig contractor managerThe contractor's manager opens the same lines and disagrees, picking planned work as the reason and putting the repair at 27.5 h. His point is fair on its face: circulating at total depth was in the program anyway. The disagreement goes to the superintendent with both answers side by side.
- 06Ruling
He rules 30.0 h: repair runs from fault to back in service
Drilling superintendentThe superintendent opens the lines and the contract clause, then settles it with a reason: the crew circulated one more bottoms up after the repair, so planned cleaning was not done inside it. Under the repair time clause, 12.0 h stay at the operating rate and 18.0 h fall to $0, a $111,000 credit.
- 07Ruling
The credit waits until the contractor acknowledges the ruling
Rig contractor managerA ruling that goes against the contractor does not reach the invoice on the operator's word alone. The contractor's manager acknowledges it here, or can dispute it under the contract instead. Only after his acknowledgement can the credit leave in a release, and the stretch shows signed.
- 08Ruling
March on Rig 2 now carries 18.0 h at $0 and a $111,000 credit
Contract auditorThe repair time ledger lists each rig and month with repair coded, found and signed, and what goes to $0. Signed rulings net $770,090 across the year so far. If every live proposal were signed as proposed, it would be $1,465,763, and the screen says plainly that this is no claim.