The supplier's process flow showed 220-4512 on the changed line. The letter's attachment did not.
A supplier change notification for titanium screws, gate by gate
A contract machinist moves passivation and final cleaning of screw components to a new finishing line at another site. The letter arrived at 17:40. The trace took under two minutes; the signatures took the next morning.
demoThe supplier, the screws, the people, the clearances and each figure shown are invented for the working solution: sample data.
- 0117:43
37 parts, 12 families, approval needed, 4 to revalidate, 11 filing actions
Supplier quality engineerThe letter sits on the left with its key passages cited. Six gates run to its right, each a question answered from the maker's own records: in our bills of material, which devices, does the agreement need our approval, which validations rest on the old line, is the biological evaluation touched, which filings. The next step bar says her decision waits for regulatory affairs.
- 0208:02
The letter lists 38 codes and leaves out a 7.3 mm cannulated blank
Supplier quality engineerOf the 38 item codes, 36 map to active part numbers and 2 point to inactive ones, so they are kept apart. The supplier's own process flow shows one more part, 220-4512, routed through the old line but missing from the letter's attachment. It is counted, marked process flow only, and added to the request for the supplier to confirm.
- 0308:05
Clause 7.2 needs 90 days' notice for a special process line; they gave 91
Supplier quality engineerThe signed quality agreement is quoted where it applies: a site or line change for passivation needs written notice and the maker's written approval before shipment. The notice period is worked out beside it, received to the first new-line lots, and it is on time. Clause 7.4 asks for validation evidence, or a plan with dates, which sets up the next gate.
- 0408:20
The new line was proven on solid screws; four cannulated families were not run
Validation engineerThe new line's validation covers solid screws from 1.5 to 6.5 mm. Read by geometry, the 3.0, 4.0, 6.5 and 7.3 mm cannulated families fall outside it, so they need revalidation before the change. Cleaning residues come due on 3 new-line lots for all 12 families, and the gamma dose rests on old-site bioburden, so a bioburden study and a dose audit are added.
- 0508:26
Same chemistry: 1 rationale to add to the biological evaluation, 0 new tests
Design quality engineerThe biological evaluation's basis is chemical characterization of screws processed on the old line. The chemistry and specification do not change, so the proposal is a rationale backed by residue results from the new line. Three risk file lines rest on these validations and hold if revalidation passes. Of 214 labels checked, none names the supplier's site.
- 0609:13
A letter to file for 4 clearances, a notified body notice, 6 markets to check
Regulatory affairs specialistThe filing assessment walks the change guidance step by step, each step cited, and reaches a letter to file for each clearance. For the European certificate it drafts a notice to the notified body and holds changed product from those markets until it approves. The country rules table flags 6 other markets. Her sign button waits until she opens the guidance and the annex.
- 0709:16
Signed letter to file; a design quality engineer checks it next
Regulatory affairs specialistWith both sources opened, she chooses letter to file as her conclusion and signs in her own name. The assessment now reads signed, waiting for the checker. Had she concluded a new submission was needed, a full-sentence reason would be required, the decision would reopen, and distribution in that market would be held.
- 0809:20
Accept on its own is not offered while four families wait for revalidation
Supplier quality engineerThe decision page sets out the six answers on the left and three choices on the right: accept, accept with conditions, reject. Plain accept is greyed out because gate 4 still owes revalidation. The follow-up keeper proposes two conditions, and the sign button stays shut until she opens the new-line validation and the quality agreement.
- 0909:23
Accepted with conditions, and three holds land at once
Supplier quality engineerHer signature records two conditions: the first 3 lots from the new line at full incoming inspection, and the revalidation report for the 4 cannulated families before the first shipment. The receiving block, the European hold and the sterile release hold apply straight away. Her acceptance takes effect only once the manager checks it.