Eleven days over 1,800 ppm, averaging 2,031.9, still leave every 30-day window under the limit.
Catalyst management on one claim: a performance guarantee with 21 days left
A hydrocracker’s second-stage reactor, three beds, a $9,600,000 load. Bed 3 reached its limit at month 41 of 48, and the vendor says eleven nitrogen days voided the guarantee.
demoSample data throughout: the refinery, its vendors, the staff and every number. The guarantee wording is sample wording.
- 01Morning
Bed 3 sits at its guarantee limit with 0 °F left at month 41
Process engineerThe reactor is drawn in section with each bed as loaded: product, lot, depth and weight. Bed 3 is amber, at its 785 °F limit from the guarantee test, and the unit now runs at 50,500 b/d under the technical manager’s dated decision. Beside it, the guarantee’s life: 1,254 days to the test, 1,210 on stream. The next step says the vendor calls the guarantee void.
- 02Morning
Eleven days over 1,800 ppm, and a vendor who declines any credit
Process engineerHe opens the vendor’s letter from the cut-away. Their review found total nitrogen above 1,800 ppm on 11 consecutive days, with a highest value of 2,194 ppm, and in their view that breaches the feed limit and voids the guarantee. The numbers are true. The question is whether they are the numbers the clause asks for.
- 03Morning
Clause 6.3 averages 30 days, and sets no limit on a single day
Guarantee readerThe agents read the letter clause by clause against the records and show each step: the load found, twelve clauses read, 1,209 daily results worked, the vendor’s letter compared, the due date set. Clause 6.3 reads a rolling 30-day average of daily laboratory results. One clause, temperature excursions, needs a person. Rulings stay with the engineer.
- 04Before ruling
The highest window comes to 1,743.3 ppm, 57 ppm under the limit
Process engineerThe test screen zooms on the summer’s daily results with the eleven high days marked, and moves a 30-day window across them. All 1,225 windows on the whole load are worked; the highest is 52,299 ÷ 30. One day has no result, and clause 6.4 carries the day before forward. Even at the worst value for that day, the average is 1,764.6 ppm.
- 05Before ruling
The trip report holds an 11-minute gap the vendor could raise
Process engineerClause 7.3 is not clean, and the agent says so. During a compressor trip the temperature log has no data for 11 minutes while the data server changed over. The control room hand log says 768 °F, and the alarm journal shows no high temperature alarm. He agrees there is no record above the line, and has the gap written into the letter.
- 06Midday
$9,600,000 × 7 ÷ 48 = $1,400,000, against the next supply
Process engineerThe claim shows the pro-rata sum with each figure cited: 48 guaranteed months, 41 used, the price of the load. Under it, what the vendor may say: still making product on it, only six whole months left, Bed 3 alone, the steeper climb. Lost production is not claimable under the letter. He proposes it, and it waits for the technical manager.
- 07Afternoon
Countersigned after opening the trip report, lab results, order and letter
Technical managerHer countersign stays disabled until she opens the four records herself. A ruling change clears her openings, so a changed letter has to be read again. Once she checks it, the panel shows the engineer’s proposal and her countersignature, and the claim moves to the contracts lead. She can send it back instead, with a reason.
- 08Afternoon
Sent inside the window, 21 days before it closed
Contracts leadHe opens the guarantee letter, the vendor’s letter and the letter as it stands, then sends. Sent inside the window, reads the panel, with the vendor’s answer due in 30 days, and a line says the agents sent nothing. Nothing on the screen says the vendor will pay; the claim stays disputed. A copy of the letter as sent downloads for his own file.