Material Supply Risk Management

Supply risk management that starts from each client program: agents join plan, stock and supplier confirmations, name the batches a material runs short for, and rehearse responses before a person signs.

See one supplier's reply traced to client batches ↓
Watch with transcript →
The problem

A supplier's longer lead time met a pull-forward, and nobody saw the gap

A client asks to pull batches forward for a launch. The same week, the supplier of a custom-color film coat confirms a longer lead time in an email reply. The material availability check still counts kilograms per material number, plans on the old lead time until someone retypes it, and says nothing about which client's batches lose the coating.

The gap surfaces months later, at dispensing, when only expediting is left. Meanwhile the same supplier's other colors, for other clients, carry the same longer lead time and nobody has looked at them.

Built forMaterials plannersSupply chain leadsBuyersSupplier quality specialists

The Problem Today

A shortage check counts kilograms per material number, so which client's batches lose a material surfaces only at dispensing.

Q9(R1)
ICH guideline adding product availability risk, 2023 published

Joined by hand each week

  • Plan
  • Stock
  • Orders
  • Emails
  • Lead times sent as emailsA supplier's new date waits until someone types it in
  • QC release days left outThe days a received lot waits for release are not in the shortage date

The Solution

  1. Plan, stock and orders joinedEach program's batches against released stock and usable deliveries
  2. Run-out counted kit by kitWhat the batch record dispenses, with held lots never counted
  3. Responses rehearsedEarly partial, re-sequence or second source, each with its sums
  4. Signed, then sent outThe supply chain lead signs the supplier request and the client alert

Built-in controls

  • Held lots never count as cover
  • Nobody approves a package they prepared
  • Outside free text waits for a person

What You Get

Each client hears of a shortage with a plan while there is still time to close the gap.

  • Pull-forwards answered with supply shownClient volume accepted with the material behind it
  • Clients see their own risksEach client's planner sees its programs, dates and the plan
  • A plan that rechecks itselfEach plan revision and supplier reply recomputes the run-outs
Features

Supply risk management features, from a supplier's reply to a client alert

A coating supplier confirms a longer lead time just as a client pulls batches forward, and planning, purchasing, the supply chain lead and the client each act on it.

demoThe contract plant, its clients and suppliers, the people, the lots and each quantity shown are sample data.

  1. 01Supply web

    Supply chain mapping from supplier to material to each client program

    • One strand per material and program. Line weight shows the share of a program's batches a material feeds, and a single-source material hangs on one thin strand.
    • Programs named, not material numbers. The banner names the client program short of a material and from which week, so the planner starts from the client's batches.
    • Each agent shown with its sources. Every agent's step, sources and confidence sit in the rail, so the planner can open the record behind any conclusion.
  2. 02Supplier reply

    Supplier lead time confirmations read from fixed fields, free text held

    • A new lead time read from its field. The confirmed lead time and delivery date come from the supplier's fixed fields, so the change reaches the plan without anyone retyping it.
    • A note held for the buyer. Anything the supplier types outside the fields is set aside unread by agents and blocks the request it concerns until a named person opens it.
  3. 03Run-out

    Material run-out date for a client program, counted kit by kit

    • Dispensed quantity, not the coat applied. The sum divides released stock by what the batch record dispenses, spray losses included, so the run-out matches what the dispensary weighs.
    • Release days added to each delivery. A delivery counts only from the day QC can release it, so a lot still in quarantine is not treated as cover too soon.
    • A held lot left to QA. Stock on QA hold is marked as depending on a QA decision and counted neither as cover nor as a gap, so the decision stays with the quality unit.
  4. 04Rehearsal

    Shortage responses rehearsed with kits short, client dates and approvals

    • Assumptions anyone can change. Kits pulled forward, partial quantity, arrival, QC release days and lead time can be edited, and each option recomputes at once.
    • A second source with its approval route. A new supplier for a client product is shown with the client's approval and any filing the client decides on, so it is not offered as a quick fix.
  5. 05Challenger

    Challenger that plays the client, an auditor and the supplier against the sums

    • The agents' sums held to the batch record. The challenger checks the other agents' arithmetic against the master record before any option is rehearsed, and marks what it fixed in the run.
    • Points a person must settle. Who approves a second source, and whether the supplier can be held to the agreed lead time, go to the named specialist and the buyer.
  6. 06Free-text note

    Supplier free text opened by the buyer before any request goes out

    • Read, then confirmed. The buyer opens the note and confirms it was read, which is logged, and only then can the response package be approved.
    • Asks answered in fields. If the note asks for something, the answer goes back as a request in fixed fields, so a conversation never moves a date by itself.
  7. 07Approval

    Response package approved by the supply chain lead with ID and password

    • Both drafts opened before signing. The supply chain lead opens the supplier request and the client alert and picks a reason code before the signature is enabled.
    • The preparer cannot approve. The materials planner prepares the package and cannot approve it; the supply chain lead signs with their own user ID and password.
    • Routine confirmations accepted by sample. Date confirmations that put no batch at risk wait below, and the ones the agents sampled must be opened before the rest are accepted together.
  8. 08Supplier portal

    Supplier portal where an early partial delivery is confirmed in fixed fields

    • Only the supplier's own orders. The supplier sees its purchase orders and the CDMO's requests addressed to it, with no view of the plan or of other suppliers.
    • Each answer recomputes the run-out. Quantity, ship date and the remaining delivery feed the sum, so a later remainder or a smaller partial shows as kits short at once.
  9. 09Client view

    Client supply view with each program's risk, the plan and the dates

    • An alert with the plan in it. The client's planner reads which batches were at risk, what was asked of the supplier and when the CDMO will confirm the answer.
    • Answers in fixed fields. Acknowledged, a request for a call, or accepting later dates if the partial fails: each is a field, and a typed message waits for a person.

Supplier quality gets single-source materials ranked by batches exposed

Planning prepares, purchasing reads what suppliers write, supplier quality owns second sources, and the supply chain lead signs what goes out.

Materials planners

Run the supply check on each plan change and prepare the response

  • Batches at risk named by program and week
  • Sums written out against the batch record
  • Responses rehearsed before they are proposed
Supply chain leads

Approve supplier commitments, client alerts and setting changes

  • One package to read, with both drafts
  • A reason code on each commitment
  • Settings that change only with approval
Buyers

Place and change purchase orders and read supplier notes

  • Lead-time changes read from fixed fields
  • Supplier free text held for them
  • The agreed lead time raised when it slips
Supplier quality specialists

Keep the approved supplier list and start second-source assessments

  • Single-source materials ranked by batches exposed
  • The client's approval route recorded first
  • Second sources started well before a gap

The agents' first count left 25 batches covered; the batch record said 21

The coat applied is not the coat dispensed

The first draft divided 272.4 kg by the 10.8 kg left on the tablets; the batch record dispenses 12.4 kg a kit, so 21 kits are covered and 4 are short.

One reply, five more programs

The 16 weeks apply to the supplier's other custom colors, so five more programs were rechecked and two order-by dates moved weeks earlier.

A held active lot, neither cover nor gap

8 December kits depend on QA's decision on a held active lot; the agents named the QC supervisor and the plant's QA head and counted nothing.

An order placed the day the lead time changed

The order went out the morning the 16 weeks began, so holding the supplier to the agreed 10 weeks went to the buyer, and the plan uses the confirmed date meanwhile.

demoSample data, from the working solution.

The client alert is built from fixed sentences and never names another client

Plan joiner

Joins the bill of materials, the plan revision, stock by status, open orders and supplier confirmations.

  • Never counts a held lot
  • Never edits the plan
Run-out calculator

Counts each program's dispensed need against usable stock and usable delivery dates, and names the kits with no material.

  • Never rounds stock up
Supplier chaser

Drafts structured requests, reads fixed-field replies and carries a supplier's change to its other materials.

  • Sends nothing without the supply chain lead's approval
  • Never acts on supplier free text
Response rehearser

Plays an early partial, a re-sequence and a second source forward with editable assumptions.

  • Never proposes a second source without the client's approval route
Challenger

Plays the client's planner, an auditor, the buyer and the supplier, and tests the sums the other agents drew up.

  • Never softens a point to close it
Client alert writer

Drafts the client alert from fixed sentences and the computed dates.

  • Never names another client, a supplier's price or an unapproved promise
More screens

About one material in five behind the client programs has a single supplier

The web before the run, the single-source register, the strand after the supplier answered, the counting rules and the record of who did what.

Before the run, nothing concludedThe last scheduled check found nothing at risk on the earlier plan; the supplier's reply and the new plan revision came after it, so the web waits for a run.
Single-source materials by exposure148 of 712 materials hang on one supplier, ranked by planned batches exposed, each with its second-source status and the client approval route it needs.
Covered, if the partial landsAfter the supplier confirmed 60.0 kg early in fixed fields, the coating strand reads covered if the partial lands, and stays watched until the lot is received and released.
Counting rules, locked where they must beHeld lots never count and a second source needs the client route, both locked; release days by material class, the horizon and the watch thresholds are proposed and approved.
Each send and signature on recordThe planner's choice, the buyer's opened note, the lead's approval, the request and alert sent, and the supplier's answer, each with what the signature meant.

demoSample data, from the working solution.

A held lot is never counted as cover, and that setting is locked

Counting a held lot as stockStock on QA hold shows as depending on QA's decision until the quality unit releases it.
A second source without the clientA new supplier for a client product starts from the approval route in its quality agreement, and the client decides whether a filing is needed.
Sending anything unsignedRequests and alerts go out only after the supply chain lead's signature, and whoever prepared the package cannot give it.
Acting on free textSupplier and client notes are held for a named person and block the action they concern until opened.
Ruling on held materialWhether a held lot can be used is for the QC supervisor and the plant's QA head; the agents name them and give no view.

Questions supply teams ask about supply risk management

What is supply risk management at a CDMO?

Supply risk management at a CDMO links each client program to the materials, suppliers and stock behind it, so a lead-time change or a pull-forward shows which client batches run short. Here agents recompute run-out dates on each plan revision and supplier reply, and people sign the response.

How does a material availability check differ from a run-out by program?

A material availability check gives a shortage date per material number. The run-out here counts each program's kits in dispensing order against released stock and usable deliveries, adds QC release days, and names the batches left without material.

Why does a single-source material need its own watch?

ICH Q9(R1) addresses product availability risks from quality and manufacturing issues, including a sole supplier of a critical material. The register ranks single-source materials by batches exposed and records the client's approval route before a second-source assessment starts.

Can a supplier's new lead time change the plan without a person?

The run-out, yes: the supplier's fixed fields recompute it at once, because the risk exists the moment the supplier confirms it. Anything the supplier writes as free text waits for the buyer, and commitments back to the supplier wait for the supply chain lead's signature.

Who decides whether held material can be used?

The quality unit. The QC supervisor and the plant's QA head decide on a lot on QA hold; the agents show which batches depend on that decision and keep the lot out of cover.

Pick the material
you worry about most.

Send one client program's plan, bill of materials and open orders, and we will map its supply and run-out dates.