- Before
- Issues and clears 15 to 25 permits a shift across 3 units, the water treatment trains and the 33 kV switchroom. The isolations are on separate sheets in another office.
- Now
- Sees each permit, lock and crew on the station drawing, and each request checked before signing. This is the last signature before anyone puts their hands in the plant. So the engineer sees the other permits on that equipment first.
A motor test blocked while four people work inside the pump it would turn
A combined-cycle station runs three generating units and four water treatment trains. It is a weekday, 09:14, on the day shift. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0109:14
The shift opens on the station drawing
Shift charge engineerThe shift charge engineer issues and clears each permit on the day shift. The board is the station mimic, a live drawing of the plant. It shows Unit 1, Unit 2 feedwater, Unit 3, the 6.6 kV unit board and the 33 kV switchroom. It also shows the water treatment trains, cooling-water intake and chlorination. Each isolation point is drawn as a lock and each live permit as a pin. The strip above reads 11 live permits, 28 people at work, 27 points locked, 4 requests and 1 held back.
Legend: “Held by a permit · Shared · common certificate · Proposed by a request · Free”. It sits on the station single-line drawing at its current revision
- 02Since 07:42
Four people inside a feed pump
Performing authority, pump contractorThe permit is for a mechanical seal replacement on a feed pump. Its isolation certificate holds five points, each proved by the authorized isolator before issue. The suction, discharge and recirculation valves are locked shut. The casing drain is locked open. The pump's 6.6 kV motor breaker is racked out, locked and earthed. The job is at step 7 of 9, laser alignment, with the coupling refitted and hands on the shaft.
Hazards: “Stored pressure and hot water · Rotating shaft and coupling · 6.6 kV motor supply · Manual handling of the seal cartridge (38 kg)”
- 0309:15 · Checks run
A test permit asks for the breaker back, and the board blocks it
Electrical maintenance leadThe maintenance lead raises a sanction for test, a permit to run a test. It covers an insulation-resistance test of the pump motor, then a 2-minute uncoupled run. The shift charge engineer runs the checks on the board. The isolation planner builds the test plan from the standard 6.6 kV motor plan. That plan removes the breaker isolation so the breaker can be racked to service. The conflict checker finds that point held by the seal permit. It draws the conflict on the diagram and blocks the request.
“A run would turn the shaft they are working on.” · No override on the board
- 04The decision
Two safe routes, and no third
Shift charge engineerThe request shows why. The work order assumes the motor is uncoupled, but the seal crew refitted the coupling at step 6. The engineer can re-plan the test for after the seal permit clears. Or the engineer can ask the maintenance lead to change the method to an insulation test only, from the switchboard, with the motor cable disconnected. Override is shown, and not available. The engineer re-plans the test for 15:45, linked to the seal permit. The breaker isolation stays in until both are closed, and the maintenance lead is told.
“Override · Not available · conflict rule 1, set by the HSE manager”
- 05Sharing a point
One valve, two permits, one common certificate
Conflict checkerTwo permits can share a point without a conflict. A high-pressure feed valve on one water treatment train is held by two permits. One is a high-pressure pump bearing change, with 3 people on. The other is a tank internal inspection, with 2 on. Both sit under one common isolation certificate. So the board shows the point as shared, and it cannot be removed until both permits are cleared.
“Common isolation certificate · cannot be removed until both permits are cleared”
- 0608:44
The drawing changed but the standard plan did not
Isolation plannerAnother request is an impeller inspection on a Unit 3 pump after a vibration alarm. The planner compares the standard isolation plan, revision C, with the current process drawing, revision F. Revision F was issued last month and added a bypass valve. The plan lacked it. So the planner adds it as a new isolation point and holds the request until an authorized isolator walks it down.
Limit: the isolation planner does not mark a point as isolated. Only an authorized isolator, in the field, proves it.
- 0708:33
An expired authorization holds the roof job
Competency checkerA roof fall-arrest anchor inspection is booked with an access contractor. The competency checker checks each named person against the permit type and today's date. One technician's working-at-height authorization expired at the end of last month. The request is held until another technician is named or the authorization is renewed.
“Working-at-height authorization expired · held by the competency checker at 08:33”
- 0809:16 to 09:18
Each lock proved in the field before issue
Authorized isolatorA strainer basket clean on another water treatment train passed all checks. No live permit holds its two isolation points, and the crew and isolator are authorized. The isolator locks both valves shut and proves each one. The proof is its lock number and zero pressure at the gauge behind it. Only then does the decision read “Isolations proved · ready to issue”.
“Both points are locked and tested. Your signature issues the permit. The performing authority then accepts it and signs the crew on.”
- 0909:19 · Signed
The engineer signs and issues the permit
Shift charge engineerThe issue screen shows the work, the area and the isolation certificate, with both points proved by the isolator. The permit is valid to 19:00, then revalidated at handover. The engineer signs with badge and PIN. The performing authority, who leads the crew, accepts on a device and signs 2 people on. The permit goes live on the board.
Agents check and block. Only people isolate, issue, accept and clear.
- 1019:00 handover
The night shift acknowledges each permit
Permit chain keeperThe permit chain keeper drafts the handover from the day shift to the incoming night-shift engineer. It lists what continues and must be revalidated, and what clears before 19:00. It flags the suspended heat recovery steam generator permit with its isolations in. It also flags the two confined spaces that need a gas re-test before re-entry, and the shared point. The incoming engineer must acknowledge each permit by 19:15.
“Feed pump: the seal permit holds five isolation points. The motor test is blocked on the breaker until the seal permit clears.”