WorkflowSupply Chain, Procurement & Finance

Construction Change Order Review

Construction change order review that asks whether anything is owed before it asks how much

See one case, screen by screen ↓
Watch with transcript →

Built forContract administratorsProject controls analystsCapital delivery headsInternal auditors

The Problem Today

Change orders get argued on price before anyone checks whether the work was owed, so work already in the contract gets paid for again.

48%
of change orders one city auditor checked had the wrong markup published
8-14%
of the original contract value is what change orders usually add published

Four records, kept in four places

  • Contract
  • Rates
  • Drawings
  • Site diary
  • Late notice goes unrecordedA missed notice limit is a lost defense
  • Audit sees a small sampleA few approved orders checked by hand, the rest never

The Solution

  1. Whether anything is owed, tested firstIs it a change, whose risk, was it instructed, was notice on time?
  2. Notice dated to the dayEvent, notice and details measured against the contract's notice limit
  3. Priced at contract ratesContract rates and the contract's all-in markup, matched to site quantities
  4. The administrator decidesReject, negotiate, approve or ask for details, in a response citing the contract

Built-in controls

  • Each verdict quotes its clause word for word
  • No agent rules a claim out as too late
  • Each check recorded, step by step

What You Get

Work the contract already covers gets paid for less often, and claims are answered inside their response window.

  • Overpayments found after approvalApproved change orders checked again with the same tests
  • Held back before paymentClaims not owed, or above contract rates or site quantities
  • Markups as the contract saysExtra supervision and insurance charges taken out
In short

What is Construction Change Order Review?

It is software that checks each contractor change order against the contract before it is paid. Construction Change Order Review first tests entitlement, meaning whether anything is owed. It asks if it is a change, who carries the design or the risk, if it was instructed and if notice came in time. Only then does it price the claim at the contract's own rates and markup. It matches the quantities to field records and drafts a response that cites the contract. The contract administrator decides and signs.

How to choose AI solutions for utilities →

Updated

The problem

Change orders get paid for work that was always in the contract

On a utility's capital project, a contractor can ask to be paid more because the work changed. That request is called a change order. It arrives as a PDF, a pricing spreadsheet and a covering letter. The contract administrator must answer it, and a 42-day response window is already running. The right first question is whether anything is owed at all. That takes four checks: was it a change, who carried the design or risk, did anyone instruct it, and was notice on time. Answering them means reading many documents, each kept somewhere else. The Employer's Requirements, the utility's description of the work, alone run to hundreds of pages. Then come the bill of quantities, the schedule of rates, the drawing register, the tender clarifications and the site diaries. So the quick thing gets done instead. Someone re-prices the quantities and negotiates the number.

That order is backwards. Work that was always in the contract can be negotiated down and still be paid for. Markups arrive at 15% plus supervision plus insurance, when the contract allows 10% all-in. New pay items go in with no pricing review. Nobody records that notice came after the 28-day limit, so that defense is lost. Internal audit can sample 20 approved change orders a year by hand, which says nothing about the rest.

typical48%of change orders a city auditor general reviewed had markups that did not follow the contract
typical8-14%of the original contract value is what change orders usually add across the industry
typical17of 18new pay items added by change order had no recorded price review, in one city's internal audit
Where a change order's response days goestimated
By hand27 days
With the solution3.2 days
  • Logging the request and reading the claim, letter and quotes2 → 0.1 d
  • Finding the clauses, the scope, the bill items and the drawing revisions8 → 0.5 d
  • Dating the event, the notice and the particulars2 → 0.1 d
  • Chasing quantities from daily reports, logs and surveys6 → 1 d
  • Pricing at the contract's own rates and markup5 → 0.5 d
  • Drafting, reviewing and signing the response4 → 1 d

Estimated split for one contested change order, in working days, by hand and with the solution.

How it works

Change order review, entitlement first and price second

What comes in
Claims in5 sources · requests, contract, rates, quotes, field records
Agents at work
Claim readerlines · dates
Then
Clause finder
Scope checker
Notice clock
Then
Field record matcher
Rate and markup checker
Then
Response writerevery clause cited
A person decides
Contract administratordecides and signs
What comes out
Entitlement verdict
Markup recalculated
Signed response
One case, step by step

A cable tray claim, checked for whether it is owed before it is priced

The sample utility is building a 132/11 kV substation. The contract is a $48.6M design-build EPC contract, so the contractor both designs and builds. Eleven days ago, the contractor sent a change order for $640,012. It asks to be paid for more cable trays in the 11 kV switchroom and cable basement. Here is what happens next, screen by screen, in the working solution.

A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.

  1. 01Morning

    The claim opens with a verdict before a price

    Contract administrator

    The contract administrator acts for the Engineer on two projects. They have 11 change orders open, each with 42 days to answer. The cable tray claim is on day 11 of 42. On the left is the claim as the contractor wrote it. The middle shows the entitlement tests, which check whether anything is owed. The right shows the cost check against contract rates. The overnight check ran from 06:38 to 06:47 and has already answered all four tests.

    Not entitled: “In the original scope. The contractor's own design change. No instruction. Notice 18 days late.” · Reject · $0 · recommendation · you decide

  2. 0206:38

    The claim as sent, with nothing priced yet

    Claim reader

    The claim reader lists what the contractor asked for. That is 1,860 m of 600 mm heavy-duty ladder tray at $182 and 1,240 supports at $64. It adds 1,150 hours of re-routing and pulling labor at $78 and a $17,020 scaffold lump sum. The direct cost comes to $524,600. On top come 15% overhead and profit, 5% supervision and 2% insurance and bonding. The contractor's letter says the trays follow “the revised cable routing on drawing … rev D”. The administrator can replay the check step by step. The cost column stays locked while the tests run.

    “Valuation waits for entitlement” · “Waiting for entitlement: the cost is checked only after the four tests are answered.”

  3. 03Test 1

    The trays were always part of the contract

    Scope checker

    Section 6.4.2 of the Employer's Requirements sits on page 214 of Part 6. It already requires “all cable trays, ladders, supports and fixings for the complete cable installation, including the 11 kV switchroom and the cable basement”. It also asks for 25% spare capacity. In the tender, the bill item for cable containment was priced at $1,118,400, “complete, lump sum”. A tender clarification confirmed the spare capacity is in that lump sum. Anyone can run the same search on the Scope screen.

    “Work the contract already describes is in the contract price unless an instruction changed it.”

  4. 04Tests 2 and 3

    The contractor's own design, and no instruction to change the work

    Scope checker and Clause finder

    Rev D was issued by the contractor's own design team, on its own transmittal. The utility's requirements have not changed since the contract was awarded. Under Sub-Clause 4.1, the contractor is “responsible for the adequacy of the design and for its development”. The only instruction came eight days later. It is a site instruction that reads “Rev D routing approved for construction, no change to the Contract Price”. Sub-Clause 13.1 is quoted beside it, word for word, with its page.

    Scope checker: “Reports what the documents say. Never decides entitlement.”

  5. 05Test 4

    Notice on day 46 of a 28-day limit

    Notice clock

    The contractor became aware of the event on the day of the rev D transmittal. Its notice letter is dated 46 days later. Sub-Clause 20.2.1 allows 28 days, so the limit had already passed. The notice ruler shows both dates. Below it, the run log lists each agent step with its time.

    “A late notice is a further ground. The contractor may ask for it to be excused. That decision is yours.”

  6. 06For the record

    The cost check, for the record, finds rates and markup above the contract

    Rate and markup checker · Field record matcher

    The cost column now opens, marked for the record. The tray is claimed at $182 against $131 in the schedule of rates (+39%). Supports are claimed at $64 against $41. Labor is $78 against $62 on the dayworks schedule. The scaffold is already in a preliminaries item, the contract's line for general site costs. The claimed 22% markup becomes the contract's 10% all-in under Appendix C. At contract rates, the claimed quantities are worth $402,380. The tray installation log shows a net change of only 140 m, against 1,860 m claimed. At those field quantities the work is worth $102,934. The subcontractor quote attached to the claim prices the tray at $118/m.

    Rate and markup checker: “Never values a claim before entitlement is answered.”

  7. 07Signed

    The administrator rejects at $0 and signs the response

    Contract administrator

    The response writer has drafted the letter to the contractor's commercial manager. It goes test by test and quotes §6.4.2 and Sub-Clauses 4.1, 13.1 and 20.2.1. The value at contract rates is attached for the record only. The letter states that this does not admit anything is owed. The contract administrator can edit anything and chooses what the signature means. Then they sign and send.

    “Drafted by the Response writer · every clause quoted · edit anything before you sign”

  8. 08Next

    A claim that is owed, priced at the contract rate

    Contract administrator

    A rock excavation claim in transformer bay T2 passes all four tests. A borehole had shown stiff clay to 4.5 m, so the rock counts as unforeseeable ground under Sub-Clause 4.12. Notice came on day 6. Now the valuation opens. Rock is priced at the contract's $112/m³ instead of $148, on 1,480 m³ from the as-dug survey. The recommendation is to negotiate at $210,012 of the $294,030 claimed.

    “Entitled, but priced above the contract. Offer the contract value.”

  9. 09The queue

    Eleven change orders, each with its verdict and its clock

    Project controls analyst

    The register shows the whole queue across four live contracts. In all, $2,530,280 is claimed. On the 9 claims already checked, $891,166 is recommended and $1,152,383 is held back. Another $486,731 waits for details or for the check. Filters pick out claims not owed, priced above the contract or notified after 28 days. One claim on another contract asks for extra site costs because the work ran longer. It is on day 38 of 42 and needs a request for details.

    “11 open across 4 live contracts · $2,530,280 claimed · checked overnight, decided by you”

  10. 10Each month

    All approved change orders checked again, instead of a sample

    Internal audit manager

    The audit re-check runs all 214 change orders approved in the last 12 months back through the same tests. It finds markups not applied as the contract says on 61. Extra charges sit on top of the markup on 38. Work already in the contract was paid again on 9, and quantities exceed the field records on 17. In all, $898,100 can be recovered from 121 of them. Separately, 14 late notices were paid with no recorded decision. Recovery letters are drafted for 4 contractors and wait unsent.

    “214 re-checked this year · 20 a manual sample would cover”

Who it’s for

Contract administrators, project controls and audit on each change order

The same claim, seen by the four roles who decide it, price it, co-sign it and audit it. First their month by hand, then with the agents.

Contract administrator
Decides and signs
Before
Acts for the Engineer on two projects, with 11 open change orders, each on a 42-day response clock. The contract documents sit in five places. A rate can be argued all week, but the first question is whether anything is owed at all.
Now
Opens each claim with the four entitlement tests answered and each clause quoted with its page. A drafted response is ready to edit, sign and send.
Project controls analyst
Prices change orders, checks quantities
Before
Prices change orders, keeps the cost report and chases quantities from site. Too often they re-price a claim, then find the work was in the bill all along.
Now
Sees each claimed rate beside the contract rate, and each markup worked out as the contract says. Each quantity shows the field record behind it.
Head of capital delivery
Co-signs any change order over $250K
Before
Answers to the CFO for the program, where one contract has change orders worth 15% of its value. Needs to know which of those were never owed.
Now
Sees change orders as a share of each contract against the usual 8 to 14%. Sees why money was held back, by the test that held it.
Internal audit manager
Runs the re-check
Before
Samples 20 approved change orders a year by hand. That says nothing about the other 194 of 214.
Now
Gets all 214 checked again with the same tests. Findings come by type, with dollars, and recovery letters are drafted for review.
The agents

Clause, scope, notice and rate agents behind each change order review

Entitlement is tested first, then each claim is priced at the contract's own rates. The contract administrator decides.

Claim reader

Reads each change order request, its covering letter and quotes. Lists the claimed lines, quantities, rates and markups, the event and notice dates, and the contractor's stated reason, quoted word for word.

  • Never edits a submission
  • Each number points to its page
Clause finder

Finds the contract clauses that apply, such as variation, notice, design responsibility, risk and provisional sums. It searches the Conditions of Contract, appendices and tender clarifications, and quotes each clause word for word with its page.

  • Never paraphrases a clause without the quote beside it
Scope checker

Compares the claimed work with the Employer's Requirements, the bill of quantities, the preliminaries and the drawing revisions, including who issued each one. Reports whether the work is already included.

  • Reports what the documents say. Never decides entitlement
Notice clock

Dates the event, the notice and the details. Measures them against the 28-day and 84-day limits and the 42-day response window.

  • Never rules a claim out for lateness. Flags it late for the contract administrator
Field record matcher

Matches claimed quantities to daily reports, installation logs, as-dug surveys, weighbridge tickets and photos, and reports the field quantity and the gap.

  • Never accepts a quantity with no field record behind it
Rate and markup checker

Prices the quantities at the contract's own rates and works out the markup as the contract says. Flags extra charges, such as supervision or insurance, that the markup already covers.

  • Never values a claim before entitlement is answered. If entitlement fails, it values for the record only
  • Flags a rate more than 5% above the contract rate
Response writer

Drafts the response to the contractor, citing each clause and record. The response can be a rejection, a counter-offer, an approval or a request for details.

  • Never sends. Only the contract administrator signs
Contract administrator

Decides and signs; co-sign over $250K.

Ask in plain words

Questions about a claim, a clause, a rate or a notice date

Ask about any change order, clause, rate or notice, or say what to draft. Each answer points to its clause or record. These answers use the sample data.

Why is the cable tray claim not a change?

Because the trays were always in the contract. Employer's Requirements §6.4.2 requires “all cable trays, ladders, supports and fixings… including the 11 kV switchroom and the cable basement”. The cable containment bill item prices that work at $1,118,400. Rev D was the contractor's own drawing. The site instruction said “no change to the Contract Price”. Notice came on day 46, against a 28-day limit.

Which claims came after the 28-day notice limit?

Two. One is an upgraded pipe bedding claim, with notice on day 63. Late notice is the only ground left on it, so it needs your view and a legal opinion. The other is the cable tray claim, on day 46, though it already fails on scope. All other notices in your queue arrived within 28 days.

Where are markups above the contract's 10%?

Four claims in your queue carry $100,390 above the contract's markup, at the claimed quantities. The cable trays are at 22% against 10% all-in ($62,952, for the record). Night traffic management adds an $18,400 supervision lump sum on top of 10%. Feeder bays are at 22% ($11,700). Fire suppression is at 22% ($7,338), and its check is still running.

Draft the request for details on the extended-preliminaries claim

Drafted. The request asks the contractor for the delay analysis on the accepted schedule. It also asks for the time-related costs behind the $41,200 a week for site staff. Last, it asks for the fully detailed claim under Sub-Clause 20.2.4. The letter goes out before day 42, and the draft is open for you to sign.

The screens

The entitlement gate, the notice ruler, rates and the audit re-check

From the working solution, on its sample data. Pick one to see it large.

The entitlement gateThe claim as sent, the four entitlement tests with their clauses quoted, and the cost check against contract rates.
The check, replayedThe tests answered one by one, while the valuation stays locked.
Design and instructionWho carries the design and whether a variation was instructed, each clause quoted with its page, beside the recommendation.
The notice rulerThe 28-day notice limit against the day the notice landed, and the run log of each agent step.
Sign and sendThe drafted response with each clause quoted, the meaning of the signature, and the sign and send step.
A claim that is owedFour tests passed, the valuation opened, and the claim priced at the contract rate and the surveyed quantity.
The change order registerEach open change order with its tests, entitlement, claimed and recommended values, notice days and response window.
Is it already in the contract?A search across the Employer's Requirements, bills, schedules, drawings and tender clarifications of a live contract.
Rates and markupsEach claimed rate beside the contract rate, each markup worked out again, and what each contract allows.
Notices and clocksEach event and notice against the 28-day limit, and the 42-day response windows up to today.
The capital programChange orders as a share of each contract against the usual 8 to 14%, and why money was held back.
The audit re-checkAll 214 approved change orders re-checked, findings by type with dollars, and the largest recoveries.
SettingsClocks, approvals, markup rules and rate tolerances per contract, and the agents and people.
Governance

Quoted clauses and signed decisions in construction change order review

Each verdict quotes its clauseEach entitlement test shows its clause word for word, with the document and page. It also shows the evidence behind it, such as the drawing transmittal, the site instruction and the letter dates. Each quantity shows its field record.
Whether it is owed comes before what it is worthThe valuation step stays locked until the four tests are answered. They ask whether it is a change, whose risk it is, whether it was instructed and whether notice came in time. When entitlement fails, the cost check is marked for the record only.
The contract administrator decides and signsAgents read and draft. Only the contract administrator rejects, negotiates, approves or asks for details. They sign electronically, and the meaning of the signature is recorded. The head of capital delivery co-signs above $250,000, and the capital committee above $1,000,000.
No agent rules a claim out for late noticeThe notice clock flags a late notice and shows the 28-day limit against the day it arrived. It does not rule the claim out. That decision, and its reason, stays with the contract administrator.
Each check on the recordEach agent step, edit, signature and letter is logged with its time. The check can be replayed step by step. Approved change orders are checked again with the same tests, so internal audit sees all of them.
Contract documents stay with the utilityThe contract, its schedules and the site records stay in the utility's own environment. Contractors see only the response sent to them. Recovery letters stay drafts until someone signs.
Configuration

Notice clocks, markup rules and co-signature limits per contract

The clocks, markup rules, tolerances and who signs what are all settings. Each comes from that contract’s own conditions.

SettingDefaultChoose from
Notice of claim28 daysFrom when the contractor became aware · Sub-Clause 20.2.1, set per contract from its Conditions of Contract
Fully detailed claim · response window84 days · 42 daysSub-Clause 20.2.4 and the Engineer’s response under Sub-Clause 3.7.3, set per contract
Warn the contract administrator atDay 35Set as a day of the 42-day response window
Markup on variations10% all-inPer contract. One contract uses 12% all-in. Supervision, insurance and bonding are inside the markup
Rate tolerance5%Per contract. A rate further above the contract rate is flagged
Co-signatureAbove $250,000Head of Capital Delivery co-signs; the capital committee above $1,000,000
Field record requiredAbove $10,000Any quantity worth more than this needs a field record behind it
Meaning of signatureI have reviewed the contract and decide as statedI have reviewed the contract and decide as stated · I decide as stated, subject to legal review
Connections

Contract conditions, bills, drawings and the field records behind a claim

Change order requeststhe contractor’s request, notice letters and pricing spreadsheets
Conditions of Contractvariation, notice, design and risk clauses, appendices and tender clarifications
Bills and schedules of ratesbill of quantities, schedule of rates, dayworks and preliminaries
Employer’s Requirements and drawingsscope sections and the drawing register, with who issued each revision
Field recordsdaily reports, installation logs, as-dug surveys, weighbridge tickets and photos
Subcontractor quotesthe quotes attached to a claim, read against the rate claimed
What it changes

Change order cost held back, and approved orders re-checked in full

Each figure carries its label: a target the solution is built to, an estimate, a typical published result, or a proven one.

estimated
$1.3Ma year
of change-order cost not paid on a large utility's capital program
Held back from change orders
4% of change-order spend held back
demo
214of 214
the sample year's approved change orders re-checked against the contract, instead of a sample of 20
Manual sample20 a year
With agentsall 214
target
2days
to an entitlement answer, inside the 42-day response window
Day 2 of 42
median target

“Demo” means seen in the working solution, on its sample capital program. “Target” is the design goal, measured in the live solution. “Estimated” is our estimate. It covers the working-days split and the results' $1.3M, which is a $420M program × 8% change orders × 4% held back, on sample inputs. “Typical” marks published figures. The City of Toronto Auditor General (2026) found markups not applied per contract on 48% of change orders in capital projects. The South Florida Water Management District Inspector General (2024) gives an industry norm of 8 to 14% of contract value. City of Fort Worth Internal Audit (2022) found 17 of 18 added pay items with no documented pricing review. The contract clocks come from FIDIC 2017 Sub-Clauses 20.2.1 (28 days), 20.2.4 (84 days) and 3.7.3 (42 days). Names on the screens are sample data.

Questions

Construction change order review questions from capital delivery

What is construction change order review software?

It is software that checks each contractor change order against the contract before it is paid. Construction Change Order Review first tests entitlement, meaning whether anything is owed. It asks if it is a change, who carries the design or the risk, if it was instructed and if notice came in time. Only then does it price the claim at the contract's own rates and markup. It matches the quantities to field records and drafts a response that cites the contract. The contract administrator decides and signs.

How does change order review work, step by step?

The claim reader lists the claimed lines, markups and dates. The clause finder, scope checker and notice clock answer the four entitlement tests, each with its clause quoted word for word. Then the field record matcher and the rate and markup checker price the claim at contract rates and field quantities. Last, the response writer drafts the letter.

Does it catch markups and extra charges above the contract?

Yes. It works out each markup the way the contract says and flags extra charges the markup already covers. In the sample queue, one claim asks for 15% overhead and profit, plus 5% supervision, plus 2% insurance and bonding. That is recalculated to the contract's 10% all-in. Across four claims, $100,390 sits above the contract's markup at the claimed quantities.

Can internal audit check every approved change order instead of a sample?

Yes. The audit re-check runs each approved change order back through the same tests: entitlement, contract rates, markup and field quantities. On the sample data it checked 214 approved change orders again. It found $898,100 that can be recovered from 121 of them. Recovery letters are drafted and not sent.

Does it decide that a claim came too late to be paid?

No. The notice clock measures the notice against the 28-day limit and flags it late. It does not rule the claim out. The contract administrator decides, and can sign with the meaning “I decide as stated, subject to legal review”.

Does it work with our contract forms?

The clocks, markup rules and rate tolerances are set per contract, from its own conditions. The sample program mixes design-build EPC, design-build and construct-only remeasured contracts. Three use a 10% all-in markup and the fourth uses 12%.

Who can reject, approve or negotiate a change order?

Only the contract administrator, with an electronic signature whose meaning is recorded. The head of capital delivery co-signs above $250,000. The agents read and draft, and none of them can decide.

What do you need from our contracts team to begin?

Your contracts, schedules of rates, change order procedure and a sample of past change orders. The Agentic Solution Engine builds and deploys the solution from those requirements and documents. It goes live once every quality gate has passed. We will walk you through it on your own change orders first.

Try construction change order review
on your own approved change orders.

We'll run Construction Change Order Review on a sample of your own approved change orders and the contracts behind them.