- Before
- Starts at 07:00 with yesterday's lab results and the analyzer trends. Finds out the far end was low only when a sample fails, and by then a notification to the regulator is due.
- Now
- Sees the dead-end point fall below 0.2 a day before it happens, with the reason, three options and the by-product effect of each. Approves the booster dose before 07:30.
A Tuesday morning's chlorine forecast, booster dose and signed notification
A utility supplies its network from two treatment works through four supply zones. It is a Tuesday in October, 07:10. Here is what happens next, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 0107:10
The day opens on the network, each point against its limits
Water quality managerThe water quality manager owns each exceedance on the network. The first screen is the map. It shows 26 sampling points with results in the last 24 hours and 38 analyzers reporting every 5 minutes. Each point's latest results are drawn as bars against its limits. Points near a limit pulse, and pipes are shaded by water age from 0 to 7 days. The watch list on the right already holds two items. One is a low chlorine forecast at a dead-end point. The other is a coliform bacteria result at a sampling kiosk.
“This month so far: 642 of 642 samples taken on time · 617 of 618 results inside every limit”
- 02+36 h
The forecast slid to tomorrow evening
Water quality managerThe time slider steps through Now, +12 h, +24 h, +36 h and +48 h, and redraws the chlorine bars from the forecast. At Wednesday 19:10 the bar at the dead end of one spur drops under its line. The analyzer there reads 0.24 mg/L now. The forecast is below the limit from Wednesday 07:00, with a low of 0.18 mg/L at 19:00.
On the map: “Forecast 0.18 mg/L · below the 0.2 limit”, and the next routine sample is Thu 08:30.
- 03The reason
Older water, and the decay rate on that spur
Residual forecasterThe reservoir feeding the spur has been held at 92 % since Friday for a pump overhaul. Demand is also down 11 % in the cooler weather. The 06:00 hydraulic run shows water age at the dead end rising from 6.0 days now to 7.2 days by Wednesday evening. On this spur chlorine decays at 0.225 per day. That rate is fitted from 41 grab samples and six weeks of the spur's analyzer (R² 0.91). Monday's grab sample already read 0.26 mg/L.
“The next routine sample here is Thu 08:30: without an action it would be the first anyone knew.”
- 04Each far end
Fourteen far-end points, ranked by their lowest forecast
Residual forecasterThe forecast covers each far-end point for the next 48 hours, with water age, decay per day and confidence. Only the dead-end point falls below 0.2. The next point up the spur (0.20) and the booster outlet (0.21) sit on the same spur. No other point needs action. The kiosk point's chlorine is normal at 0.46. Its problem is bacteria.
“Alerts need a confidence of R² 0.80 or more.” Below that, the forecaster asks for a sample instead.
- 055 steps · 6.6 s
A booster dose, a flush or doing nothing, side by side
Action plannerThe planner finds what can act on the spur: the booster on standby, a hydrant and the routine sample. It models each option. A booster dose of +0.25 mg/L from 08:00 reaches the end at about 01:00 Wednesday. The low is then 0.39 mg/L, and TTHM rises by 3 to 55 µg/L against a limit of 80. It wastes no water and uses about 9 kg of hypochlorite a day. Flushing the hydrant sends 140 m³ to waste and needs a crew for 3 hours. Even then, chlorine stays below 0.2 from 07:00 to about 09:00 on Wednesday, until the fresh water reaches the end. Doing nothing leaves it below 0.2 for about two days.
Do nothing: “The Thursday sample would likely read below 0.2 mg/L: a license breach, a notification to the regulator within 24 hours, repeat sampling and, if it persisted, advice to customers on the spur.”
- 06Approve
The manager approves the booster dose, with a note to the control room
Water quality managerThe manager approves +0.25 mg/L at the booster from 08:00 today, until the reservoir is back to its normal level. A setpoint request goes to the control room operator, who applies it, with the note attached. The approval is recorded on the audit trail with the forecast it answers.
“Booster to +0.25 mg/L from 08:00. Hold until the pump overhaul is closed and the reservoir is back below 80%. Call me if the outlet reads above 0.6.”
- 0707:31
The control room confirms, and the forecast re-runs
Control room operatorThe operator confirms the setpoint. Then the residual forecaster re-runs the forecast with the booster dose in it. At the dead end, the lowest residual is now 0.39 mg/L on Wednesday at 19:00. The next point up reads 0.44 and the booster outlet 0.45. To prove it, the sampling scheduler puts an extra grab sample on a sampler's route for Wednesday 10:00.
Approvals: water quality manager “Approved 07:21” · control room “Confirmed 07:31” · sampler “On the route”
- 08Tomorrow, redrawn
The dead-end point is back above its line
Water quality managerBack on the map at +36 h, the dead-end bar reads 0.39 mg/L. The watch list marks the spur as fixed: “booster dose running”. The strip at the bottom now reads “0 breach forecast”. No sample failed, so there is nothing to notify.
“Booster dose running from 08:00. Lowest forecast tomorrow now 0.39 mg/L (was 0.18).”
- 0905:52 → 05:55
A coliform result, caught a minute after the lab released it
Limit checker and Sampling schedulerEarlier that morning, the laboratory released a certificate for the kiosk sampling point. It showed 2 coliform bacteria per 100 mL, no E. coli and free chlorine of 0.46 mg/L. At 05:53 the limit checker opened the exceedance and started the 24-hour repeat clock. At 05:54 the sampling scheduler put three repeats first on a sampler's route, leaving 09:30. They are at the site, one point upstream and one downstream. At 05:55 the water quality manager was texted as on-call manager.
Suggested cause: the sample tap in the kiosk was last disinfected in August, so “disinfect the tap before the repeat”.
- 10Signed
The notification signed with 22 hours to spare
Compliance officerThe report writer drafted the notification at 06:30 from the exceedance record. It says what was found, where and when, and covers the certificate, the three repeats and the tap disinfection. The compliance officer reads it beside the minute-by-minute timeline. Then they sign and send it through the regulator portal, and the receipt is saved to the record.
“You are sending this exceedance notification to the regulator as the compliance officer.”