Invoice lines with a scaffold service code sat under the mechanical contractor, so the rate per job carried them.
Turnaround cost estimating, eight days after scope freeze
A refinery’s coming turnaround takes 14 units down for 38 days. Agents have read six final reports and 28,340 cost records. The control estimate now has to reach finance with each bar open to its source.
demoPlant, estimators and every dollar shown are sample data.
- 01Before the move
The bridge opens at $169.3M, and says why it should read $168.4M
Turnaround cost engineerThe walk starts at the last full-site turnaround’s final report, $92.6M as reported, and climbs bar by bar to the base and the range, with a dial under each assumption. Under the P50 sits one line: $168.4M once M-0147 is signed. One proposed move still changes the estimate, and the cost recutter names it before anyone touches a dial.
- 02Recut
Five ways of counting cost, recut into one breakdown of nine lines
Turnaround cost engineerSix final reports kept cost by contractor, discipline, unit, contract lot and work breakdown. The recut puts each line in one breakdown, and past totals stay as they were. Mechanical rate per job runs $20.3K to $26.9K as reported and $18.6K to $22.0K in one breakdown, tightening further only as proposed moves are signed. So far $36.7M is proposed in 186 moves, and $15.9M is settled.
- 03Scope bar
Scaffold left in the mechanical rate counts twice on 376 added jobs
Estimating leadThe scope bar prices added items in three parts. Mechanical jobs use the rate per job, and scaffold for them comes from its own take-off. With $4.2M of scaffold still inside the mechanical rate, the bar carries it twice: 376 × $1,817 = $0.68M. The lead can check that sum and its three sources before anyone decides the move.
- 04The move
1,128 invoice lines with one service code add up to $4,196,310
Turnaround cost engineerThe move opens beside its evidence: the mechanical contractor’s invoices, its contract and the final report page. Each scaffold bill carries the same service code, and the contract let the scaffold firm work under mechanical. Once signed, the rate per mechanical job falls from $16,696 to $14,879. Another 38 lines of access and rigging, $312,480, could be either, so they stay put, flagged.
- 05Countersign
The engineer agrees, the lead opens three sources, and the P50 settles
Estimating leadThe cost engineer agrees, giving the reason that the invoices support it. Someone else has to countersign, so the estimating lead opens the final report, the invoices and the contract first. Then the bridge redraws: base $151.6M, P50 $168.4M, P10 $151.2M and P90 $197.6M, with $20.1M of past cost now settled.
- 06Range
Three past events land above the P50, and the range shows each one
Turnaround cost engineerEach dot under the curve is a past event’s growth over base, applied to this base. Three of six land below the P50 and three above. P70 at $177.9M covers four of six, and P80 at $185.4M covers five. Funding at the P50 is a company choice a person sets. The curve comes from 5,000 draws, labelled as sample data.
- 07Rate question
A $0.2M question on the scaffold contract holds sign-off
Contracts specialistAn amendment sets the scaffold firm’s step at 5%, but the copy on file has one signature, not two. The rate checker shows what the paper says beside what the estimate uses, and leaves the reading alone. If it does not apply, the contractor bar falls $0.2M, which is over the $0.1M line that holds an estimate, so the contracts specialist rules first.
- 08Finance reads
Finance reads 11.1% contingency against 12.2% used in past events
Finance business partnerSigning stays locked until finance opens the price escalation and contingency bars. Contingency is $16.8M in four parts: emergent $4.6M, discovery $6.8M, known estimating uncertainty $3.4M and true contingency $2.0M. Past budgets held 7.8% to 9.1% and used 12.2% on average. At 13.8%, the average without the short record, this bar would be $20.9M, and that judgment stays open.
- 09Sign-off
Four holds ticked, and one judgment printed beside them
Finance business partnerThe sign-off card lists what had to be true first: the move that changes the P50 settled, the rate question ruled, and both bars opened by the checker. Beside them sits the open judgment on contingency, with the small moves that do not change the P50. Because the engineer prepared the estimate, only finance can countersign it.