Over the profile by 8.9% five years ago, 19.0% now, widening five years running, and the draft does not say why.
One gap in the fluid tailings report, traced and corrected before filing
Draft 4 of the annual report is due in 22 days. Pond 2's volume in the draft does not match its year-end survey, and the gap moves the site toward its first trigger.
demoThe mine, its ponds, the people and all volumes shown are sample data.
- 01Draft 4
206.1 million m³ in the draft, 7.5 below the first trigger
Tailings leadThe profile chart sets new fluid tailings by year against the approved profile and the three threshold bands. Beside it, the report as a stack of 38 thin tables: 29 tied, 6 untied, 3 waiting. The draft reads 15.8% over the approved 178.0. A strip under the chart says where to start: Pond 2 reads 5.7 lower than its survey.
- 02Draft 4
Table 6 carries 126.5 where the survey page says 132.2
Tailings leadPond 2's table has four untied numbers, all in the same column. Clicking the new fluid tailings cell traces it: 126.5 in the draft, 132.2 in the source, with a link to page 14 of the year-end survey. Total fluid tailings for the pond reads 404.9, and the density row is flagged as well.
- 03Draft 4
The water balance sheet still divides by last cycle's density
Tailings leadThe tie-out agent shows each step. The draft number came from the water balance sheet, loaded as a placeholder before the survey arrived 18 days late. That sheet divides 525.16 million t by 1.297, a density measured three years ago. With the newer 1.279 it lands on 410.6, the survey value. The gap is larger than the survey's own ±3.7.
- 04Draft 4
The engineer opens page 14 of the survey before he may correct
Tailings engineerThe correction belongs to the engineer who owns Pond 2, and the correct button stays locked until he has opened the survey himself. Page 14 gives 410.6 million m³, ±3.7, from sonar mudline and drop soundings checked by cone tests. Opening is recorded under his name.
- 05Draft 4
Proposed 404.9 to 410.6, and it waits for someone else
Tailings engineerHe picks his reason, late survey replaces a placeholder, and sends it. The panel says plainly that it waits for the tailings lead, since nobody checks their own correction. Correcting the table fixes the report. The cause sits in the sheet behind it, which belongs to the water balance specialist, who still has to move it to 1.279.
- 06Draft 4
Tables 1, 2 and 4 follow once the lead opens the same page
Tailings leadThe tailings lead opens page 14 herself, then checks. Only then does Table 6 read 410.6. The site inventory, the new tailings table and the thresholds table depend on it, so they tie with it. The correction, its reason and both names sit in one green box, and the line can now move.
- 07Draft 4
Now 211.8: 1.8 below the trigger, and 215.7 at the top of the range
Tailings leadThe line moves to 19.0% over the approved profile. The reported value sits under the first trigger, but the top of the survey's ±3.9 range sits over it, so the report has to say so. Early warning turns on. Thirty-three tables tie now. Any decision on a threshold is the regulator's.
- 08Before signing
Another filing says a well changed, and this draft says all 12 were sampled
Tailings leadBecause the report goes public as filed, an agent reads the draft the way a tough reader would: against last year, the plan and other filings. Eight findings wait for the lead. One sets the draft's claim that every monitoring well was sampled each quarter beside a groundwater filing where one well ran dry and was replaced.
- 09Before signing
Six gates open, and the signature stays shut until each one closes
Tailings leadAll tables tied, the water balance sheet updated, each outsider finding decided, uncertainty statements checked, the restated number decided, and a sample of tied tables opened and agreed. Until then nothing can be signed. After the lead signs, the reporting coordinator reads the signed report and files it as the second person.