Restart readiness review on a two-train gas plant, 214 days after a fire
A failed instrument tube on a compressor started a fire that took out the inlet header and fire water ring. Train 2 has been without feed since. Gas-in is set for next week, and the leaders must decide which train comes back first.
demoThe plant, the fire, the people, the tags and the counts are sample data. Nothing on this plant is real.
- 01Morning
Eleven units in the order they must come back, four of them lit
Restart review leadThe plant is drawn as a network of utilities, flare, inlet separation, acid gas, compression and both trains, with lines showing what must be signed first. A unit lights only when its proof is signed, and nothing can light before what it depends on. Utilities, flare and relief, inlet separation and acid gas handling are lit. Train 1’s amine, cold section and inlet compression are stopped.
- 02Morning
231 of 41,286 calendar entries lapsed while the plant sat idle
Clock walkerEight calendars, five years of history, walked across all 214 days: relief valve tests, calibrations, shutdown systems, fire and gas devices, inspections, preservation checks, temporary repairs and operator qualifications. Most came due and were done on time. 231 lapsed: 63 redone, 168 still open, all on Train 1. Each lapsed row names the unit it blocks.
- 03Morning
No nitrogen log for 19 days, and pressure under the plan for six of them
Preservation readerThe plan said to hold the regenerator at 3 psig of nitrogen and log it daily. When the Train 1 day crew moved to the rebuild, the rounds passed to a night shift with nobody named, and the log went blank. Pressure history shows the blanket under the minimum for six days. The agent says plainly it cannot tell whether air got in; process safety sets the checks.
- 04Morning
A clamp allowed for 90 days on a 1,050 psig line, with no engineering review
Integrity engineerA bolted clamp went on over a pinhole weep on a compressor discharge line after the fire, allowed for the nitrogen leak test only. Its limit passed long ago. The engineering review is blank, there is no thickness reading under it and no clamp data sheet, and the line sits in heat zone IV of the fire. The integrity engineer decides first; process safety countersigns.
- 0509:17 and 09:20
Hold one train, release the other first: proposed, never signed by the lead
Restart review leadThe suggestion sits on top: of Train 2’s 652 remaining items nothing open was found, and no person has checked them yet. The lead proposes the hold on Train 1 and the release of Train 2, and has the failed calendar feed read again before the release can be signed. She can propose; she can never sign.
- 0609:35
Concurred after opening the blinds, the live-train work and the flare load
Process safety engineerBefore her concurrence counts, she opens her three checks herself: Train 1 isolated by six blinds, work beside a live train, and the flare carrying one train. Each opens to its record. She concurs, or refuses with a reason. The release now waits on the plant manager’s sample and signature.
- 0710:10
Twelve of 652 items opened by the plant manager before the bulk signature
Plant managerThe sample is drawn one or more from each Train 2 unit, high risk first: the same tubing that failed, now replaced and braced, relief valve bench tests, a shutdown valve stroke, a gas detector, a dryer, compressor oil, an operator’s refresher. Each must be opened by the person signing, and he marks each one as matching the record or not.
- 0810:14 and 10:17
Train 1 held in his own words; Train 2 signed, words not yet read
Plant managerHe picks the reasons and writes why. Hold: the clamp is past its 90-day limit with no engineering review, and the regenerator log has a 19-day gap. Release: Train 1 is blinded in six places, Train 2’s tubing is replaced and braced, and the twelve sampled records match. Typed words are not compared by the product; a second person must read them before the release takes effect.
- 0910:23
Released, not started: four hold points stand before gas-in
Process safety engineerShe reads his words, with the record beside them, and lets the release take effect. Release is not gas. Blinds out and reconciled, the leak test, air freed and the final walk all read not done, each with its owner, and each has to be confirmed by a person in the plant. Train 1 stays held until its open items close.
- 10After the release
Train 2 lights in order, and the gas-in still waits
Restart order keeperOn the graph, Train 2’s residue compression, amine and cold section are lit by the plant manager’s signature, in the order they depend on each other. Its inlet compression still has items to sign, Train 1 stays amber, and gas-in shows its date with no start. The agent lights nothing itself; it shows what the signature allowed.