Petroleum license compliance on one well job that started 11 days short
An abandonment engineer plans to plug an idle platform well in 19 days. The rig slot is booked. The contract he remembers asks for notice; the contract as amended asks for something else.
demoThe operator, the licenses, the Ministry letters, the wells and the people are sample data, and so are the clause texts and day counts.
- 01Before the question
Twelve licenses on one line, from award to expiry
License administratorEach operated license is drawn as a life line through its phases, with relinquishments, work, guarantees and restoration marked, and today’s line through all of them. Above it sits one box: may we do this? The footer counts the calendar: 9 late, 148 due in 90 days, 45 with counsel, 1,430 duties in all. Five new Ministry letters wait to be read.
- 02The question
Not on this plan: written approval first, and the plan fails by 11 days
Abandonment engineerHe types the job in plain words. The answer reads the clause as needing written approval from the Ministry, 30 calendar days ahead of work. His plan leaves 19. The latest filing for his date passed 11 days ago, and silence does not count as approval. The panel works the rig slot too: when the reply is needed, and what holding the rig would cost.
- 03The clause
Amendment 3 deleted the notice clause and replaced it with approval
Abandonment engineerWhat the agent read is listed in date order: the contract as signed, the amendment, and two Ministry letters, one setting four required items and one saying the thirty days run only from a complete application. Opening the amendment shows the passage itself. Notice became written approval, and the Ministry’s silence shall not be treated as approval.
- 04The draft
The planned start moves to the earliest date the clause allows, plus margin
License administratorHe opens the drafted application, moves the planned start and gives the reason: contract lead time. The draft cites the article as replaced by the amendment, the four items the old letter requires, the rig and the estimated cost, and asks for a reply before the rig slot closes. He signs it as maker. He cannot also check it.
- 05The check
Counsel opens the amendment and both Ministry letters before she can sign
Upstream counselHer sign button stays off until she has opened each source herself, and the panel counts them. Here the later letter is open: the thirty days run from the date the Ministry receives a complete application, and an incomplete one does not start the clock. She can sign and file, or send it back to the administrator with a reason.
- 06The filing
Filed 33 days before the planned work, and the work stays blocked
Upstream counselThe application now reads as filed, signed by the administrator and checked by counsel. The panel says what it means: work stays blocked until written approval is on file, because silence is not approval in this block. A reminder to the Ministry is set fifteen days before the reply the rig slot needs. No agent filed or signed anything.
- 07Until the Ministry replies
Releasing the job to the rig stays locked until approval is on file
Abandonment engineerThe engineer’s own view of the application shows where it stops him. Releasing the job to the rig is disabled, with the reason: no written approval on file, so the rig cannot take this job. It also tells him his well plan still carries the old date, and offers to revise his plan to the new start.