- Before
- Starts with the clocks, checking which patches are near day 35 and which installs missed their outage. Thirty-five days sounds like a lot until a vendor hides the notice in a portal PDF.
- Now
- Opens a dial where the red sector shows the work. Finds the evaluation and any plan already drafted, with the notice sentence behind each decision, and signs.
An RTU security notice at day 31, evaluated and planned the same morning
A large utility runs Cyber Assets at substations, a power station, control centers and a water works. Three weeks ago, the RTU supplier posted a security notice on its customer portal. The utility last evaluated that source ten days before that. Here is day 31 of the cycle, screen by screen, in the working solution.
A worked example on sample data. Names, IDs and figures on the screens and in this section come from the demo.
- 01Morning
The queue is a 35-day dial with a bead for each patch
OT security engineerThe engineer owns the patch evaluations for the substations and the power station. The home screen is a 35-day dial with a bead for each of the 47 open patches. The inner ring counts the days to evaluate. The outer ring counts the days to install or plan. Days 25 to 30 are amber and days 31 to 35 are red. The severity bands past day 35 are printed under the dial. Below it, a tile for each of the 23 sources shows where its cycle stands.
“47 patches open · 19 to evaluate · 28 to install or plan · 12 plans running · 0 late this year”
- 0206:00 sweep
The RTU notice reaches day 31 and turns red
Clock keeperThe Source watcher found the notice the day it was posted. The Inventory matcher matched 14 RTUs of the affected model. At day 25 the Clock keeper reminded the engineer and the compliance analyst, but there was still no evaluation. At this morning's sweep the hand moves from day 30 to 31. The bead for RTU firmware 4.2.9 turns red. The patch fixes an authentication bypass, a flaw that lets someone skip the login, in the RTU's web configuration screen. It is rated 8.8 on the CVSS severity scale. Four days are left to evaluate.
“06:00 · the RTU notice reached day 31 with no evaluation: escalated to the OT security engineer and the compliance analyst”
- 03One click
One click on Evaluate now, and the agents draft the whole evaluation
Source watcher · Inventory matcher · Applicability assessorThe engineer clicks Evaluate now. The Source watcher reads the 4-page notice signed by the supplier's PSIRT, its product security team. The Inventory matcher lists 14 RTUs of that model across several sites. The Applicability assessor finds 11 affected and 3 not applicable, at 0.96 confidence. The Outage fitter places 7 installs before the action deadline, in outages at three substations. It flags that a fourth substation's next window is 7 days too late.
“Outage fitter · one substation misses the deadline: next window is the T2 maintenance, 7 days late”
- 04The notice
Each decision rests on a sentence of the supplier's notice
Applicability assessorThe patch file shows the supplier's notice. The sentences that decide applicability are marked and numbered, with margin notes beside them. Firmware 4.2.7 and 4.2.8 fall inside the affected range. Two RTUs at another substation and one at the power station run 4.3.0, installed earlier. The note on the fix adds the utility's own operating rule. Losing the RTU's readings at a high-voltage substation needs a planned outage.
Affected: “Remote Terminal Unit, all hardware revisions, firmware 4.0.0 through 4.2.8.” Not affected: “The issue is resolved in firmware 4.3.0 and later.”
- 05Per asset
Fourteen RTUs, fourteen decisions, each with its reason
OT security engineerThe decision table lists each RTU by tag, bay and firmware. Each row shows applicable or not applicable, the reason with its citation, the action and the date. The four RTUs that miss their window go into a mitigation plan, with the install in the T2 maintenance. The other seven are installed at three substations. They go in a bay outage, in feeder maintenance and in planned maintenance. The engineer can change any decision before signing.
“14 RTUs · 11 applicable · 3 not applicable · drafted · you sign”
- 06The outage plan
Each install placed in the next outage that beats its deadline
Outage fitterOutage fit lays the next 60 days of planned outages at each site against each patch's deadline. Of 15 install groups, 13 fit and are booked into outages before their deadlines. Two miss. The four late RTUs need Bays 1, 2, 5 and 6 out, and the next outage that does that is the T2 transformer maintenance. At the power station, a plant DCS patch misses too, because the Unit 2 outage moved two weeks later.
“Install or plan by the action deadline; the next window covering Bays 1, 2, 5 and 6 is the T2 maintenance, 7 days after it.”
- 0706:03
The plan template opens already filled in
Mitigation plan drafterThe plan is drafted from the RTU template, with controls taken from the supplier's own workarounds. First, turn off the RTU web configuration screen from the substation's engineering workstation within two days. That needs no outage and can be undone, and the substation technician owns it. Second, block TCP 443 to the four RTUs at the substation firewall, owned by the OT security engineer. Third, alert on any connection attempt, owned by security operations. Last, install 4.2.9 in the T2 maintenance.
“46 days · inside the 60-day limit, so no delegate approval needed”
- 0809:41 · day 0
Signed on day 0 of the action clock
OT security engineerThe engineer signs the evaluation and the plan together. The red bead leaves the inner ring and starts again on the outer ring at day 0, with 35 days left to install or plan. The Clock keeper logs the evaluation date and starts the action clock. Each affected RTU is now booked into an outage or covered by a dated plan.
“Signed on day 0 of the action clock · all 35 days to spare · plan complete in 46 days”
- 0910:05
The plan on record, with its evidence list and approvals
CIP compliance analystThe full plan shows the security patch and why it cannot be installed in time. It lists the four assets, the timeframe and the four actions with owners and dates. The evidence to collect is a configuration export showing the HTTPS server off, the firewall rule export and the monitoring rule ID. It also includes an install record with the firmware version for each RTU. The compliance analyst reviews it at 10:05. The CIP Senior Manager's delegate is needed only for a revision or an extension.
“The Clock keeper asks for each on its date.”
- 10The same morning
Six GPS clocks with no patch source, found before the audit
Inventory matcherThe sweep also compares the inventory's 41 models with the source list. Six GPS clocks at one substation were added by a time-sync upgrade work order. They run updateable firmware 1.4.2 but have no tracked source. The engineer adds the clock maker as a source. Its clock starts, with the first evaluation due on the same action deadline.
“They are updateable (firmware 1.4.2), so CIP-007-6 R2.1 needs a source. Without one, no evaluation clock starts.”