A 10% cap, an annex that sits on top of it, and $21.6M of contingency
A lump-sum compression platform bid: 1,380 pages in 14 documents, a 60-day window and a price freeze 16 days out. Here the biggest step in the contingency gets its reading, its number and its signature.
demoBidder, owner, suppliers, people and amounts on these screens are all sample data.
- 0108:30
The bid of record is $1,120.0M, and 24 risks still wait for people
Bid risk managerThe bridge stacks the price as it stands: cost estimate $976.0M, contingency $61.0M, margin $83.0M, signed lines only. Under it the contingency climbs clause by clause, 17 steps signed. The tallest unsigned step is R-07, Clause 42 with Annex D, at $21.6M proposed. Below, all 286 clauses in 1,380 pages, split by where each one landed.
- 02Before the desk
11 places where an annex changes a clause in the conditions
Contract reader and clause finderLaid out step by step, the read starts with the contract reader, which took 14 documents and 1,380 pages read only, keeping document, page and clause for each passage. The clause finder sorted 286 clauses by the contractor's playbook. The cross-reference step found 11 places where an annex changes a clause; Annex D 4.6 is one, and counsel reads what it means.
- 0308:40
156 clauses are proposed as accepted, and still need counsel's sampled read
Contracts counselEach of the 14 documents shows its pages and how many clauses carry commercial effect: 118 in the conditions, 34 in the scope, 16 in the guarantees annex. The playbook proposes 156 as accepted as written, but none of them is accepted on an agent's word. Counsel reads a sample and signs, and the sign-off gate stays open until she does.
- 0409:00
A 10% cap in Clause 42.1, and Annex D 4.6 puts its damages outside it
Bid risk managerBoth passages open side by side with their pages: the conditions cap total liability at ten percent of the contract price, $112.0M at this bid. The annex says its liquidated damages are in addition to that limit. Read with them are the exceptions in 42.3 and the capacity damages of up to $68.0M. A liquidated damages cap means little until both are read together.
- 0509:04
Priced over the gas forecast at 31.8%, inside the desk's possible band
Bid risk managerThe exposure is the contract's own number, $68.0M. The likelihood comes from integrating the damages over the owner's test-year gas forecast, which gives $21.6M, an effective 31.8%, inside the desk's 25 to 35% band. She places it with that basis showing. Nothing changes in the bid yet: the reading waits for counsel and the signature for the director.
- 0609:06
Counsel opens both passages before she confirms what they mean
Contracts counselCounsel owns the meaning. Her button stays shut until she has opened Clause 42.1 and Annex D 4.6 herself, so a confirmation is a reading, not a click. She confirms that the annex damages sit outside the cap. The step now reads ready to sign, and her name sits on the first of the three lanes.
- 0709:08
The director's signature lifts the bid of record to $1,141.6M
Bid directorThe bid director checks the sum before he can sign. Once he does, contingency steps from $61.0M to $82.6M, the bid of record becomes $1,141.6M, and the Clause 42 limit moves with the price to $114.2M. The bridge shows 18 of 41 signed. Each signed risk on it carries three names, and agents hold none of them.
- 0809:09
The compressor supplier caps all liability at $9.3M, against $128.8M accepted
Bid risk managerThe flow-down puts eight unsigned quotes in five packages against the head contract. For the compressor package the contractor accepts performance and fuel damages outside the limit and delay damages up to $56.0M, $128.8M in all, while the quote caps everything at 5%, or $9.3M, once for all claims. That leaves $119.5M with the contractor. The quote is unsigned, so no recovery is credited.
- 0909:10
The price build file matches the bridge at $1,141.6M
Cost estimatorThe estimate is built line by line, and contingency lines load only once signed. With the signature in, R-07 waits for the estimator, who loads it into the price build file. The file and the bridge agree at $1,141.6M, checked by the ledger after the change. What goes to the estimating system is what the three people signed.