Turnaround Schedule Health Check demo
Schedulers see the turnaround schedule tested against job packs, blind lists, material dates and the crane plan, with each collision pinned. 1:24
What the demo shows
Checks a turnaround schedule’s logic against scope, packs and permits, for schedulers.
Agents read the schedule file and cross-check it against job packs, the blind list, purchase orders, kept scope, the crane plan and permit rules. Each disagreement lands as a pin with cited sources and a proposed fix. The scheduler decides, the execution lead countersigns, and the tool never edits the schedule.
Transcript
- Turnaround Schedule Health Check tests a schedule against the real world for schedulers.
- This schedule passes its network checks.
- A 5% limit lets 932 activities go untied.
- The math cannot see job packs or blind lists.
- The agents can. 411 pins land, 9 on the critical path.
- On day 11, the E-2417A bundle pull starts before blind B.
- 24-0187 is in.
- Mkechi, the scheduler, ties the job to the blind walk.
- 31 crane hours move off the peak.
- Float falls from 52 hours to 22.
- She decides. The tool never edits the schedule.
- Hamish, the execution lead, opens every source and countersigns.
- 411 collisions the math could not see.
- Two people on every fix.
- Built on Botminds: agents, data, screens, and governance on one platform.
Transcribed from the film’s narration. Captions are on the player.